2.
This FM sets out the requirements for economic appraisal of large projects
within PPARC and describes good practice in appraising cases for the approval of
smaller projects. Further guidance can be found in Government Accounting Chapter
29 and the HM Treasury publication "Appraisal & Evaluation in Central
Government" (The Green Book). The Green Book gives comprehensive guidance -
Chapter 1 is a general introduction; Chapters 2 and 3 provide background for
those who are new or have limited experience in this subject; Chapter 4 provides
advice on technical matters and is aimed at those who undertake
appraisal/evaluations. The guidance contained in this FM is intended as an
overview, and detailed guidance should be sought from The Green Book, a copy of
which is held in PPARC Finance Division, Swindon Office. (See Appendix A for
information on how to obtain copies.) FM 303: Costing and Charging is also
relevant.
3.
Economic appraisal, also known as investment or option appraisal, is concerned
with looking for the best value for money from the use of resources. The
objective is to place the consideration of costs and benefits on a common basis
in order that valid comparisons can be made between options.
4. In
any proposal to commit resources to a project there are always at least two
options, one being the "do nothing/do minimum" option, which in itself
may have significant cost implications; the other being the spending of
significant sums in order to achieve a particular objective. There may be
several further options as to how this might be done, for example: different
levels of specification; different timescales; different locations; and purchase
or lease. Although this FM is concerned mainly with the appraisal of capital
projects, many of the principles can be applied equally well to research or
development projects.
5. All
cases to commit sums of £100k, or more, to capital projects should be
accompanied by a full statement of the economic appraisal. This requirement also
applies to cases to enter into lease, rental or hire agreements where the total
cost over the period of such an agreement is £100k or more. It applies equally
to single purchases of £100k or more and a collection of purchases intended to
provide a single facility of that value.
6.
This FM should be applied as far as possible to all agreements to commit PPARC
to major expenditure. Where decisions are made to build an instrument at an HEI
it can be accepted that the appraisal has, by implication, been done within the
peer review process. However, where the work is likely to be carried out within
PPARC, ie at an Establishment, then a fully documented economic appraisal should
be carried out at the same time as the peer review process, to document that
this is the most cost effective way in which to proceed. PPARC should be able to
show that all options have been evaluated and the chosen way forward represents
the best long term value.
7.
The same principles apply to the appraisal of cases to make lower value
purchases, both capital and recurrent, and these principles should be considered
when completing requisitions although it is not necessary to submit a full
statement of economic appraisal with the requisition.
8.
The economic appraisal forms part of the case for proceeding with a project, and
so should be retained on the official files for later review and inspection.
9. There
are nine basic steps to be carried out in an appraisal during the course of a
project with the first seven being required before the project is started. These
are:
1. Planning and project specification
2. Formulation of objectives
3. Generation of options
4. Selection of options
5. Appraisal of options
6. Presentation of results
7. Project approval
8. Monitoring and performance measurement
9. Post project evaluation and feedback.
10. This
part of the appraisal should set out the relationship of the capital project to
the strategic plans and aims of the organisation. How will it contribute to the
achievement of objectives within the area of science concerned? What are the
specific areas of work which will benefit from this expenditure? Does the
proposal have the support, at least in principle, of local senior management?
11.
On occasions the need for capital expenditure will have been generated by a
particular event rather than as the result of following a particular plan. For
example, buildings could be damaged by bad weather or equipment damaged by fire
or vandalism. Nevertheless, the case for repairing the building or replacing the
equipment must still be made in the context of the aims and objectives of the
scientific programmes being supported. The question must be asked at this stage,
and answered, about whether it is justifiable to replace equipment lost, or can
the work proceed in other ways and the money spent more beneficially in some
other area.
12. The
objectives supporting the case for capital expenditure must be clearly stated.
They should be ends not means; specific not general; few and not overly complex;
measurable and verifiable; and realistic within the resources likely to be
available.
13.
The objectives must be consistent with PPARC’s plans and policies as well as
legislation. For example, a case to purchase a large piece of equipment must
consider health, safety and environmental issues. Can it be accommodated
satisfactorily within existing buildings or other facilities?
14.
In formulating the objectives underlying the case for a capital project,
conflicts may arise. These could be related to resource constraints, standards
(internal or external), and procedures (internal or external). It is important
that this part of the case makes any such conflicts explicit, so that they can
be considered at the outset, and not later in the project life.
15.
