|
Newsletter issue 13
UNITED KINGDOM INFRARED TELESCOPE
Newsletter
Issue 13, Autumn 2003
Flexible Scheduling at UKIRT in Semester 03A
Jane Buckle & Andy Adamson
Joint Astronomy Centre, Hilo
As announced in the last Newsletter, UKIRT was flexibly scheduled for
the first time in Semester 03A. At the time of writing, the semester
is just complete, and it is time to review the success or otherwise of
the undertaking and consider what has been learnt and what changes
should be made. We first give a few statistical indications of the
degree to which flexible observing has benefitted the science output
of the telescope.
Flexing at UKIRT is based on a short list of principles, endorsed by
the UKIRT Board:
- Completion of programmes, especially high-priority programmes, is
the key goal.
- Programmes requiring the best observing conditions should have the
best possible chance of being done in those conditions.
- Observers who come to the telescope should have a good chance to
carry out their own observing programme.
- UKIRT programmes vary
considerably in complexity, and there are a number of different
atmospheric constraints. Summit observers must therefore retain a
significant degree of discretion in selecting programmes for
execution.
The first two principles are addressed through the TAG, who award
summit occupancy to highly ranked projects and/or projects with tight
weather constraints. Low-ranked projects, even if they have severe
weather constraints, are unlikely to be awarded summit occupancy. The
third principle is addressed directly by the UKIRT flexing model, and
the fourth principle is addressed by procedures at UKIRT that are
overseen by support astronomers. Summit observers can observe their
own project unless the weather is not good enough for it, and can
choose (according to their technical expertise) between the top few
projects in the queue when not observing their own project.
|
|
FIGURE 1:
The completion of all flexed projects for 03A, colour coded by
conditions constraints.
|
Early indications are quite positive. Across all programmes in the
flexed queue, the average completion rate is a creditable 77%
(Fig. 1). Across the top 10 flexed programmes, however, the average
completion rate is much higher, at 94%. A considerable amount of
effort was put into monitoring progress through the semester; as an
example, Fig. 2 plots the progress (in percentage completion) for each
of the top ten programmes, weekly through the semester. Of these ten
programmes, the ones not completed are those which, for a variety of
reasons, did not always have MSBs (minimum schedulable blocks) in the
observing queue although their targets were available. The completion
rate of programmes not available until late in the semester was
artificially lowered by the unexpected extension to the aluminizing
shutdown.
|
|
FIGURE 2:
The completion per week for the top ten ranked programmes.
|
These completion rates are a measure only of the telescope time
accessed by each programme through the semester. PIs now have to judge
how much of the science has been completed by the data taken. On the
UKIRT PI report, which all PIs are now required to return, PIs are
asked to estimate the scientific completion of their programme. Early
signs are again good: almost all of the reports so far returned state
that their science programme is as complete as their time
allocation. There are a few exceptions to this, of course; these
involve complex observing modes known to be testing the capabilities
of the instruments.
Statistics such as these indicate that the essential goal of flexible
scheduling - preferential completion of the best programmes - was met,
even in the first semester of operation. However, it was also clear in
the course of the semester that the speed of the feedback loop between
the observatory and remote PIs was insufficient in some cases to
guarantee the science quality of the data. This was clearly identified
as a critical area for both telescopes. Semester 03B therefore brings
a number of enhancements in the OMP software - the JCMT/UKIRT shared
suite allowing us to operate in this mode at all. It is now possible
for a remote PI to access the pipeline-reduced data products in
essentially real time via their project home page, and so the "loop"
should be much better closed in Semester 03B than in 03A. But PIs
beware - while raw data are persistent for the whole semester, reduced
data products remain on disk only for a short while; make sure you
react quickly when you get the automatic announcement that data are
available for your programme!
Primary Mirror Aluminising - Summer 2003
Marc Seigar
Joint Astronomy Centre, Hilo
Between June 23rd and July 29th UKIRT was closed for aluminising the
primary mirror and modification of the mirror plug and covers to
support WFCAM. In addition a new facility UPS was installed.
Due to the crowded instrument delivery schedule over the past few
years, it had been a long time since the mirror was last aluminised
(almost five years) and, as a result, there were very few science
staff at JAC who had seen the procedure done before.
| | | |
| | |
|
|
FIGURE 1:
Lowering the mirror cell
| | | |
FIGURE 2:
The mirror and (below it) the mirror-cell
| | |
FIGURE 3:
The mirror-cell in full view
|
The first step in the process was to lower the mirror cell, complete
with mirror, onto a trolley on which it could be wheeled out from
under the telescope (Figure 1). This entire structure weighs about 20
tonnes. The mirror was then (carefully!) lifted out of the cell
(Figure 2). This was only the second time this had been done since the
installation of active optics actuators around the edge of the mirror
- the anchorage points can be seen in Figure 2. Figure 3 shows the
mirror cell after extraction of the mirror. The aluminium cylinders
are the pneumatic supports which are connected together in three
sectors and form the "pneumatic whiffle tree". There are 80 of these
pneumatic supports, each of which supplies a pressure of 80 lbs per
square inch to the mirror. During the shutdown each of these supports
was tested for leaks. One of them was already known to have a leak and
was repaired.
