|
Newsletter issue 12
UNITED KINGDOM INFRARED TELESCOPE
Newsletter
Issue 12, Spring 2003
Progress on the WFCAM Instrument at the UKATC
Mark Casali & the WFCAM Project Team
U.K. Astronomy Technology Centre, Edinburgh
After years of calculation, design and reviews, WFCAM is now leaping off
paper and into aluminium. Progress over the last six months has been
rapid and the large team is moving all sub-assemblies forward in
parallel toward a system integration phase beginning in the summer - a
critical time when unexpected problems and delays may show themselves.
An important theme in our risk mitigation plan has been to work closely
with manufacturers after issuing of contracts, so that we become aware
of problems and delays early on and can work with them to recover lost
time. This approach has already saved the project from major slippages
due to manufacturing delays and technical problems.
Other groups are involved in major work packages for WFCAM. CASU at the
IoA in Cambridge are developing the full data reduction UK pipeline as
well as the summit pipeline necessary for data quality assurance. The
WFAU at the IfA in Edinburgh are developing the science archive and user
interface tools to query the large catalogues and image data. JAC in
Hilo have taken on telescope-side software developments for WFCAM, the
design of the new M1/WFCAM interface plug, and design and procurement of
the WFCAM handling truck. SUBARU are procuring the remaining three
Hawaii-2 detectors for us, as part of an agreement with PPARC.
Electronics and detectors
We have so far received only one of the four science grade Hawaii-2
devices ordered, along with several engineering devices and
multiplexers. Rockwell are experiencing delays due to poorer than
expected device yields. In the meantime we have carried out extensive
tests of the one we have (#41). QE across science bands is good with
mean values of 0.66, 0.68, 0.77, 0.76 at Y,J,H,K. Persistence, which
has been something of a problem with the HgCdTe PACE process on saphire,
is virtually unmeasurable. Read noise is better than spec and we
achieve a 15-electrons CDS with a prototype preamp + controller lab
system. Cosmetically the device is quite good with a single dead column
in one of the quadrants and a roughly circular patch of a few hundred
contiguous bad pixels. One unexpected problem discovered during focal
plane prototyping was a mechanical instability in which the detector
squirmed out of its ZIF socket by ~15 microns with each thermal cycle.
With WFCAM's f/2.4 fast final focus we need excellent detector
coplanarity and mechanical stability, so this has forced a late
re-design of the focal-plane assembly.
All four 32-channel SDSU controllers have been received - a major
electronics milestone. These required the development of new 8-channel
analogue boards and 250 MHz fibre link, and the entire 128 channel
system will be able to read out the four 2kx2k detectors in around 0.65
seconds. The controllers will be mounted under the mirror cell, with
ATC-designed preamps on the cryostat.
|
|
FIGURE 1: The WFCAM cryostat in the lab.
|
Cryostat and mechanisms
The WFCAM cryostat was delivered just before Christmas, and vacuum tests
were conducted in January 2003. Some re-seating and cleaning of o-ring seals
was found necessary to remove leaks and the cryostat vacuum performance
is now satisfactory. The radiation shield, internal optical tube and
focal plane ring have also been delivered. We anticipate that the first
cooldown, during which key internal temperatures will be checked, will
occur towards the end of February. Optical alignment tests of the
cryostat assembly will be done vertically, but flexure tests of the
entire cryostat with field lens tower will be conducted horizontally.
A new stiffer primary mirror lifting plug, onto which WFCAM will mount,
is being manufactured and will be
shipped to JAC in time for mirror aluminizing in summer when it will
replace UKIRT's original one.
|
|
|
FIGURE 2:
The M2 mirror with lightweighting pockets visible. This will fit on
the existing UKIRT tip-tilt/hexapod assembly.
|
FIGURE 3:
The M3 Zerodur double-arch mirror. This will operate at around 120K.
|
The WFCAM filter paddles are a new type of cryomechanism and were
prototyped and tested cold last year. Tests consisted of cold lifetime
tests involving thousands of cycles inside a large test cryostat.
Accuracy and repeatability has been shown to be excellent. The full 8
paddle set is now being manufactured.
|
|
FIGURE 4: The WFCAM handling rig on display at the suppliers
|
Optics
Manufacturing of all the optical components by SESO and AMOS is now
well under way. The cryostat window and final field flattening lens are
finished and awaiting coating. Rough machining of the other components
including the new lightweighted secondary and double-arch zerodur
tertiary is complete. Small imperfections (chips) arose from the
machining process in the field lens, M2 and M3 optics. These have no
impact on the performance of the field lens and M2, and have been
removed by grinding in the case of M3. SESO has test-coated samples with
their proposed broadband anti-reflection coating and have shown that
our specification is achieved.
