SCD project status meeting minutes 20 Jun 2000 In attendance : ENA (chair), WSH, TJ, RPT, NEJ, IMC Aim was to confirm status of 'Open Actions' (SCD project Notes 1.1). Preliminaries ------------- Deadlines described by ENA as 01 Sept for "first run through" although this includes one month for ORCADR adjustments. RPT is unavailable until the *end* of August, but can complete the uploading of the CSO data from their ftp archive. Action : RPT to upload CSO tau data ( Section labels refer to those in Open Actions 1.1. Items not explicitly mentioned have no change to their status). 1.1.1 : TJ : update ready for release 1.1.2 : TJ : hard to do, and automatic reduction of nights with mixed filters (fortunately there are few of these) will be impossible. 1.1.4 : Upload is now automatic, RPT : Once per semester perhaps someone (RPT?) must upload the complete CSO record from their ftp archive. 1.1.5 : Fits to be scrutinized by NEJ. 1.1.9 : ENA : may not be available by 01 Sep. 1.2 : TJ : making filter names in data headers correct in the database was trivial, changing them on disk was possible, but that the changes within SCUVAX needed effort from FJO. 1.4 : : Interpolation is not possible if end-of-shift focusses are not done (which is usually the case)