|
UKIRT Annual Report 2001-2002
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2001-2002
4. New Instrumentation
4.1. MICHELLE (10-20µm imager and spectrometer)
MICHELLE passed acceptance testing at the UK ATC in May 2001, although some
concerns remained over flexure performance. A strengthening rib was added and
improvements to the grating mountings were identified, which resulted in
repeatable 1 pixel spectral flexure from slit to array. A software look-up
procedure using the translation stage to compensate for this motion was
implemented and proven to work well (observations showed that minimal peaking
up is needed when placing a point source in the slit). Final waveforms were
developed which gave the necessary array performance and efficiencies on
telescope, for all observing modes. MICHELLE would have benefitted from
additional time in the laboratory post-acceptance, but the project cash limit
made this impossible. A request for access to contingency funds was approved
in June 2001 and the closing cost of the project was £6446k, within the
approved total.
After a successful engineering period in Hilo and transfer to the summit, the
cryostat was fitted to UKIRT on 21st August 2001. First light followed on
22nd August, producing excellent images. Whilst the transfer and installation
of the MICHELLE hardware and software to UKIRT went well, some issues were
raised by the compressed timescale. The data reduction recipes had not been
adequately tested, and quite a lot of effort was needed to get them working on
site. It was decided to adopt ORAC3 in conjunction with MICHELLE's arrival,
which increased the number of software bugs in the Observation Manager and
Observing Tool software. An engineering interface was needed for much of the
on-telescope commissioning. The process of integrating chop control software
was completed close to the start of PATT observing. After a seven week
commissioning period, the first PATT MICHELLE run took place on 15th October
2001.
Considering the complexity of this instrument, the MICHELLE fault rate was
remarkably low during 01B, %lt;0.3%. However this disguises the fact that
MICHELLE had to be warmed up in December and was unavailable for three weeks,
during which several MICHELLE runs were scheduled. Backup programmes using
other facility instruments were done instead. The warm-up was required due to
water damage of the hygroscopic window, probably incurred during a major storm
in November, which resulted in large regions of unusably high emissivity. Since
the window is part of the cryostat, to replace it required a full warm-up.
Unfortunately the same problem occurred in 02A, again after a major storm. To
avoid a reoccurence a sacrificial thin window was installed in front of the
main window into the cryostat, which can be swapped quickly without a warm-up,
and dry-gas purging of the entire calibration unit was implemented. The
former required design work and procurement of suitable samples of KBr; the
latter required the acquisition of a large compressor and various installation
work on the telescope. Both were ready by the time of the second down time in
February 2002. Problems were also experienced with the Joule-Thomson (J-T)
cooler and with the optics closed cycle cooler; both cold heads were serviced.
Temperature fluctuations experienced with the J-T cooler were believed to be
due to blockages caused by contaminants in the supply lines, and regular
purgings were implemented. In 02A the fault rate increased to 4% as new modes
were tested and the instrument was heavily used. Lost time was dominated by a
calibration unit fault, fixed by re-engineering a drive shaft nut. Also, a
grating microswitch failed, the J-T cooling system failed, and there were
occasional problems with the EDICT array controller. Fixes or workarounds
were developed. Two gratings (LowQ and MedN2) were incorrectly fitted,
affecting two PATT programmes in 01B and 02A.
The sensitivity of MICHELLE in all modes is up to a factor of two lower than
predicted. Causes were investigated, though hampered by poor weather which
severely restricted engineering and prevented an investigation of
chopping rates. Despite these problems, and the poor weather, MICHELLE was
successfully used for numerous PATT runs and papers are in preparation or
already published.
4.2. UIST (1-5µm imager and spectrometer with 1024x1024 array)
During semester 01A the UIST team at the UK ATC were heavily engaged in making
the instrument's performance acceptable for delivery to the telescope, in
particular in the area of electronics and array control. The read noise was
measured to be 150 electrons, which was within a factor of three of the
expected noise but a factor of ten away from the 15 electrons that can be
achieved with these arrays. Booting the full EDICT system in an operationally
viable manner was also an outstanding issue. Effort for development of the
UIST high level software was made available as team members overlapping with
MICHELLE returned. Integral-field spectroscopy using the IFU is the most
novel mode and the UIST graduate student at the UK ATC worked on the ORAC-DR
recipes required for this mode. Software in general was a critical item, in
particular the interface to the telescope system.
The noise performance could not be brought within acceptable levels in time for
the initially proposed February 2002 delivery. Acceptance tests were delayed to
April 2002, and excluded array performance. The instrument was accepted on
provision that certain essential items were completed before delivery. JAC and
UK ATC staff held detailed discussions of the predicted scientific performance
of the instrument with current noise and agreed a programme of continued
engineering work. Significant improvement in the array performance was made
post-acceptance, using digital averaging techniques combined with multiple
non-destructive read-out. By early 2002 the high-level software for UIST
was largely complete, and the instrument fit within the ORAC environment
including the Observing Tool and Observation Manager. Reduction software for
the imaging and spectroscopy modes were adapted from the other instruments by
JAC staff. ORACDR reduction recipes for the IFU were effectively completed at
the UK ATC. The project closed at £2982k, within the total allocation
of £2984k.
Acceptable noise performance was achieved prior to delivery in August 2002. Six
engineers and scientists from the UK ATC came to the JAC for commissioning,
which began on August 19th. UIST was installed on the telescope in September
2002 and first light was achieved on September 24th 2002. Commissioning took
place over 20 nights between October and December. UIST integrated well with
the telescope and software systems. On-telescope flexure measurements were
acceptable and a UIST-specific pointing model was installed. Cryogenic
performance and image quality is good. All but two of the grisms and one of
the blocking filters performed well; the problem grisms and filter will be
replaced. Thermal readout, the IFU and polarimetry were all successfully
implemented. The most problematical issue with the instrument is the
throughput, which is lower than expected (25% compared to 40%). This is
under investigation.
|