|
|
|
____________________
|
|
|
|
UIST Engineering
|
Engineering History
|
|
ENG History:
- Jan 09: Diamond noise pattern on array in short NDR
exposures; horizontal stripes of noise in longer exposures. UIST
unavailable for the night; traced to a grounding wire.
- Aug-Oct 08: UIST off scope and warm. New cold-head.
- Jun 08: Throughout the 2 month summer cass block (08A/08B)
UIST very occasionally threw up a noisy bottom-right quadrant.
Examples images:
Full array (GIF), zoom in with slice (GIF) and
semi-reduced wce image
(FITS) - note that the fits image is flipped
horizontally. Occurred once every hundred frames or so; single bad
frames were usually preceded and followed by perfectly good frames.
- Nov 07: UIST still off scope though cold. Tests show
that the
noise in the top two quadrants noticed in July remains.
Was initially thought to be bad video boards. However, swapping
boards didn't move the noise to other quadrants. Eventually
discovered to be "the internal 5vdc interlock cable for the controller
that had been tied in very tightly with some of the video board signals,
which in turn seemed to have caused the noisy channel on quadrants 1
and 2. After moving the cable away from the rest of the video signals
the problem immediately went away."
- Aug-Oct 07: UIST off scope and warm - replacing coldhead
and rotating array back to where it
was at the start of the year (normal orientation).
- July 07: Noise in the top two quadrants of the array.
The problem was in the controller. There is one video board per
quadrant so two boards (video 0 and 1) appear to have a bad channel. Video
board 3 was swapped out with a spare last December due to a channel problem but
hasn't been repaired yet. Can't use
WFCAM spares as there are several mods required. See 20070601.009
- May 07: Uist suddenly starts to warmup at 3.30am on
2007-05-26. See this
temperature plot of the temps over a five day period (each block
is 12 hrs). [Light blue - array, dark blue - coldhead stage 1, red -
optical bench]. However, it then starts cooling back down again (with
no intervention from us). Pressures were nominal and coldhead sounded
fine throughout: suspect a possible clog in the coldhead that cleared
itself. Even so, a week later we conducted a mini-warmup to purge the
coldhead of the blockage. UIST was down for only one night.
- Apr 07: Array returned and back in UIST. However,
bottom-left quadrant found to be dead upon cool-down. Suspect pin
alignment. Warmed back up and rotated the array through 180 degs.
All four quadrants live following the cool-down, but array is now
shifted with respect to the optical path. Result is vignetting in
imaging (loss of 4% of the array) and shifted IFU slices (now losing
half of one of the slices); all of the reference pixels used with
UPICK for imaging acquisition are also shifted, albeit by the same
amount in x,y. Living with this for 07A - summer Cass block.
- Mar 07: While UIST warm ship array to Raytheon for
QE measurement. Lengthy report delivered.
- Jan 07: UIST warm and open; use LED and detector to
measure through-put of optics with Suzie Ramsay Howat. Found to be
within ~10% of predicted value for entire optical train. Now question array
QE or pupil alignment.
- Jan 07: UIST warm and open: replace L2/L3 lens unit,
and install new filter for IJ and JH grisms.
- Oct/Nov 06: David Atkinson visits with SDSU controller
(arrives late because of earthquake). Initial problems with not being
able to detect light on the array; eventually traced to missing load
resistors on the UIST detector board. (With no load resistors all of
the outputs were simply being driving to the VddOut output FET drain.)
Erik and David fitted 10K load resistors to the video inputs on the
four SDSU video boards.
- October 06: Towards end of 06B cassegrain period the
UIST temps started to creep up (by a few degrees, though array
remained steady at 30K) - fault 20060924.003 and 20061023.002.
Traced to vacuum degrading. Pumping from Turbovac on the instrument
noticeably improved the temps (reversed the upward trend), and the loss
of vacuum was later tracked to the Q3/4 outputs wiring pole connector,
which was very loose. Erik tightened the connector down; he also
tightened the screws on the other 3 wiring pole connectors which were
only slightly loose.
- August 06: UIST back on after summer WFCAM block. UIST removed
for possible shipping to ATC (didn't happen); spacers adjusted on new
2pix and 4pix slits for IJ.JH spec (slightly better); new
coronagraphic mask installed. OT updated to accommodate posn angles with
"imaging" (for coron only), and to make the new slits available.
- January 06: UIST back on after 6 months off for WFCAM. New slits
with spacers installed for IJ and JH, plus prototype coronagraphic
mask. Slits don't seem to help though, and coron pol mask
orientated 90 deg w.r.t. normal pol imaging mask (so dispersion
will be along aperture).
- June 05: UIST back on after telescope after WFCAM run. But bad connection to
DAQ 2 giving 4-bad/4-good columns in the top-left quadrant. Also, problems with filter
wheel 2 stuck, and focus a bit flaky towards end of 2 month run on scope.
- February 05: Grism wheel 2 failure
- Oct-Nov 04: UIST off during WFCAM commissioning. Back on mid-Dec
(wasn't opened).
- August 04: UIST warmed up when chiller failed. Back to nominal
operating temp after being down for two days (31 Aug/1 Sep).
- August 04: Heavy engineering (rewiring) and computer upgrades in control
room, though UIST remained cold and on telescope.
- December 03: UIST off scope (cryogenic/vacuum problems) from Dec '03
until 2 April '04.
- March 03: UIST off scope to replace grisms and filters
|
|