Joint Astronomy Centre
Show document only
JAC Home
JCMT
UKIRT
About the JAC
Contact Info
OMP
Outreach
Seminars
Staff-only Wiki
Weather
Web Cameras
____________________

UKIDSS Observing
Other Observing
Schedule
Applying For Time
Get UKIDSS Data
Get non-UKIDSS Data
Data Reduction
Acknowledge Us
Telescope
WFCAM
Cassegrain
Technical Reference
JAC Safety Manual
TSS Priority Page
UKIRT Annual Report 1999



THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
1999

3.6. Other Developments

3.6.1. Service Observing

Service observing is carried out on approximately nine nights per semester, a level agreed with the PATT UKIRT TAG. An analysis covering the period May 1999 - May 2000 produces the following results: during this 12-month period, 60 service applications were received. For a nominal 2.5 hours/project this amounts to 150 hours or about 15 nights. Given that not all nights are clear, the normal allocation is considered appropriate. Proposals were received from all over the world, from mainland USA (8 proposals), Germany (6), UK (35), India, Greece, Netherlands, France, Italy (1 each). 34 projects were deemed completed and at least some data were taken for another 23. Common themes included: brown dwarfs, often confirming SDSS candidates; monitoring of Supernovae; binaries and transients, especially X-ray transients; multiwavelength campaigns involving spacecraft; recovery of PATT projects via one-off calibrations or missing fields. Publications arise from the Service programme at a slightly higher rate than from normal UKIRT operations. This reflects the limited nature of the programmes carried out, the fact that in many cases the data are reduced by UKIRT staff, and the fact that many service programmes are key to completing papers based on work carried out at UKIRT and elsewhere.

3.6.2. Reactive Scheduling

In semester 99A, 10 nights were allocated for reactive recovery of ``starred'' projects (U/99A/17 Eales and U/99A/61 Cotter), for an ongoing commitment to the ``starred'' LT46 project to monitor Sakurai's object, and to compensate projects over-ridden by GRBs etc. Approximately half this time was required to complete the two in-semester programmes. The remainder was distributed between overridden programmes, targets of opportunity, UFTI training and engineering. In semester 99B 12 nights were allocated for reactive recovery, 10 of which were allocated to ``starred'' projects (U/99B/08 Eales and U/99B/49 Hodgkin) and the LT46 project. The two new programmes required considerable reactive recovery; these observations were carried out by T.Kerr, T.Hawarden and C.Davis. The effectiveness of the reactive scheme is clearly demonstrated by the completion statistics on these two programmes: given the original scheduled time only, Eales' programme would have achieved only 17% completion; by the end of the semester, it was 77% complete. Similarly Hodgkin's proposal was 100% complete by the end of the semester while classically it would have been only 36% complete.

3.6.3. Flexible Scheduling

Two experiments investigating the requirements of flexible scheduling on the basis of weather conditions were carried out in semester 1999B. The objective was to meet the needs of relatively demanding (better than 0.5" seeing) imaging programmes by flexing them against observations with less stringent requirements. In one case the ``most demanding'' observer was present and was expected to fall back to a less demanding project if required. In the other case the reverse situation applied. In one case the alternate project was a mixture of observations drawn from the service-observing queue, in the other it was a self-contained project of basically similar observations. For each run the absent PI was asked to supply a detailed observing plan for review by the actual observer. In addition a set of guidelines was established, setting out the rules for switching between projects and determining how any time lost would be charged to each project. Overall the experiment was successful: the two projects requiring good seeing obtained more data in appropriate conditions than they would have done in a traditional fixed schedule. The flexing process also allowed a better match of observing windows with target RAs for all the projects involved. A number of lessons were learned which must be applied to further developments in this area. The JAC overhead was about 50-60% greater than would have been required to support a single observer who made their own target lists, wrote their own tapes etc. To mitigate this overhead through use of software tools will be a key to any future flexible scheduling of UKIRT.

3.6.4. Newsletter

The Newsletter was published twice, preceding PATT deadlines, edited by C. Davis.

Contact: Sandy Leggett. Updated: Fri Oct 15 14:13:47 HST 2004

Return to top ^