The mirror was then placed into its transportation box and delivered
from UKIRT to its destination at the Canada France Hawaii Telescope
(CFHT - Figure 4).
At CFHT the mirror was cleaned and stripped of the old coating
(Figures 5 and 6). Chemical safety regulations dictate that everyone
had to be trained and specially clothed.
| | |
| | |
|
|
FIGURE 4:
Transporting the mirror cell to
the coating chamber at the CFHT
| | |
FIGURE 5:
Cleaning the primamry begins...
| | |
FIGURE 6:
Cleaning in full-swing
|
The next step was to coat the primary, which is done in a large vacuum
tank. The evaporative coating process consists of simply boiling small
samples of aluminium in carefully-selected places in the vacuum
chamber; in the absence of air the atoms drift in a straight line and
stick to the first thing they hit. The art comes in knowing just where
to put the samples, and how much to use to obtain the right thickness
of coating. On this occasion, the first attempt proved to be perfect,
with a coating thickness of 850 nanometres. The amount of aluminium
used was only about 2 mg - about one eighth the amount of aluminium in
a typical soft drink can!
Back at UKIRT, the newly coated mirror was lowered back onto the
mirror cell, as shown in Figure 7.
Two other projects were ongoing whilst the primary mirror was going
through the various stages of cleaning and re-coating at the
CFHT. Both tasks were performed in order to support the new Wide Field
Camera (WFCAM), which will be delivered to UKIRT early next year. The
first was modification of the mirror plug (at Bear Machinery in
Honolulu); the new mirror plug is shown in Figure 8. The second task
involved modification of the primary mirror covers on the telescope
so that they will close while WFCAM is mounted on the telescope
(Figure 9). Both tasks were completed successfully and in good time.
| | |
| | |
|
|
FIGURE 7:
Reinstalling the primary back onto the mirror cell
| | |
FIGURE 8:
Working on the mirror plug
| | |
FIGURE 9:
Modifying the mirror covers
|
So, well done and a very big thank you to all those involved,
especially the ETS group who spent around eight weeks at the summit whilst
this heavy engineering was going on and being prepared. We are also
grateful to the CFHT for the use of their aluminising equipment and
the efficiency with which they accommodated this work.
A web page showing more photos of the shutdown can be found at the following URL:
http://www.jach.hawaii.edu/JACpublic/JAC/ets/ukirt-aluminising-shutdown/webpage
The latest on WFCAM from the UKATC
Mark Casali
UKATC, Edinburgh, U.K.
WFCAM sub-assembly integration and testing is proceeding on many fronts
simultaneously. Among the important recent milestones are
|
|
One of the four science-grade detectors from Rockwell
|
- delivery of all four Hawaii-2 Science Grade detectors from Rockwell
- delivery of the window, field flattener lens and field lens from SESO
- delivery of all eight acquisition and data processing PCs
- manufacturing of all parts for all cryo-mechanisms
- achievement of operating temperature for the focal plane assembly in
the final cryostat, after modifications to the thermal paths.
- successful cool-down with the large 480mm window
- the first successful SDSU controller operation from the high-level WFCAM
software
- completion of the fast-autoguider CCD hardware and software
Problems are of course always present. Among these are
- difficulties in achieving the wideband coatings on the large optics: this has
forced us to descope to simpler coatings on all surfaces
- bugs in the 32-channel SDSU controllers: these are being investigated
and removed in consultation with Bob Leach
- delays with our test cryostat: essential for measuring and achieving
detector coplanarity and alignment
At time of printing (September 2003), delivery of WFCAM to the JAC is
expected for March 2004
See
www.jach.hawaii.edu/UKIRT/instruments/wfcam/ for a
description of the instrument, and
http://www.roe.ac.uk/atc/projects/wfcam/ for an overview of the
project and the latest news from the ATC.
Update on the UKIRT Deep Sky Survey (UKIDSS)
Steve Warren
Imperial College, London, U.K.
