3.1. Summary
- In semester 03A UKIRT became flexibly scheduled; the ultimate goal being completion
of high-priority programmes.
- Semester 03A was also the first full semester of common-user use of UIST.
- In June 2003 the primary was realuminised.
- In semester 03B the dome drives were replaced.
- In semester 04A MICHELLE was offered and used in every mode, before being
transferred to Gemini North on long-term loan.
- Preparations for WFCAM ramped up from 2003; in September 2004 WFCAM arrived and
first light took place on October 21st 2004.
|
|