|
Newsletter issue 15
UNITED KINGDOM INFRARED TELESCOPE
Newsletter
Issue 15, Autumn 2004
WFCAM Arrives Safely in Hilo
Paul Hirst
JAC
All 14 of the WFCAM crates safely arrived at JAC on
17th August 2004, marking the end of a long period of anticipation,
and the start of a long period of engineering. With the arrival of the
WFCAM team from the ATC the following week, unpacking and assembly of
the instrument in Hilo commenced.
The instrument was shipped with all the optics and
the detectors packed separately for safe transport, so our first job
was to build up the instrument in Hilo, starting with mounting the
large tertiary mirror onto the baseplate and building up the
instrument from there. WFCAM was transported to UKIRT on 14th
September, and mounted onto the Michelle manipulator in the dome the
next day. Warm functional tests were carried out the following week
and everything appears to be in order.
|
|
|
WFCAM is unpacked and partially assembled in the lab at JAC in Hilo
|
|
|
|
WFCAM is then loaded onto a truck for the slow drive up to UKIRT
|
Due to the delay in fabrication of the WFCAM
corrector plate (a large aspheric optical component that seems to have
been particularly difficult to fabricate), we had been planning on
carrying out the first stages of commissioning with an aperture mask
in place of the real corrector plate. This would have given us
adequate image quality to complete many stages of the commissioning,
though at the cost of very low throughput. However, we have recently
received good news - the corrector plate has now been shipped and
should be arriving at JAC the last week in September. With some fine
tuning of the commissioning schedule, we're now planning on having the
corrector plate in the cryostat before first light - very welcome news
to all!
|
|
|
WFCAM arrives safely at UKIRT, where it is transported into
the dome through the roller doors.
|
|
|
|
Mechanical engineers Keith Burch and Jim Elliot and, in the UKIRT
control room, software engineers Alan Pickup and Andy Vick - just part of the
WFCAM team from the UK-ATC.
|
Currently, our commissioning schedule calls for
lifting tests during the first week of October. These will finalise
the technique for mounting the instrument on the telescope. The
lifting tests will be followed by cool-down the week after and
installation on the telescope. We're aiming for first light towards
the end of October or in early November.
|
|
|
WFCAM on the "Michelle" handling rig inside the UKIRT dome.
|
The UIST Grisms Saga...
Chris Davis
JAC
Many UKIRT users will know that we've been trying to acquire a usable IJ
grism for UIST for some time. Its a long and somewhat painful story, and
the upshot is that we're still working on this.
The first IJ grism was manufactured by Hyperfine Inc., along with an
HK grism that has been is use with UIST ever since. Both grisms used
fairly innovative technology in that they were "replicated"; a layer
of epoxy is spread onto the Infrasil prism face and a master grating
is then 'stamped' onto it, leaving behind the required grating as an
impression in the epoxy. These replicated grisms were expected to
give better throughput than the more commonly-used direct-ruled
"KRS-5" grisms. The HK grism has indeed been a real winner, being by
far the most popular spectroscopy mode with UIST (see e.g. the report
from Richard Wilman et al. earlier in this newsletter!). However, the
Hyperfine IJ was found to give very poor
throughput when cold. So UIST was commissioned in Autumn
2002 without a low-resolution IJ capability.
A replacement IJ was immediately ordered from Zeiss, a popular supplier of
optics in Germany who had provided many of the other grisms in UIST. The
new IJ grism was delivered in Spring of 2003 and installed and tested (a
number of other upgrades and improvements were also carried out at that
time). However, the IJ was again found to perform extremely poorly over most of
its wavelength range, giving almost no throughput in the I-band. The
plot below shows the transmission of the grism plus UIST optics over the
0.8-1.35 mm wavelength range.
|
|
FIGURE 1:
An IJ spectrum of HIP68209, showing the poor throughput at
over most of the wavelength range.
|
Rather than pay in full for a second unusable grism, JAC and
the UKATC negotiated partial payment and the return of the bad grism
to Zeiss. But removing the grism obviously involved an instrument
warm-up and potentially lost observing time. Add to this the busy
schedule of the ETS group in Hilo (Michelle was being recommissioned at
UKIRT for a brief period of use in early 2004 before its return to
Gemini), and the return of the grism was delayed by almost a year.
We have recently sent out tender documents for a third IJ grism. This
time we plan on resorting to the more widely used, and therefore hopefully
safer option of a direct-ruled KRS-5 grism (all the short- and long-
grisms in UIST are made of KRS-5). We've also had similar throughput
problems with the HK-low grism that was to be used for cross-dispersed
spectroscopy. However, given the relatively small gains offered by this
mode, and the possibility of freeing up two slots in the grism wheels,
we've decided to replace the cross-dispersed mode with a JH grism and a
second wollaston prism. The latter will mean that spectro-polarimetry is
possible with all grisms in UIST.
Its still early days, but we hope to procure these three optical elements
in the next few months. If all goes to plan, IJ, JH and additional
spectro-polarimtery options should be made available sometime in 2005.
View from the Top
Thor Wold
UKIRT/Joint Astronomy Centre
We are now in the semester that never was...technically, we have
no semester 04b because of the WFCAM commissioning which is coming up
shortly. This left us with just a couple of months for regular observing,
so we decided that rather than stamping that few weeks with 04b, we would
just continue with the 04a label. This was also inspired by having to
extend 04a somewhat in the first place, in order to fill the months of
August and most of September prior to the advent of the commissioning.
