Director JCMT Note 991026
JCMT Note from the Director
26 October 1999
The upcoming JCMT Advisory panel and Board will address a
number of issues. I invite users to give their input as part of the
decision making process. The first part of this note is to alert you
to these. The second part is to inform you of some operational
decisions that have been, or will soon be forced on us.
Overall you should note a number of projects are coming to
fruition. The Observatory and Telescope Control projects are
almost complete and the major observatory project at the current
time, the surface upgrade, is coming to a conclusion with the
imminent arrival of the new fast holography system and the panel
adjuster electronics system. Testing and commissioning of the 21
micron active surface will commence in the spring. The next major
development project, the linking of the JCMT with the SMA is
also ramping up and work will begin in earnest before Christmas.
Remo Tilanus will be the JCMT project Scientist for this project.
This offers a hugely and exciting prospect for subarcsecond
astronomy to users.
(a) Issues for the Advisory Panel and Board
1. New instruments
As you will undoubtedly know, there are three potential new
instruments vying for support and funding. These are HARP-B,
HARP-D and SCUBA-2. Below lists a top-level briefing on each:
HARP-B
This is a 16-element 350 GHz SIS focal plane spectroscopic
camera to be housed on the right-hand Nasmyth platform and fed
through the encoder bearing by a K-mirror optical train. It is
already well along on the approval route, having had a very
successful CoDR in March and a K-mirror PDR in September.
However, due to problems with UK staffing levels, HARP-B
still needs formal Board approval now that the project has been
reorganised to reduce the requirement on UK staff effort. MRAO
are the project leaders along with the UKATC and HIA Victoria.
The science case is now on the web
at MRAO with a
link from the JCMT homepage.
HARP-D
This is currently being worked up into a proposal by the
Netherlands. It will be a clone of the MPIfR CHAMP array
currently on the CSO, but operating at D-band. It will be built
jointly by SRON and the MPI für Radioastronomie (group of Karl
Menten) and will be on loan to the JCMT for at least 2.5 years,
with a possibility of another year before moving to the ALMA site.
It will have 16 elements, with minimum spacing on the sky. It can
provide 2 GHz of bandwidth for each detector. To obtain optimum
system sensitivity the design includes cold optics (15K) and an
optically tuned single-sideband separation. The intention is not to
use a beam de-rotator as the observing strategy will allow
sufficiently short observations so that the rotation corrections can
be done in software. The timescale is about 3.5 years.
The science case is now on the web
at Leiden with
a
link from the JCMT homepage.
SCUBA-2
SCUBA-2 is proposed as a wide-field (8x8 arcmin minimum)
twin-wavelength (850/450 micron) camera operating with new
technology detectors, He-3 cooling and no moving parts. It is
designed to mount at the left-hand Nasmyth, be simple to operate,
reliable, background limited and devastatingly powerful as a
mapping facility. The new technology detectors are more akin to
CCD-type of detectors, being directly illuminated in the focal
plane with 0.5 F lambda pixel spacing rather than the 2 F lambda
?horn-feeds previously typical of these wavelengths. The timescale
for SCUBA-2 is 4 to 4.5 years.
The science case is now on the web
here
with a
link from the JCMT homepage.
Unfortunately, there is inadequate funding remaining in the
Development Fund to support all three instruments. Clearly, we
wish to have all three and so I anticipate there will be pressure to
extract additional funds from the agencies to support this exciting
programme. To ensure the success of this it is important that you
lobby your representatives on the Advisory Panel and express your
priorities. While we will continue to fight for all three instruments,
the Board will undoubtedly wish to have a prioritised list of the
instruments. This has already been provided by the Panel last
November (and reinforced in May). This was SCUBA-2 (ensure
enough funds remain to build it), HARP-B (go ahead and build it
now), HARP-D (go ahead with low-level R&D prior to
construction). The situation is now clearer in that SCUBA-2 is
better defined (and much more expensive than anticipated) and
there is a clearer way to achieve a D-band array.
If, after reviewing the scientific cases, you disagree with this
priority order, let your views be known. I will assume silence
equals agreement. The Advisory Panel meeting is on November
8/9.
2. Guaranteed time for instrument builders.
The Board has agreed the principle of guaranteed time to
instrument builders and I was charged to come up with an
implementation plan. I polled the builders for their views and from
the responses I have made a proposal (below). This will be
commented on by the Advisory Panel, and ITAC. Please make
your views known to your panel representatives if you have strong
agreements or disagreements with this. Note, the Board have
approved the principle, this is an implementation debate.
(i) Time should be linked to the complexity of the project with the
following being a first suggestion: small 5, medium 10, large 15
shifts. A backend (for example) should count as an instrument.
Other instruments, such as RxH3, should be treated on a case by
case basis.
(ii) There should not be a penalty clause
(iii) The science programme should be open to the Co-I^Òs involved
in the instrument, the case should be adjudicated by the ITAC and
should come from a subset of the original science case for the
instrument (where appropriate).
3. Big observing programmes
The user community has already been polled on this. There were
23 replies: 13 from the UK, 5 from Canada, 3 from the Netherlands
and 2 from the USA. I am most grateful for those respondents for
taking the time to reply. The replies were carefully thought out;
respondents had clearly given the issues serious thought and provided
some helpful and interesting suggestions that will be incorporated into
a paper for the Board.
(b) Operational issues
SCUBA
The SCUBA upgrades went very well and the microphonics have
been greatly reduced by the new ribbon cables. Also, preliminary
results show that the new blocking filters have given
improvements to the flux conversion factors at 850 and 450, and
that the wider band 450 filter shows a large improvement over the
standard 450 filter. NEFD data have been harder to come by but
preliminary estimates are that there are gains at both wavelengths,
more at 450 than 850, which was expected.
That was the good news. The bad news is that although SCUBA
looked excellent after cool-down, best ever in fact, four days later
it developed a noise problem on the array. Two mini-warm-ups
have failed to cure the problem. This also happened in July and the
cure then was a full warm-up with baking and extended pumping.
Although the symptoms are not identical, we are now embarking
on an extended warm-up. Watch this space.
TSS shortage
The second operational matter is that a second Telescope System
Specialist is resigning as from December. This will mean that from
then until we recruit and train-up replacements, we will be unable
to support sixteen hour observing nights on the JCMT and will
have to resort to something like twelve hour nights for two-thirds
of the time. It is anticipated that these hours will run from
something like 8pm to 8am.
Clearly this will be disruptive to a number of programmes already
allocated time this semester. I will be liasing closely with the TAG
Chairs to try and ensure that these are treated fairly and that
implications for semester 00A are understood at the ITAC meeting.
Professor Ian Robson
Director, Joint Astronomy Centre
Director, James Clerk Maxwell Telescope
|