The UKIRT Infrared Deep Sky Survey (UKIDSS) will begin after
commissioning of the Wide-Field Camera (WFCAM). The anticipated start
of the surveys is mid 2004. UKIDSS will use approximately 1000 nights
of UKIRT time over 7 years (subject to continuing Board support!),
taking about half of all the UK time on the telescope. A description
of the scope and aims of UKIDSS was provided in Newsletter Issue 10
(Spring 2002). This brief note provides an update on UKIDSS activities
since that time. The web page www.ukidss.org gives fuller details. As
always, please contact Steve Warren, the Survey Scientist, at
sjw4@ic.ac.uk, if you have any queries, comments, requests, or you
have help to offer. See also the previous article by Mark Casali for
an update on the status of WFCAM.
Technical web page
There have been some minor technical changes to the instrument which
are detailed on the technical page, www.ukidss.org/technical.html. The
array spacing has increased from 90% to 94%. Two filters have been
added, a Br-gamma filter and a Z filter (0.83-0.925 micron). The Z
filter has a similar central wavelength to the Sloan z' filter, and
takes advantage of the unexpectedly good short wavelength quantum
efficiency (Q.E.) of the WFCAM arrays. Because of this good Q.E. the
Galactic Clusters Survey have decided to expand the number of filters
used to include the full broad-band set ZYJHK, at the expense of
reduced areal coverage. Details of the revised fields will appear on
the web pages once they have been finalised.
At a meeting of the consortium in November we finalised the list of
image parameters that will be measured, which is provided on the
technical page.
A set of UFTI observations to investigate issues of fringing, flat
fielding, and sky subtraction has been designed, and are expected to
be executed in September and October of this year. The results of the
analysis of these observations will be reported on the UKIDSS web page
shortly after completion of the observations.
Two-year plans
The consortium has been focusing on the 2-year plans, detailed at
www.ukidss.org/surveys.html. Meetings were held in May and June to
consider detailed implementation issues. Each working group drew up a
list of detailed requirements, for example, filter sequence, field
priorities, jitter sequence, microstepping, etc. The next step in this
process will be filling and prioritising all the MSBs for the entire
2-year plan, once the Survey Definition Tool is complete. At the same
time a more detailed scheduling model will be developed, to identify
areas where the requirements of the different surveys may come into
conflict.
Complementary optical data with the ESO VST
There has been a positive response from both ESO, officially, and from
the ESO community to the suggestion that a substantial fraction of the
ESO time for surveys with the VST (which is nominally 40% of the total
VST time) be devoted to obtaining complementary optical data in UKIDSS
fields over the first 3 years of operation of the VST. The VST is
expected to become operational towards the end of 2004. Following
input from the Large Area Survey (LAS), the Galactic Cluster Survey
(GCS), and the Deep Extragalactic Survey (DXS) working groups an
outline request to support these surveys was presented this Spring to
the ESO Working Group for Surveys (WGS), and to an ESO workshop
devoted to Large Programmes and future public surveys. The total
amount of time required for UKIDSS VST support is estimated at between
100 and 155 nights. There was strong support for this proposal from
both fora. The next step is for the ESO WGS to formulate a policy for
issues such as the procedures for proposing surveys, the actual amount
of time to devote to surveys, and the provision of pipeline and
archive facilities. Later this year UKIDSS will need to write a
scientific and technical case for the time.
World data release
The current consensus of the survey working groups is that the data
from the first two-month WFCAM run should be released to the world
about 15 months later, and that the data from the completed two-year
plans should be released 12 months after the completion of
observations. This is the position stated on the web page.
View from the Top
Thor Wold
UKIRT/Joint Astronomy Centre, Hawaii
It has certainly been yet another busy semester here at UKIRT, not
least due to our July-long shutdown for primary mirror aluminizing and heavy
engineering. However, this was also of course the first semester of fully
queue-scheduled observing. This went rather well, overall, judging from the
reports from the PIs - both those who spent time at the telescope and
those that had their observations done fully via the queue.
There were some snags. Most noticeable was the lack of
full information regarding location of targets, especially in
crowded fields. Finding charts with different scales and even at
different wavelengths can sometimes be unhelpful (optical images in
particular are often not helpful). From the observer's
viewpoint, every bit you can give us to help us to determine the
location of sources is essential. Otherwise, we can sit here for
quite a while, with your clock running, trying to figure out what is
what...
During the July engineering, Tim Carroll and I spent the first
week up-top, mostly working over at the Canada-France-Hawai'i (CFH)
telescope in the aluminizing room dealing with the preparations,
but also at UKIRT doing a lot of odds and ends and watching the
dismantling of the telescope and transport of the mirror to CFH.
This was quite an educational experience. It was also quite weird
being up there and working during the daytime. I never had to shut my
room window shade, for example; something we always have to do
with our usual sleep-cycle.
Tim and I also had the job of creating the list of tasks and the
proper chronology for coming back on-line after everything got put
back together. I must say that our guys did a fabulous job!