So, you won't see a UKIRT semester 04b in the record books
anywhere. But do not be alarmed...
We are greatly looking forward to the first round of WFCAM
commissioning. The second round, it is hoped, will occur early in 2005
and then we expect to start with WFCAM observing soon thereafter.
The reorganization of the computer room facilities, both to
rationalize things and to be ready for the terabytes of data from WFCAM,
was completed in mid-August.
The very long-awaited new Puainako Street Extension was finally
dedicated on September 21 and is now available. We will probably be
changing our instructions to visitors to use this route up to Hale Pohaku,
rather than the old way up Kaumana Drive. The only reason to go the old
route would be if you had to put gas in the car, as there are no gas
stations available along the new road. However, this road will not only
be much faster but it'll also be very much safer. It connects with
Kaumana Drive at the 6-mile marker, well above all the narrow, curving
road, and so directly onto Saddle Road (okay, I know Saddle Road is also
narrow and curving!).
Speaking of the Saddle Road, you will note a sign at the 8 mile
marker signifying roadwork underway. This is odd, and somewhat
misleading, as there is no roadwork for the next 11 miles. The
construction of the bypass of the military training area at Pohakuloa (the
other side of the Mauna Kea Access turnoff) is well underway. I think the
sign refers to the next segment, which will be from the turnoff by the 27
mile mark, east back to the 19 mile mark. Thus far, there is scant
evidence of any real construction.
Following this, and of course pending funding, the idea is to then
re-align and widen the road from there down to the 8 mile mark - but this
will be a few years away. For more information as to Saddle Road plans,
see my previous column in the Spring 2004 issue.
Down in Hilo and in the University of Hawaii-Hilo Science Park,
the construction of the new Mauna Kea Astronomy Education Center is
underway, with the titanium cones and main center taking shape. For
some shots of the construction that is underway, visit
maunakea.hawaii.edu/menu.html
and click on construction. There are other pages giving general
information on the facility also available from this main page. This is
happening right at the corner where you turn left to get to the JAC
offices, so it'll be rather surprising for anyone who has not visited us
in the past few months. Contracts have been issued for the equipment for
the theater and planetarium. Upon completion in late 2005, this facility
will give our visitors and their families a rich experience in culture and
science.
Your beloved home-away-from-home, Hale Pohaku, experienced an
invasion of honeybees this summer, following the wet winter and spring
which contributed to an explosion of flowers. At one point, this resulted
in having to vacate building C entirely and having a beekeeper come and
remove the hives, which were nicely stuffed into the double-walls between
rooms (necessitating the removal of portions of walls). One wonders if it
might not be productive to have bee hives located out in the mamane forest
away from the buildings. This is not the first time they have found the
dorms to be nice hive spots, and the hive removal does not result in
having any honey to harvest.
Curiously, the moist first part of the year also caused the
pastureland lower down to become green and lush, yet no cattle were
brought in. The result is tall grass, and perhaps the strategy is to
allow the land to lie fallow and re-seed itself to create a better pasture
for next year.
In the meantime, MKSS appears to be still bent on replacing the
exterior siding of the dorms. Very slowly. This is kind of a Chinese
water torture situation. While they try to do the work in "late
afternoons" (which seem to be defined as after 1 or 2 PM), it is still
noisy at times. They are now working on building B, the largest dorm,
which cannot be entirely vacated. Yet, they do the work every now and
then and with a very small crew (often one person), rather than hiring a
contractor with a large crew and getting this done in a matter of a few
days - even if working only late afternoons. Even though they try to keep
the nearby rooms empty during the times they do work, the noise can still
permeate at times...and I really want to sleep past 2 PM, thank you!
The rare Mauna Kea Silversword plant which bloomed last year (see
previous articles) grew some side shoots from the main plant. These
shoots have also bloomed this year, but with flower spikes only about a
meter high. It will be interesting to see how the plant continues to
grow and change. The tourists are certainly not leaving it alone.
While WFCAM will begin occupying blocks of time on our telescope,
I do hope to see you soon, as we will certainly still be conducting our
usual observing with our suite of instruments in between the WFCAM runs.
We shall still aim to deliver the best observing experience you will run
into on the planet.
Aloha!
Aloha to Dean Shutt
|
|
Dean Shutt (right) with Tim Chuter
and Andy Adamson (left and centre) on his last day at the JAC.
|
Dean Shutt, the JAC Chief Engineer, retired at the end of July 2004. Dean
was with the JAC for four years, in which time his energy and enthusiasm
for UKIRT have been demonstrated repeatedly as we have installed new
instrumentation (Michelle and UIST), and worked through the development
cycle for WFCAM. One of Dean's key responsibilities was safety - of staff,
visitors and the telescopes; the most obvious aspect of this from the
point of view of visiting observers was the implementation of the safety
briefings which observers are now routinely given before leaving for the
summit. The JAC's safety record over the past few years has been second to
none on the mountain. This is just one aspect of Dean's dedication to the
JAC which was repeatedly demonstrated and recognized by all who worked
with him.
Dean and Laura will be moving to Oregon later this year. We wish them all
the best and a happy time in the workshop they are planning to build!
UNITED KINGDOM INFRARED TELESCOPE
Newsletter
Issue 15, Autumn 2004
|