Software
The WFCam software is currently progressing in two major areas, the
camera control system and the high level sequencing and control
systems.The real-time software for the camera controller has reached a
stable release, and is now frozen for a time to allow development of
the interfaces to the control systems. The sequencing and control
systems are currently running in simulation mode, and we hope to have
tested these on the final hardware in the next few weeks. The next two
months will also be the first all up tests of the mechanism control
and other services in a cold cryostat, work which was completed last
year. Also, the prototype survey component of the Observing Tool (OT)
is currently being tested.
Instrument Handling
WFCAM will mount above the primary mirror, and so some special handling
gear will be required to safely install the one tonne cryostat. A custom
lift truck has been designed by Hyster and JAC personnel will attend
acceptance tests in North Carolina at the end of February.
Delivery
Delivery to JAC is planned for before Christmas 2003, with
commissioning on the telescope early in 2004.
For the very latest information on WFCAM, please visit the WFCAM web pages at the
UK Astronomy Technology Centre in Edinburgh.
UIST commissioning in Autumn 2003
Suzanne Ramsay Howat1, Stephen Todd1,
Sandy Leggett2 and Chris Davis2
1U.K. Astronomy Technology Centre, Edinburgh, U.K.
2Joint Astronomy Centre, Hilo, Hawaii.
The new UKIRT Imaging Spectrometer achieved first light on the telescope
on 24th September 2003. This major event signified the end of an
intense period of installation and testing by engineers and scientists from
the UK Astronomy Technology Centre (UK ATC) and the JAC. Weather,
telescope and instrument cooperated to allow UIST to be tested in its
three major modes (imaging, spectroscopy and integral field
spectroscopy) during the first half-night of observations. A 20 night
commissioning period followed, completed in December 2003, before
'shared risks' PATT observing with the instrument began.
|
|
FIGURE 1: JHK "true colour"
image of the elephant trunks" in the Eagle nebula.
Right - a wide-field L-band image of the same regions,
revealing some of the reddest and most embedded sources
in the region.
|
|
The commissioning offered a chance to test out in more detail the UIST
observational modes: thermal and non-thermal imaging and spectroscopy,
spectral and imaging polarimetry and 3-D spectroscopy with the
integral field unit. Three-colour JHK and L images of the Eagle nebula
obtained during the commissioning (Fig.1) shows the powerful
combination of the UIST field (2' square) and spatial resolution
(0.12arcsec pixels). The field of view of thermal
imaging in particular offers significant gains over IRCAM.
|
|
|
FIGURE 2: Top - a wide-field
UFTI image of the star forming region G25.65. Note the
"Herbig-Haro-like" bow shocks centre-left in these
data. Bottom - a UIST IFU "image" of the bow-shocks
structure discovered in the UFTI data. The UIST image shows
the 1-0S(1) emission, though images of this object
were obtained simultaneously in other H2 lines, allowing
for excitation analysis.
|
|
|
|
|
FIGURE 3: An IFU "map" of
part of the planetary nebula NGC 7027. The greyscale
shows H2 1-0S(1) emission, the contours Br gamma
emission. |
FIGURE 4: An L-band spectrum
of NGC 1068 showing the strong absorption feature at
3.4um.
|
|
Exploration of the integral field mode was one of the highlights of
commissioning. UIST's deployable IFU is a unique feature of the
instrument. Spectra are obtained over a 3.3arcsec x 6arcsec area of
the sky, with spatial resolution of 0.24arcsec x 0.48arcsec. A 3D cube
of data is produced by the pipeline reduction software. Extremely high
fidelity observations of the wavelength dependent morphology of
astronomical objects can be obtained with an order of magnitude
greater efficiency than slit scanning techniques. A molecular hydrogen
(1-0 S(1)) image of newly discovered bow shocks in the high mass star
forming region G25.65 is shown in Fig.2.
|
|
FIGURE 5: Mark Horita, Tim
Chuter and Chris Davis install new optics (grisms,
filters and slits) into the UIST wheel modules at
UKIRT. Sandy Leggett - also involved in the engineering
work - took the photo. |
|
Once the initial checks of
the IFU were carried out, experiments in mapping larger objects were
undertaken. Three IFU positions are required to span the diameter of
the planetary nebula NGC7027. Images in 1-0 S(1) line of H2 and in
Brackett gamma (Fig.3) show the excited molecular gas located in
complex filamentary structures beyond the ring of co-located ionised
and molecular gas.
