|
UKIRT Annual Report 2001-2002
THE UNITED KINGDOM INFRARED TELESCOPE
ANNUAL REPORT
2001-2002
6. Longer-Term Plans
6.1. WFCAM Operations and the UKIRT Infrared Deep Sky Survey
Besides normal PATT-sponsored programmes, the UKIRT wide-field camera
(WFCAM) is expected to spend a large amount of time on a major, public,
infrared sky survey. This programme - comprising a heirarchical set of
surveys of differing areas and depths - is being defined by the
UKIRT Infrared Deep Sky Survey (UKIDSS) consortium. The period from
2001 to 2002 was a crucial one in the development of the
surveys. Organizationally, the biggest single advance was the appointment
in late-2001 of Dr. Steve Warren to the position of UKIDSS Survey
Scientist. Dr. Warren's work since that time has centred on coordinating
the production of the survey proposals, short-term planning and
giving input to the pipeline and archive teams in Cambridge and Edinburgh.
Before this appointment, the consortium had produced the second evolution
of the survey proposal, which was put to an external panel in Spring 2001.
The UKIRT Board meeting of May 2001 considered both the proposal and the
panel report. This meeting set an approximate fraction of UKIRT time to be
devoted to WFCAM work (around 60%), and accepted the "legacy" components
in the UKIDSS proposal (the Large-Area Survey, Galactic Plane Survey, and
Galactic Cluster Survey). The consortium was asked to produce revised
plans for the deeper elements (the Deep Extragalactic Survey and Ultradeep
Survey), for separate panel review in advance of the second Board meeting
of 2001. This second panel's report was supportive of the deeper
components' science aims but was concerned that the UKIDSS survey as a
whole should not be allowed to squeeze out work by other survey teams. The
November 2001 Board accepted the revised plan, and approved an operations
plan produced jointly by the JAC and UKIDSS consortium.
Late 2001 saw negotiations over the possible involvement of ESO in the
WFCAM surveys, and ESO access to the resulting datasets. The final
outcome of these negotiations was that the ESO community would gain access
to the reduced WFCAM data in the same way as the UK community, and a copy
of the raw data would be made available to ESO for archiving. ESO
scientists became involved in UKIDSS meetings, and some adjustments to
field centres and priorities resulted.
In 2002, UKIDSS work centred on the production of an initial two-year
plan, requested by the winter 2001 Board; this included an intense period
of discussion within the Deep Extragalactic Survey
group as to which of the many well-studied
fields available would be included in the survey. The two-year plan was
accepted by the UKIRT Board in November 2002; scheduling issues were left
to the observatory and the UKIDSS Survey Scientist.
6.2. AO and the OHANA Project
The
Optical Hawaiian Array for Nanoradian Astronomy project (OHANA, a Hawaiian
word meaning family) aims to link together the optical/infrared telescopes on
Mauna Kea to produce a world-leading interferometer with unsurpassed
resolution. By early 2001, the project
had three identifiable phases: phase I was the production and testing of a
flexible "injector module" which would be used to inject the adaptive optics
(AO) corrected signal from each telescope into a fibre optic cable; phase II
was the first interferometric test over a relatively short baseline such as
that between CFHT and Gemini, and phase III was full interferometry between an
array of telescopes. The project was naturally keen to incorporate UKIRT, since
its position on the south end of the summit ridge would give the array a long
north-south baseline. Funding for OHANA
from the French government was approved through to phase II in 2001. The
science case became public in October 2001.
Initial contact with C. Dainty at Imperial College (ICSTM) suggested that the
required AO system could be relatively cheaply built and installed on UKIRT,
which since the departure of Hokupa'a to Gemini has been without AO. An
exchange of engineering details, and a visit in August 2001 by C. Paterson from
ICSTM, showed that the convenient location of UKIRT's cassegrain focus, and the
availability of the IRCAM platform after the arrival of UIST, made the
installation of any off-the-shelf AO system relatively straightforward. The
May 2001 UKIRT Board meeting was presented with a proposal to carry out the
required work at ICSTM and to allow for the later incorporation of UKIRT into
OHANA. The Board suggested that the proposal should go through the grants line,
but supported the August visit of ICSTM personnel.
By the end of 2001, phase I was coming to an end with the successful production
of the first injection module and a fast infrared camera, and phase II was
under way. The November Board meeting supported the proposal that UKIRT should
be involved, defining OHANA as effectively a "visiting instrument". Contact
with ICSTM continued through the year, though at a reduced level; in August
2002 C. Dainty left ICSTM, but the group remained keen to be involved in this
novel use of off-the-shelf AO.
6.3. Optical Infrared Coordination Network for Astronomy
The
Optical Infrared Coordination Network for Astronomy (OPTICON) programme
is a European Union (EU) research infrastructure network funded from
2000 to 2004 as part of the EU 5th framework programme.
In its submission for continued funding in the
sixth framework programme (EU FP6, from 2004) it has proposed
funding access to medium-sized telescopes via travel grants and
operations funding. The broad goal of this provision is to achieve
Europe-wide coordination in ground-based optical/infrared observational
astronomy facilities. An advanced draft of the OPTICON proposal to EU FP6
was worked on at a meeting in Toulouse in September 2001, at which UKIRT
was represented. The November 2002 Board meeting reviewed UKIRT's
participation in the OPTICON telescope network of medium-sized
telescopes and agreed that the terms were acceptable; UKIRT was formally
asked to make a submission to OPTICON by PPARC in December 2002. This
submission was made in early 2003. The proposal was submitted to the EU in
April 2003 and the results are expected in late summer 2003.
|