|
UKIRT Annual Report 2001-2002
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2001-2002
3.3. Telescope and Enclosure
3.3.1. Telescope and Dome Control
The telescope performed reasonably well although telescope faults did lead to
lost time during the report period. An RA drive fuse failed in semester 01A,
producing serious tracking problems which took some time to trace. In 01B
corrosion led to a failure of the primary mirror support, followed by a fault
caused by a tip-tilt piezo shorting after winter storm damage. In 2002 the
major telescope faults were jammed mirror covers, a drive failure due to a
broken connection (which lost an entire night) and a failure of the primary
mirror support system leading to oscillations in the mirror (again losing an
entire night). The latter fault was traced to a bad valve, which was
replaced.
In 2002 there were also major dome faults. One occurred after a storm with
exceedingly high winds, which tore the exterior dome cladding. The tear was
repaired by riveting an aluminium sheet over the broken section. Also, two of
the three dome drives failed, leaving the dome running on one drive only, with
no spare. Modifications to the dome software were made to allow the dome to run
smoothly in this mode, and a replacement system will be installed in September
2003.
Major advances were made in 2001 with the Portable Telescope Control System,
bringing us closer to replacement of the existing system, commonality between
UKIRT and JCMT telescope control, and compatibility with UIST. Also in 2001
the telescope pointing was much improved when the new pointing model was
installed. A new dome tracking routine, running under EPICS, was implemented.
Considerable progress was made with the autoguiding systems. Autofocus mode
was made to automatically offset the "guide telescope" to put the star in
the Shack-Hartmann box, and the fast-guider acquisition mode was
successfully commissioned. The crosshead code was updated in 2002 and the
changes mitigated many of the time-out problems which have been in this system
from its inception.
Cooling of the primary mirror was advanced in engineering in April 2001.
Control was transferred to the control room Allen-Bradley panel; the system
now tracks the dome temperature but further characterization and engineering
work is needed. In 2002 wavefront sensing runs were carried out with both
secondary mirrors, to determine their contribution to the telescope's spherical
aberration; the difference was small and indicated that the primary is the
main contributor. Top-end lab tests showed that the performance of tip-tilt
with the heavier WFCAM secondary will be acceptable.
3.3.2. Emissivity
In the summer of 2001 the emissivity had risen to an unusually high level of
17% (in CGS4 echelle measurements). Dichroics were sent off to Zeiss for
resurfacing; in the meantime the gold-patch dichroic was installed which
resulted in a 5% improvement. Early in 2002, the standard dichroics were
returned from Zeiss but found to be faulty. In 02A dichroics with acceptable
coatings were delivered and installed, leading to an emissivity of 14% when
measured with MICHELLE. This figure is consistent with the long period since
the last aluminizing; after realuminizing in summer 2003 a major improvement is
expected.
3.3.3. Image Quality
Seeing of quarter-arcsecond quality was reported on a number of occasions in
late summer 2001. Statistically there is a clear improvement in the seeing
through the night, suggesting some contribution from mirror seeing, or other
local source; it is also possible that this is site-related, since Subaru has
reported a similar effect. Early in 02A images were elongated after a long
period during which poor weather precluded a quality assurance (QA) night. QA
measurements were obtained as early as possible and the primary mirror support
lookup table corrected.
|