|
UK observing guidelines
UK observing guidelines
The UK TAG allocates its share of JCMT observing time
on a project-by-project basis, with observers from some
identified projects required to be in attendance.
As a result of this semi-classical starting point, the rules for
observing during UK time in the schedule are slightly different from
those applying during Dutch
and Canadian time and need a little additional explanation to the
general rules described elsewhere.
General principles
The scheduled (UK) project has priority when the weather is suitable,
but other, appropriate projects are observed whenever the weather
is unsuitable for the scheduled project, the choice being determined
again by weather and TAG priority.
To achieve a more realistic match to the weather statistics, the
UK TAG usually assigns additional 'flex' time to the formal allocations
for highly ranked proposals needing weather grades 1 or 2.
These proposals then appear within somewhat expanded time
slots in the schedule. During these blocks, proposers who have been
allocated time will be permitted to spend on their project all of the
time during which the weather coincides with their assigned weather
band, up to a maximum time equal to their actual formal allocation.
In return for this increased chance of completing/advancing their
programmes, scheduled observers will also be expected NOT to
pursue their programme when the weather is either
better or worse than their assigned band (or if by good luck they get their
full allocation of appropriate weather before the block is finished) and
instead to implement an appropriate proposal from the appropriate-weather
backup/flex queue as directed by the JCMT scheduler (basically the highest
ranked proposal on the appropriate queue for which targets within the
appropriate RA range are available).
Example of how this is meant to work in practice
Suppose you have been
awarded 2 shifts of grade 1-2 weather. Where possible this will be scheduled
within a 4 shift block, and if the first 2 nights were dryer than grade 3
weather you would be able to pursue your programme. However, if the weather
deteriorated to grade 3 weather on night 3 you would,
according to the
rules of flexible observing,
be expected to implement
the highest rated appropriate proposal from the Grade-3 weather queue.
If on night 4 the weather deteriorated further to Grade-4 conditions, you
would be expected to implement the highest rated appropriate proposal from
the Grade-4 queue, etc.
Note for UK applicants allocated 'Scheduled' time
Where your project has been awarded a formal allocation that requires an
observer, it is your
responsibility, as PI, to make sure that someone - yourself or one of
your collaborators - will be here to cover
the allocated shift(s) plus associated flex time.
The JAC does not, alas,
have sufficient staff to provide service observing except on an
emergency basis, but we will be happy to help you find someone.
Note that even if, in the flexible observing scheme, your project
should be completed before you arrive for your scheduled run, you
will still need to provide an observer for those shifts.
You are expected to travel to the telescope and staff
the whole of your expanded run. In return for this flexible block the ITAC
expects disciplined observing, in terms of moving to the backup queues if
appropriate. The ITAC, and national TAGs, will not look kindly on
observers who continue to pursue their own programmes in inappropriate
conditions.
Note for UK applicants allocated time with "No Observer Needed"
You are encouraged to
complete MSBs for your project as soon as possible (before
the end of the first month of each semester), to enable
your proposal to be implemented
whenever a suitable situation should occur. The ITAC's intention is that,
in this way, as many programmes as possible should be completed or at least
significantly advanced during the semester.
|