Everything came back to life sensibly and we were able to get
everything re-aligned, etc., within a few nights' work, and without
any major problems. Congratulations are in order to the ETS staff
for a job very much well done!
While our crew was so efficient and well-organized, the same surely
cannot be said about the ongoing construction at your beloved Vacation
Resort Hale Pohaku. The project, to bring HP into compliance with the
Americans With Disabilities Act, was to be a 'few months' long
(starting in mid-January). But unfortunately, at this writing, it is
nowhere near being finished. Activity is truly on-again, off-again,
on-again... with periods of construction crews working and periods of
no activity at all.
The worst of this situation is the reconstruction of the
lavatories in the Commons Building, a project that was supposed to be
finished by around March, but which was delayed and delayed and is
now due for completion in late August. In the
meantime, if you do not have a room, you have to put up with the portable
facilities, which were put in place 'way back in March outside the west
door. These naturally went unused until utterly necessary, and then it had
to be pointed out that they did not have facilities for hand-washing --
so a garden hose was set up with a sink! I think it was a while before
anyone realized that it would be nice if at least one of the units had an electric
light in it!
In the meantime, it was decided that the outer walls of the
dorms needed to be replaced, as I mentioned in the previous
Newsletter. They began by working on building C, all the while still
putting people in rooms, but on the opposite side of the building
from the work. Well, this has not worked out too well at all, causing
people to lose sleep from the racket. We have repeatedly had to
send reminders about the contractors not working in the mornings,
but it always seems that after a few weeks they are right back at it,
from 7:30AM.
Then, in June, work ceased. The scaffolding is still in place on
the Mauna Kea side of building C and the suspicion is that work will
at some point re-commence. I have always been of the opinion that
the folks that run Hale Pohaku often forget what it is like to
have to contend with working all night and trying to sleep in the
day. The worry now with HP regulars is that they will next target
building B, which houses (by far) most of the daily tenants.
If this does happen, it will definitely not be a
thing to look forward to at all.
Back in Hilo, construction is nearly finished on the new Puainako
Street Extension. I've mentioned this project in the past, because
it may well change how people commute between JAC and Hale Pohaku.
The project ought to be finished by around October if the weather
cooperates. It may then be most efficient to turn left out of the
University Park for about a block, then drive up the new road, which
will re-connect near the 6 mile mark of Kaumana Drive, thereby
avoiding all of the twisty, narrow part of Kaumana. The only real
reason to follow the current route (up Mohouli) would be if one had
to fill up on gas on the way. We will be sure to let our visitors
know of the new situation when access becomes available. The
Puainako extension will eventually also connect into the re-alignment
of the Saddle Road, so it will make your commute not only quicker but
much safer.
|
|
The Silversword plant on Mauna Kea
|
While this past semester was loaded down with an unusual
amount of engineering time, the current one will not be too much
better, since we still have some urgent projects we have to fix in
addition to preparations for the arrival of WFCAM, currently slated
for 04a. WFCAM will also require a large block of engineering when
it is first installed on the telescope. I do hope folks will be
patient with us through this next year. Please remember we do
strive to give you the best service possible, and we do have a
reputation for just that, a reputation that we need to keep up.
The rare Mauna Kea Silversword plant that I wrote about in the
August 2001 article has indeed bloomed at last (see the
attached figure). I took this photo back at the end of May
when the flower spike was just starting to blossom (from the
bottom up). There was relatively high humidity at the time -
cloud tops were lurking nearby and I had to get this photo
while I had decent light before the next bit of cloud came in.
What surprised me, though, was the aroma! I had no idea they
carried a scent that humans could detect - of course, they
have to have some sort of aroma to attract their pollinators.
It may have been the time of day (evening, on the way up to
work) and/or the humidity that caused the plant to release the
scent, but I must say it was certainly awesome and very
pleasant. As for a description, this is difficult. If I
could make it a visual experience, I would say "amber honey".
The tour vans were oblivious to the Silversword's presence
until very recently. This was good, I suspect, for at least the poor
plant was mostly left alone. Now, however, every time we come up, there are
literally hordes of tourists cluttered around the thing..
The bloom is about finished now. If the plant survives the
waves of "specimens of touri", it ought to start to produce
side buds and develop into more of a clump (at the moment it
looks like a single plant). I expect someone is monitoring
the situation and will probably be collecting seeds for
propagation, as well as re-positioning the protective fence to
keep the ungulates from eating it (this was the fate of the
other silversword plants that were planted in the same area).
Then, perhaps, we can hope to enjoy more blooms in a few years
time. I, for one, would surely love to smell that wonderful
aroma again.
Aloha!
UNITED KINGDOM INFRARED TELESCOPE
Newsletter
Issue 13, Autumn 2003
|