|
UKIRT Annual Report 2001-2002
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2001-2002
5. Instrumentation Development: WFCAM
During semester 2001A the WFCAM team was also working on the VISTA project, and
accordingly the WFCAM project slipped three months. The team focused on
reaching design decisions in several key areas prior to the Preliminary Design
Review (PDR). A 2kx2k IR Array Multiplexer was up and running in the
test cryostat and an SDSU detector controller was selected. Tenders were
issued for optics, detector controllers and the tip-tilt system. The
autoguider design was fixed. Ordering and procurement of the main optics
became the critical path items; the prices submitted by the optics suppliers
were considerably higher than allowed for in the budget, and the lead times
were longer than expected. Ways of reducing both cost and lead time were
negotiated. When the WFCAM PDR was held in November 2001 many major tasks had
been completed: six major optical items had been ordered; the detector
controller specified and acceptance test procedures issued; filter mechanism
parts had been selected and ordered; and secondary mirror tests had been
successfully completed at the JAC.
In April 2002 tests showed that the proposed design for attenuating
interference between the optical CCD guider and the infrared arrays would
work. The formal agreement between National Astronomical Observatory of Japan
(NAOJ) and PPARC, by which NAOJ will provide three Science Grade (SG) arrays,
was signed in June 2002. The first SG array was delivered by Rockwell in March
2002 with a forecast for shipping the remaining arrays to the UK ATC around
October 2002. This date was subsequently revised to February 2003. The SDSU
controller was delayed due to technical problems. A speedier delivery option
for the tertiary was purchased to allow more time for integration and testing
before delivery.
In semester 2002B the first detector controller was delivered and the first SG
array was characterised. Filter arms were cold tested. The vacuum vessel was
delivered to the UK ATC and in February 2003 the first instrument cooldown was
achieved. Optical elements remain critical path items and slippage in
delivery of the corrector plate has delayed telescope commissioning of WFCAM
into 2004. Rockwell have delivered three SG arrays at the time of writing;
integration and testing will commence with the delivered arrays. The project
cost is currently forecast at £4249k which is within the total project
budget, including contingency.
To ensure that the required software is completed on time, the JAC will manage
the Cambridge Astronomical Survey Unit and Wide Field Astronomy Unit at the UK
ATC who are responsible for the pipeline data analysis and science archive,
respectively. The UK ATC will produce an engineering data pipeline for
commissioning the instrument.
|