Derivation of Statistical Information
This note provides some explanation on the method of production of the
weather and fault statistical summary for the performance of the JCMT.
There is very little manual intervention in the generation of these tables,
other than to correct obvious errors, mis-labelled categories, or to complete
missing entries (where they ca n be found from other sources).
o The data are extracted from the reports completed by the telescope
operators at the end of their shift, one report for each shift (evening
or morning); the shifts are normally of 8 hours duration. Because the change-over
of TOs does not occur on the shift boundaries, the shift information is
handed over to the followi ng operator who will file the report at the
end of shift.
o A completely separate fault reporting system is used by the TOs and
other staff to record time lost to faults (including problems which have
zero-time lost). This system is used by the staff to identify, trouble-shoot
and solve the faults. Each fault s hould then have an appropriate solve
report attached for future reference. This system is not used for generating
statistics.
o Input from the TO reports comprises
- - the actual time scheduled (normally 8 hours);
- - any extension of this (normally due to good weather and lack of pressing
daywork);
- - loss of time on primary and backup programs due to the weather.;
(NB : in flexible observing mode, the move from a high-frequency
primary program to a low-frequency primary program because of a deterioration
of the weather conditions does not result in any entry in the 'loss to
the primary program' category.
- - loss of time to primary and backup programs due to faults, divided
into 6 categories : ANTenna, CARousel, INStruments, COMputer, SOFtware,
and OTHer. These categorizations are performed by the TO at the time of
filing and persist in the analysis, although suggested changes in categories
are suggested by the notes to the analysis.
(NB : faults are defined as being in respect of subsystems that
have been commissioned are therefore expected to work flawlessly. If the
instrument under commissioning has a fault, this is not recorded in the
log.
(NB : previous correlations between faults as reported in these
TO reports and via the separate fault reporting system show high levels
of completeness. A similar correlation is also found between the TO reports
and any completed Observer Reports for the period.
- - automated retrieval of weather conditions for the shift in question.
These are not analysed further and are not further correlated with the
reported conditions.
o Electronic submission of each report automatically triggers the summary
analysis program (AUTO_STATS) for the month and semester to date, and the
statistics reported to the JCMT Board and in the Annual Report are essentially
these results.
o The analysis performed by AUTO_STATS may be repeated following identification
and correction of spurious entries, or significant errors in categorization.
o Occasionally reports are not filed on time, and missing reports can
seldom be reconstructed.