From the Director's Desk
From the Director's Desk
Two critical issues have occurred since the last Newsletter:
agreement of the future operational plan for the JCMT and the
very sad death of Sidney Arakaki. The latter matter is reported
in a separate note and it is grim
reminder that this is
the second death in service at the JAC within the past
year.
As has been widely reported, PPARC, in its bid to become a member
of ESO, required savings to be made in its ground-based
astronomy programme of order £5M p.a. from ~2005. The JCMT was
impacted by this remit and during the late summer a significant
amount of management staff effort was focused in preparing a
response to the requirement to come forward with a viable
operating model that also delivered the target savings
required. Because UKIRT was also involved, this was a JAC
site-wide issue.
The report produced by the senior management with input from group
leaders was extensive. Fortunately, the future scientific
directions of both UKIRT and the JCMT are in the area of
wide-field and survey-type observational programmes with
follow-up, and for the JCMT, involvement in sub-arcsecond
astronomy with the SMA. Therefore, with a reduced instrument
suite and anticipated longer observing programmes, this
naturally leads to the possibility of achieving savings through
a different operational model. The report was presented to an
international review panel (including JCMT agency
representatives) in October 2001 and subsequently to the JCMTAP
and Board.
Three possible savings models were derived: natural wide-field;
wide-field with savings; aggressive savings-driven. All produce
savings, but the amount increases with each. The first is a
natural evolution from where we are now to a wide-field model
but without being driven by the need to make savings. This
brings a level of savings that are modest. Because the majority
of the cost of the JAC is on salary related areas, this means a
small reduction in the workforce. The second takes this
direction further by seeking additional savings and staff
losses, which will be at a level that will definitely have an
impact on the "look and feel" of the JAC but where the risk to
the science output should be manageable. The third model
requires much higher levels of savings and staff reductions and
was closest to achieving the level of savings that PPARC were
seeking. In this model, the level of staff reductions was so
severe that it was assessed by JAC management as far too risky
to contemplate both in terms of managing the change and of
producing a far too stressed operational model. A critical
aspect of the model was the number of resulting single point
failures through loss of key staff leading to potentially
serious losses in programme delivery.
In the latter two models there is a noticeable reduction in user
support and users will need to take on additional responsibility
for organising their observing runs. Furthermore, major project
work at the JAC becomes almost entirely serial in nature rather
than parallel. This means that only one major piece of work can
be undertaken on either telescope at a time. On the other hand,
because of the need to retain staff due to the arrival of new
JCMT instruments (ACSIS, HARP-B, SCUBA-2) significant savings
cannot readily be achieved prior to 2006.
The Review Panel, Advisory Panel and Board agreed that given the
financial pressures the wide-field with savings model was the
minimum acceptable operational level commensurate with
scientific output. This translates into the JAC losing something
around 15-18 staff, mostly expected after 2005/6. The details
have yet to be agreed and depend somewhat on the future
instrument reliability and programme delivery, and in any case
will be for the next Director to really get into the details of
managing this process. But the broad brush has now been agreed,
the JCMT will focus on wide-field survey-type programmes as well
as having an important role in sub-arcsecond submillimetre
astronomy with our involvement with the SMA.
This brings up the question of the existing suite of heterodyne
receivers. The JCMTAP were very keen that RxB3 and RxW had a
significant role to play in the programme of sub-arcsecond
astronomy. However, the use of these instruments as part of a
single dish facility was seen to be much weaker by ~2004. It was
agreed that RxA3 has a much lower priority altogether and given
its age, obsolete components and lack of immediate opportunity
for upgrading, its useful lifetime could be considered
finite. Therefore potential future users of RxA3 are encouraged
to submit programmes sooner rather than later {link}. So the
future role of the JCMT is now defined. After the arrival of
HARP and SCUBA-2, it will be a facility concentrating of
wide-field astronomy and undertaking sub-arcsecond astronomy
with RxB3 and RxW.
Turning to the development programme, the key aspect to note is
that the JCMT Board has now approved committing all of the
remaining funds through to the end of the Development Fund
(2009) to the ongoing construction of SCUBA-2. However, such is
the rate of spend on this instrument that all these remaining
funds will be consumed around the time of the detector
proof of concept critical design review in October 2002. So
where will the remaining funds come from to complete SCUBA-2?
The UK government (the Office of Science and Technology) has
awarded £4M contingent on the full funding being identified. The
bid to the Canadian Foundation for Innovation (CFI) was
successful in the first selection round in December and has now
been resubmitted to the final selection phase. A decision is
expected in late May and because of the critical nature of the
outcome for the future of SCUBA-2 and potentially the
operational model and funding of the JCMT, the JCMT Board has
been postponed until late June. The nature of the "savings from
operations" will also be clarified in June.
As noted in a previous Newsletter, PPARC awarded funding for an
outreach post and we welcome Douglas Pierce-Price who joined the
JAC in December. Douglas has already stepped in and produced the
JCMT poster for the Hale Pohaku Visitor Center and is now hard
at work getting involved in numerous local outreach
activities. At some point Douglas will also take over
preparation of the Newsletters and the public web pages for both
telescopes.
Finally, my two tours of duty are almost up and it is time for me
to move on and return to the UK. It has been an exciting and
challenging nine and a half years in Hawaii and I am very proud
of what has been accomplished at the JAC. The credit of course
goes to the staff, without their excellence and dedication
nothing would have been possible. I should also like to thank
the user community for being both supportive and understanding
when things didn't happen as quickly or as efficiently as we
might all have hoped for. My thanks also go to the members of
the JCMT Board and Advisory Panel for their very encouraging
support over the years, and to the funding agencies for their
ongoing and prompt financial contributions. We all recognise
that both telescopes are acknowledged world class and highly
productive, the very best of their class. Both have well defined
development programmes already in place and with the future
operational models now agreed, the future at the JAC is rather
tightly defined. I had hoped that the SCUBA-2 situation would
have been decided by this point, but we should all remain
optimistic that by June the last piece of the jig-saw will have
been put in place and I can then go about moving back to the UK
with a degree of satisfaction and closure.
back to:> March 2002 Newsletter Index
Click here for printable version.
Ian Robson - Director JCMT
|