1. The purpose of this FM is to outline the
procedures for the production of the Operating Plan, the issue of
the allocations, outturn forecasting and the production of the
Operating Report. FM 103 describes
the background and timetable for the Planning, Reporting and
Bidding Cycle.
2. The PPARC Operating Plan is based on the PPARC
allocation as announced annually during October by the OST. The
Operating Plan sets out the key objectives and the programme to be
carried out by PPARC in fulfilling its mission and meeting these
objectives.
3. The effective production of the Operating
Plan relies heavily on recognising responsibilities, adhering to
deadlines, and good communication and interaction. Finance Division
Planning and Budgeting (P&B) Group is responsible for the
co-ordination and production of the Operating Plan. The completed
Operating Plan is usually submitted to the OST during the later
part of February each year. In order to meet this deadline it is
necessary for all those participating in the production of the text
and tables to be fully aware of their responsibilities and the
agreed timetable. Following the receipt of instructions for
submission from the OST, the P&B Group produce and circulate a
comprehensive guidance note together with key dates for completion
of the Operating Plan. The Director Programmes is the custodian of the
master copy of the text and P&B Group hold the master copy of
all financial tables. It is therefore important that any amendments
to either text or tables are notified to the appropriate "owners".
The P&B Group is responsible for preparing the Operating Plan
for publication.
4. Responsibility for the production of the
various components of the Operating Plan are allocated as
follows:
Contents
- P&B Group
Summary
- Programmes Directorate
PPARC Mission and Corporate Objectives
- Programmes Directorate
Financial Framework
- Administration Directorate
Research Programme
- Programmes Directorate
Organisational Development and Change
- Administration Directorate
Financial Framework Tables
- Administration Directorate
5. The draft version of the Operating Plan is
approved by Council at its meeting prior to the submission date to
the OST.
6. The reproduction of the Operating Plan,
including the design of the front and back covers, is carried out
in-house by the Joint Reprographics Services (JRS). The P&B
Group liaise with the JRS early in January to ensure a slot is made
available for the work to be carried out within the agreed
timescale. The printing costs are charged to Centre Code AFI for
administration purposes and are covered by the central photocopying
budget held by the Business Administration Group.
7. Once the Operating Plan is complete,
the P&B Group are in a position to commence work on preparation
for the issue of provisional allocations (excluding carry-forward
adjustments) to the Director Programmes, Director Administration, Director
Strategic Planning and Communications and in parallel, the Directors at the UK
ATC,
ING and JAC. The figures used for the provisional allocation are
those appearing in the current Operating Plan under year one. The
provisional allocation text and table form part of the Letters of
Delegation of Authority issued to the Directors by the Chief
Executive during April of each year (FM 101
refers).
8. The text of the Letters of Delegation of
Authority should inform the Directors of the total allocation for
their particular Directorate/Establishment, highlight any
particular issues of note and provide the date by which the first
formal outturn forecast is required by the P&B Group. Directors
are reminded that the expenditure should be monitored carefully and
are advised that appropriate measures should be taken to ensure
that allocations are not exceeded and any potential problems are
brought to the attention of Finance Division as soon as possible.
Directors also sign an annual assurance statement on internal
control (DAASIC) which includes a section on financial control.
9. The allocation table in the Letters
of Delegation of Authority sets out the resources allocated for
each main activity heading for the domestic and international
programmes to be undertaken as well as programme management and
administration, divided between staff and non-staff headings as
appropriate.
10. Directors, in turn, may wish to sub-delegate
some or all of their budget to members of the Directorate. For
Swindon Office it is the responsibility of the P&B Group, in
consultation with the Directors, to prepare the sub-delegation
memoranda and tables for issue to the Swindon Office budget
holders.
11. Provisional allocations do not include
adjustments in respect of over/underspends from the previous
financial year. Adjustments may be made to the provisional
allocations when the end of year reconciliation expenditure
exercise has been completed during May.
12. It is possible that minor inter-allocation
adjustments may be required by the budget holders throughout the
year. These are formally notified to the P&B Group by the
budget holder. The P&B Group make the adjustment, update the
working allocation table held on the PLANET system 'G'
drive and inform the budget holder of the action by means of a
footnote on the appropriate budget holder's report. Establishments
are informed of allocation adjustments by means of a letter or
e-mail together with an updated allocation table.
13. Any adjustment to the overall in-year
allocation figure is announced by the OST as part of the Winter
Supplementary Estimates in September or the Spring Supplementary
Estimates in January.
14. In order for Senior Management to keep
abreast of the overall financial situation, it is essential that
accurate forecasts are submitted to the P&B Group regularly and
on time. Tight cash management demands that all budget holders
produce comprehensive forecasts. The key element of the outturn
report is that it should report the spend to date and forecast
future expenditure on a line-by-line basis.
15. The P&B Group provide budget
holders with their first report early in July each year and monthly
thereafter, usually by the 8th working day of the month.
The first formal outturn forecasts are required by the P&B
Group the second week of July and monthly thereafter, usually by
the 14th working day of the month. A timetable of due
dates is produced for all budget holders and the sites. As
agreed at the PPARC Finance Officers meeting held on 18 November
1998, budget holders at the sites are asked to perform an
in-depth review of their area quarterly for the first nine months
of the financial year and monthly during the final quarter of each
financial year.
16. The P&B Group is responsible for the
production of the top level reports and management charts by
20th of each month for submission to the appropriate
monthly senior management meeting.
17. It should be noted that Treasury
regulations allow for PPARC to carry-forward up to 5% of recurrent
grant-in-aid from one financial year to the next. Of this, up to 2%
may be funds received from the OST and the remaining 3% carried
forward under the End of Year Flexibility scheme. For capital
grant-in-aid, up to £2M or 5% can be carried forward,
provided that it has not been paid out by OST.
18. The final budget holders reports are
produced as soon as the final payments for the year have gone
through the bank and any final journal adjustments made by the
accounting staff. This is usually by the 14th working
day of April. The final budget holders reports and the top level
management reports give the final spend position for the financial
year against the final allocation position.
19. At a meeting between the P&B Group and
the Swindon Office Directors, it is decided against which budgets
the over/underspends are carried forward to the next financial
year. As soon as the carry-forward exercise is complete, revised
allocations (which include the agreed carry-forward figures) are
issued to the Swindon Office Directors for sub-delegation to each
budget holder within their Directorate.
20. The Operating Report is submitted in draft
form to the OST by 30 June each year and a final version by the end of July.
Submission dates are confirmed by the OST annually. The Operating Report compares the Operating Plan
for the previous year against actual performance. The requirement
is to report against both the financial plan and against milestone
targets, recognising that many of the milestone targets in the Operating Plan are for the three year period of the
Spending Review, so it is possible that reporting will be progress
towards a milestone rather than achievement of it.
21. The reproduction of the final version of
the Operating Report follows OST approval and is in the same format
as the Operating Plan adhering to the stipulated timetable.
22. The Operating Report
is not 'approved' by Council, but copies of the final bound report are provided
to each member.
23. Any queries concerning the content
or interpretation of this FM should be referred to Paul Blackford,
Head Planning and Budgeting, Finance Division, Swindon Office, tel:
01793 442062, e-mail:
paul.blackford@pparc.ac.uk .
Paul Blackford
Head, Planning and Budgeting
Finance Division, PPARC