|
UKIRT Annual Report 2000
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2000
3.3. Telescope and Enclosure
3.3.1. Telescope and Dome Control
The telescope systems performed very reliably throughout
2000. Counter-weighting provisions in preparation for Michelle were
installed in the summer. The dome ventilation system (DVS) worked
reliably through this year.
Due to staff shortages, work to fix the dome seals and skirts could not be
accommodated this financial year and was deferred until 2001/2002.
3.3.2. Emissivity
Emissivity is routinely measured at the end of each night using CGS4.
Work on these measurements revealed that averaging
over a narrow band of echelle data produced an overestimated
emissivity. By extracting the complete spectrum, a
region of minimal atmospheric emissivity was identified. A reduction in the
inferred emissivity resulted; emissivity was measured as below 10%,
close to the theoretical minimum for the current telescope components.
Some features of the relationship between emissivity and photometric
zeropoints imply that an emissivity plateau exists.
The calibration between the emissivity measured with the 150 l/mm grating
and with the echelle was determined when the gratings were switched
in early summer 2000. In a further attempt to understand the UKIRT
emissivity, the TRISPEC aluminized patch was used with the 150 l/mm
grating in early 2001 to calibrate measurements taken with the commonly
used float-glass dichroic.
The results were encouraging: the inferred echelle-mode emissivity is 8%,
slightly lower than the prediction of the standard telescope
model. In all but the thermal infrared, there is no advantage to using an
opaque aluminized patch, and whether or not to do so was still under
debate at the end of the year.
To maintain low emissivity and high throughput, dichroics were exchanged
in March when it became clear that the surface had degraded, and the
primary was cleaned in December 2000.
3.3.3. Image Quality
As a result of concerted monitoring of UKIRT's seeing performance, a
number of advances were made in understanding its behaviour as a function
of conditions both inside and outside the observatory. Poor seeing is
correlated with low wind speed; above 5 miles per hour the dome
ventilation system allows the wind to blow away the dome seeing as
demonstrated in
Figure 3 , which shows the seeing disk size as a function of wind speed.
Note the improvement in seeing for windspeeds greater than 5 mph. The seeing
has been interpolated from the focus z values.
In October 2000, primary mirror cooling was attempted for the first time;
early results show that the system is capable of producing
excellent seeing when the flow temperature is suitably regulated relative
to the dome temperature.
Figure 4 shows the dependence of seeing on the temperature difference
between mirror cooling flow and dome air, where the data taken between
7 pm and 9 pm on 11th October 2000. Further work on primary mirror cooling was
delayed by staff shortages into early Semester 01A (by the end of 2000,
significant effort remained to have the flow air track dome temperature
accurately and without intervention).
3.3.4. Telescope Control System
A new interface to the UKIRT telescope control system (TCS) was installed
in time for initial ORAC commissioning in May. The longer-term goal was to
be ready for the JCMT portable telescope control system (PTCS) but in the
interim this system provided the functionality required by
ORAC. Web pages were provided which describe the peakup process under the
new system, and the key case (faint source with very accurate position but
unknown guide star position) was an early demonstrator that the entire
instrument aperture concept works well. The TCS was stable from August
on, with minor changes and improvements to the interim
interface. Work commenced on bringing the PTCS to UKIRT from the
JCMT (this is a requirement for UIST and will also remove our reliance on
VAXes).
3.3.5. User Environment
There were no major changes to the control-room environment. Further large
screens were installed as part of the ORAC commissioning, bringing the
total of 21-inch monitors to eight. Flat screens were under consideration
for ergonomic reasons, but were ruled out due to their poor performance
with Solaris workstations.
|