|
UKIRT Annual Report 2000
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2000
4. Approved Programme: Instrumentation Development
4.1. Michelle
The mid-infrared imager and spectrometer Michelle had made slow progress
in 1999. However in early 2000 progress with several mechanical problems
allowed system testing to begin in earnest at the UKATC.
In April 2000 major improvements in read noise were made by correction of
problems with the warm electronics; deliverable read noise was achieved in
June 2000.
The EDICT controller was used successfully with all the motors in January
2000. The full ORAC spine, including the DR,
became operational in December 2000.
Optical performance underwent several improvements, including
corrections to the distortion of the toroidal mirror in the imager and
correction of flexure-related and vignetting effects; deliverable performance
was achieved in early 2001. A photometer and quantitative model allowed
detection and correction of light leaks, and thermal control of the optics
was improved, such that overall background was at a deliverable level by
October 2000.
Similar steady progress was made with improvements to the mechanical
systems, which had generated many problems. The grating exchange mechanism
underwent extensive modifications before a successful cooldown in October
2000. Flexure problems were systematically attacked but remained an issue
until just before acceptance tests were scheduled in May 2001.
4.2. The UKIRT Imager Spectrometer UIST
UIST's
progress was slowed by software and electronic effort being
drawn to Michelle in the latter's big push to completion.
The optics were in hand by mid-2000, although some
grisms were damaged in shipping. The image slicer components for the Integral
Field Unit were delivered by October 2000 and while some problems
remained, the system offers acceptable performance, with a
33 6 field.
Some testing was achieved with the engineering 512 512 array
and several mechanisms were successfully qualified during 2000. Early in
2001 the first cooldown with the complete opto-mechanical system was achieved.
4.3 Wide-Field Camera (WFCAM) and Large-Scale Surveys
Four large surveys emerged as priorities for WFCAM and science
coordinators were identified. It is expected that the primary surveys
will take seven years to complete if they have access to 30% of available
UKIRT time. A formal Memorandum of Understanding is under discussion with
Subaru for provision of arrays for WFCAM. Design work on the instrument
continued and a test cryostat was set up in 2000.
|