UIST functioned with an extremely low level of fault during the
commissioning. As a result, data were obtained for twelve UIST service
programmes, many of which were completed. The service observations
ranged from JHKLM photometry of galaxies to HK spectroscopy of brown
dwarf candidates and integral field spectroscopy of elliptical galaxies.
One spectrum obtained, of the 3.4micron absorption featurs in NGC1068,
is shown in Fig.4. This spectrum confirms that the spectral shape of this feature
in NGC1068 is the same as for the Galactic ISM. The absence of a
3.0micron ice feature is also confirmed, thanks to the wide wavelength
coverage with the 1024x1024 UIST array.
Full information on the UIST performance can be obtained from the instrument
web pages
(
/UKIRT/instruments/uist/uist.html). In
comparison with predictions before delivery, the overall image quality and
functionality are as expected, with the wide wavelength coverage a notable
enhancement over CGS4. However, the raw sensitivity is lower than
anticipated due to significantly reduced instrumental transmission. During a
February 2003 engineering period, a modest improvement will be wrought by
increasing the instrument aperture. However, UFTI is recommended for JHK
imaging, unless the large field is required.
Other enhancements to UIST during the scheduled engineering time include the
installation of a new IJ grism and a grism to provide a
cross-dispersed mode for the HK bands. The IJ grism should cover a wavelength
range of 0.8-1.4 micron with higher efficiency than the work-around which has
been in use during the commissioning and shared risks observing. The HK
cross-dispersed mode will cover a range from 1.4-2.4 micron with spectral
resolution of about 1000 with the 0.5arcsec wide (4-pixel) slit. Additional
narrowband imaging filters have also been
installed.
PATT applicants may apply to use these new grisms for 03B. However, they
should mention a backup option in their proposal, in case these new grisms
prove to be unusable.
View from the Top
Thor Wold
Joint Astronomy Centre, Hawaii
As usual, it seems, many changes are happening at UKIRT and
surrounding areas. Firstly, we have a new look in the UKIRT
control room. Here are two archival photos of the changes
through the years, the lower photo is of our new layout, with
eight large flat-screen LCD monitors and a further panel
which serves as both the second head
for kiki, our data-acquisition machine, and the link
for our Polycom. The LED displays did not show up in the
photo, but believe me, they were up and running. Now, the
telescope and kauwa (the observing prep and data reduction
machine) are three-headed. With this came a new screen
management system to learn. Nobody can say they are getting
bored around here. The top photo, courtesy of John Davies,
shows observer Simon Green with his feet up on the venerable
Ann Arbor computer, circa 1985. Note the Hadfields rack to
the right, which is in the same position as always, and so
appears over just behind the unidentified reprobate in the
bottom photo. UKIRT was just beginning to hire full-time
operators around this time, but often the observer would also
run things (or Simon was just using the chair?).
|
|
|
Then and Now... The UKIRT
control room back in the mid-1980's (top), and a few
weeks ago. (Golden Oldie from 1984, courtesy of John
Davies, UKATC). Click on each image for the gorey
details... |
Down in University Park where the JAC offices are, the Smithsonian
folks are busy building their new headquarters across the street. The US
Department of Agriculture is erecting a new office and lab building at the
corner where you turn towards the office complexes, and ground has been
broken for the new $30 million Mauna Kea Astronomy Center, which will
contain an exhibit gallery and world-class planetarium.
Construction on the first $60 million segment of the Saddle
Road re-alignment is slated to finally begin this fall. This
is 13 miles of the 47 mile project, and will move the current
route through the military's Pohakuloa Training Area further
up the side of Mauna Kea, so that traffic will no longer
bisect the training grounds. This is Section II of the
project. I was quite surprised to find out that the planners
have changed their minds and decided that the next sections
they will worked on will be Sections III and IV, which will
cost $52 and $12 million, respectively. These are the
sections that will run from the 6 to 28 mile markers, up from
Hilo. The timetable for this is pending the securing of
funding. Section I, which is the western end, will be
last...so the personnel who are headquartered in Waimea will
have to wait.
