UKIRT Annual Report 2001-2002
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2001-2002
3.5. Computing
In semester 01A the Observatory Management Project (OMP) had a successful
Critical Design Review. The OMP was successfully commissioned in March 2002
with the UKIRT Service programme providing a thorough test of the design
elements common to both UKIRT and JCMT versions of the software. These include
the database structures, the server access mechanisms, the query tool and the
feedback system. The general impression in terms of usability, speed and
reliability was favourable. The OMP was fully commissioned in October 2002.
The infrastructure was thus in place for flexible scheduling to begin in 03A.
The telescope control system was upgraded as described earlier and all machines
that display to the control room at the summit were upgraded, apart from the
data acquisition machine. This last machine remains a Solaris-based system
as the acquisition software has not yet been sufficiently tested under the
Linux operating system. Acquisition and data reduction software for the new
instruments MICHELLE and UIST were developed in 2001 and 2002.
|