UKIRT Annual Report 1995 and 1996
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
1995 AND 1996
6. UKIRT Upgrades
6.7. Dome Floor Insulation
The final element of the Upgrades Programme, which has not progressed
beyond the planning stage as yet, is the project to insulate the dome
floor. This is needed to reduce the warming of the dome air at night by
the heat absorbed by the concrete floor during the day. At present
a detailed proposal exists to equip the dome with a false-floor in the
form of a layer of hard isocyanurate foam, reinforced with heavy-duty
fibre-board and surfaced with resistant rubber tiles.
Procurement and installation are expected to take place in 1998.
|