Section IV will connect to the 6 mile mark on Kaumana Drive, where
construction of the Puainako Street extension is well underway. When this
is completed, we will be able to traverse from the offices off of Komohana
Street, up Puainako and right onto the realigned Saddle Road and on up to
the summit. Not only will this be more convenient, it will be quite a bit
safer.
As if construction down there were not enough, there is a lot
to contend with up at Hale Pohaku. It seems that the folks
that run our camp forgot that their main mission was to
support people that work all night, so need to sleep in the
day! They launched a project to bring the place into full
compliance with the Americans With Disabilities Act; decided
that the ramps that lead off the upper parking lot were
substandard, so they cranked up the jackhammers nice and
early, even removing the pavement from a few parking stalls
while they were at it. Not satisfied with this, they also
started into another project, replacing the siding on Building
C, while still putting people in the rooms! They are still
putting people in rooms only one room away from the activity
to this date. The resulting impact on the lack of sleep on
the JAC TSSs merited a stiff letter of complaint - if for no
other reason than this was a safety issue. It really seems
that they DID forget that people do need sleep! I have always
thought it would behoove the folks that run the show to try to
follow our sleep patterns a few times a year, to remind
them. Also to stay in the rooms. Yeah, right...
One hopes this will be over and done with soon, but a noticeable
lack of activity after the first few weeks of intense action is now
happening. One benefit to come from this (whenever it finally
happens!) is the enlargement of the upper parking lot. In the meantime,
as of this writing, they are going to rip apart the toilets in the commons
building, which will undoubtedly take some time. We will have a host of
porta-potties located out the western door until whenever.
So, as for your wonderful Vacation Resort Hale Pohaku: so much
changes...yet so much stays ever the same.
The tour vans that run up the mountain every day to catch the
sunset are seemingly always totally full. I've heard that Mauna Kea is
now classified as a major tourist attraction, and the number of folks
wandering around at sunset is certainly an indication. The van drivers
apparently have discovered the silversword plant I wrote about in the
Autumn 2001 issue of the Newsletter. They park and disgorge the hordes,
armed with their cameras, to hopefully not abuse the poor plant. I hope
that at least this ensures that the fence around it to protect it from the
feral ungulates will be maintained.
The Rangers who have been hired to monitor the visitors have been
performing wonderfully. They keep people from knocking on our door, and
I've not found anyone up on our roof for years! They also make sure people
go down after sunset. Their hiring came just in time, with the huge
increase in the tourists.
We have just begun our experiment in fully-flexed observing.
I have had the pleasure of being the first TSS at the helm for
the first run and it appears to be working very well. Stuart
Littlefair, the observer whose program was rated highly and
who then came out to run the queue did manage to finish almost
all of his own program. We also started taking data for four
other programs (depending on the atmospheric conditions)
within these first five days allotted. Had his run been
classically scheduled, he would have gotten one night's worth
of data. Stuart was a joy to work with through this
'teething' process, keeping his good spirits up while we
worked out the inevitable kinks.
Note to Stuart: take heart that the cooks at HP didn't zero in on
you or I am sure they would have dug up some creative apellation with a
twist on the movie mouse Stuart Little. You know how they give everyone
pet names (no pun intended).
Greatly assisting in organizing and handling this is the OMP
system, which has been discussed in this publication previously. It seems
to be working well, but as always, it is still evolving as we see what our
needs are in the realm of working in fully queued-scheduling.
This winter has been considerably less wet than last. A weak El
Nino condition was declared last fall; it has already been declared to be
weakening in January and the forecast is for 'normal' weather patterns
(whatever that means!) to prevail April through October. The moisture
that made its way to the upcountry last winter and spring and made the
pastureland once again green has been long gone. So have the cattle, who
have been moved to lower pastures. The upcountry drought in Hawai'i that
has been going on for more than the past ten years continues. Even Hilo,
notorious for its rain, had a mini-drought in the first two months of this
year. Kind of hurts a lifelong resident like me to see the place turning
brown. The rains are back now, though, so it will be back to having to
beat back the jungle.
Aloha!
People
We would like to extend a welcome to Jeff Cabral, Observatory Technician
who joined the JAC in October. Jeff will be working within the ETS
Group where he will provide support for filling JAC instruments with
liquid cryogens as scheduled daily. He will also perform general
facilities maintenance tasks, vehicle safety checks and minor repairs, and
transport equipment and supplies, including cryogens, to and from the
summit facilities.
UNITED KINGDOM INFRARED TELESCOPE
Newsletter
Issue 12, Spring 2003
|