|
UKIRT Annual Report 1997
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
1997
3.4. Instruments
3.4.1. CGS3 (10 and 20
m 32-channel low resolution
spectrometer)
CGS3 was used successfully on approximately 24 nights during the year.
Despite the successful demonstration of MICS at UKIRT (see below), some
demand for CGS3 remains because of its 20 m capability, which MICS does not
possess. There has been no further development work on CGS3 and none is
envisaged before its retirement, which is anticipated to be at the end of
1998.
3.4.2. CGS4 (1-5
m multiple resolution spectrometer
with 256 256 array)
Apart from the first part of the year and a brief period in December
1997, CGS4 operated highly successfully in all modes and continued to be
the subject of considerable praise by a number of visiting astronomers.
The slit rotation mechanism, which had hampered observations during the
latter part of 1996 and continued to inconvenience or limit some kinds
of observations in early 1997, was fixed in April 1997 and has operated
very well since then. For the most part other faults with the instrument
were minor and were addressed quickly. However in late 1997 a period of
intermittently unstable array performance culminated in a failure of one
of the four readout channels in December. An emergency warm-up of the
dewar was required to repair the fault, which turned out to be a broken
resistor on the array circuit board. The schedule was rearranged so that
no visitors lost observing time. Semester 97B saw the first use of the
long camera, which provides a pixel scale better suited for UKIRT's
improved image quality, and a 40 l/mm grating (replacing the workhorse
75 l/mm grating) that allows moderate resolution and wide wavelength
coverage with the new pixel scale.
3.4.3. IRCAM3 (1-5
m camera with
256 256 array)
IRCAM3 operated remarkably smoothly, with no major faults occurring
during the year and the performance of the instrument benefited from the
improved image quality delivered by the telescope, but the coarse pixel
scale (0.28 arcseconds/pixel) of the instrument led to increasing use of
the 2X magnifier by the end of the year. The various instrument
accessories, and the unusual data acquisition mode
snapshot, were employed successfully during the year. The total amount
of time lost during 1997 was approximately 10 hours and was due mostly
to communications breakdowns between the instrument and the VAX data
acquisition software. Two observing programmes which used the snapshot
mode with the 5X magnifier suffered from lower than expected
sensitivity. This was later determined to be a feature of the
magnifier, which originally was intended for image quality tests and
which does not decrease the background per pixel when installed. Correct
information concerning this is now on the IRCAM3 web pages.
Design work began on a modification to IRCAM3 to convert its plate scale
to a smaller one that is more appropriate for imaging in the thermal
infrared. Thermal IR imaging is expected to become the primary function
of IRCAM3 once the new 1024 1024
UKIRT Fast Track Imager (UFTI) is
delivered in 1998.
3.4.4. Accessories
Both the K band Fabry-Perot (FP) interferometer and IRPOL2 were used
several times during 1997 and both performed excellently. Improved
software was installed to considerably speed up the FP alignment process.
The polarimetry data reduction software was enhanced in several respects.
3.4.5. Visitor Instruments
An integral field unit (IFU) for the J and H bands, designed and built at
the University of Durham, was commissioned at UKIRT with CGS4 in Semester
97A. The unit has 72 fibres and reformats a 4 6
patch of sky
onto the slit of CGS4. Poor weather prohibited accurate information from
being obtained but the performance of the IFU was promising. Additional
commissioning time for the instrument has been scheduled early in Semester
98A.
The MPIA thermal IR camera, MAX, had two very successful one-week runs at
UKIRT, a third in which poor weather resulted in the observers using CGS4
instead, and another during which a number of technical problems led to
considerable lost time. MIRAS, an Australian mid-infrared camera equipped
with a polarimeter had a moderately successful observing run in July 1997,
although electronic pickup noticeably reduced its sensitivity.
An agreement was reached whereby MICS, a Japanese prototype
camera/spectrometer for 8-13 m, is to
be offered to UKIRT observers
with minimal restrictions in exchange for the opportunity for Japanese
astronomers to gain experience in observing at thermal IR wavelengths.
Tests of MICS were performed in engineering time at UKIRT in March and
September 1997. In March the performance of the instrument was poor and it
was judged unsuitable for scientific use at UKIRT. The September test
showed that most of the problems with the instrument had been addressed
and that its performance was much better. The instrument was to be made
available to the community beginning in Semester 98A.
Commissioning and science time for COHSI, a revolutionary fibre-optic J and
H band spectrometer built at Cambridge University, which rejects OH line
emission, was rescheduled for semester 98A.
|