Having set the case in the context of the scientific needs and stated the
objectives of the project, it is necessary to consider the options available. In
the final case presented for approval it is not necessary to present every
conceivable option as some may be capable of rejection at an early stage for
obvious reasons. However, it is necessary to present a sufficient range of
options to demonstrate that the preferred option represents best value for
money.
16.
In considering the range of options it is necessary to ask:
a. What is implied by doing nothing or continuing as before?
b. Could the
operation be ended or scaled down, releasing resources for other use?
c. Could the
operation be of a different size or quality?
d. Could the
project be accelerated, slowed down, or phased differently?
e. Are alternative
locations possible?
f. Are there
different ways of achieving the same objectives?
g. Are there
choices of different levels of initial capital expenditure, and what effect do
these have on lifetime running costs?
h. Are all the
elements of the requirement equally important? Could some be removed to improve
the effectiveness and efficiency of those remaining?
i. Could the operation be
combined with another to advantage?
j. Could all or
part of the operation be contracted out?
17.
For example, a large computer is becoming increasingly costly to maintain and is
failing to meet the current and future scientific needs. The initial list of
options might include:
a. shutting down the computer and discontinuing the service;
b. carrying on with
the same equipment for another two or three years, accepting the higher
maintenance
costs (the "do nothing" option);
c. shutting down
the computer and transferring the service to an external bureau;
d. shutting down
the computer and transferring the services to other PPARC machines;
e. replacing the
equipment in stages over a period of years;
f. replacing the
entire configuration with newly purchased equipment;
g. replacing the
entire configuration with leased equipment.
18. It
may well be possible to think of other options, some of which may be
combinations of the operations a-g listed above. Even seven options are usually
too many to be presented in detail, and in most cases three or four would be
sufficient. Therefore, having established seven options, as in this example, it
is sensible to carry out a crude sift in order to test them against the criteria
upon which a final decision will be based. One technique which may be used is a
simple weighting and ranking exercise. The procedure used is as follows:
a. Write down all criteria which are relevant to the decision
as to which option to proceed with.
b. Exclude those
criteria on which there is no difference between options.
c. Work through the
criteria one by one, rating each option against each criterion on a scale of
100 or 10) points for the preferred option and zero for the least preferred, with
intermediate scores for the relative to the extent to which they meet the criterion.
d. Weight the
criteria according to importance by giving the least important criteria low
weights and the most important high weights, say on a scale of 1 to 3.
e. Multiply the
scores of each option against each criterion by the criterion weighting.
f. Add up the
weighted scores of each option; the one with the highest score is the most
preferred.
g. Test the
sensitivity of this analysis by altering the scores or weightings, particularly
where the numbers are open to doubt or disagreement.
19.
This exercise is best done by a small group of people who can then compare their
conclusions and discuss the relative ranking of options. The likely outcome is
that, in the example in paragraph 17, three or four of the options will be
clearly unacceptable and so can be rejected at this stage, leaving perhaps three
or four options which can be taken forward for more critical appraisal. It
should be noted that up to this stage cost is not the determining factor as to
whether a project should proceed, although it is possible that some options
might be rejected at the crude sift as being unrealistically expensive.
20.
Having short-listed three or four realistic options, with an absolute minimum of
two, it is necessary to carry out a more detailed appraisal of each in order
that the one which represents the best use of resources can be selected. The
factors which need to be considered are:
a. Capital Cost - the estimated capital cost of the option
should be identified, at current prices. For projects spanning more than one
year the annual incidence of expenditure should be forecast. Estimates must
include any special procurement costs, consultants’ fees and VAT, together
with any consequential capital costs such as the alteration of or addition to
existing accommodation and services.
b.
Running Costs - the estimated annual incidence of recurrent costs or annual
changes in recurrent costs should be identified, as should any savings which
will result from the capital investment. These costs or savings should also be
expressed at current prices. Such costs or savings might include staff, power
requirements, maintenance, spares etc.
c.
Benefits - the main improvements and other benefits arising from the
investment should be identified and related to the decision criteria
established earlier (see paragraph 18). Quantitative estimates of the money
values of the benefits, again at current prices, should be made wherever
possible. Any objectives which cannot be achieved in full by each option
should also be identified. Benefits might include the ability to attract
additional repayment work.
d.
Unquantified Benefits - investments in scientific equipment and facilities
often depend on projected benefits which are largely unquantifiable in money
values. These should be identified as far as possible and explained in the
context of the relevant scientific strategy, policies and objectives.
e.
Timing - the timing of the project and the expected benefits must be clear. In
the case of equipment the expected lifetime and length of the requirement
should be given.
f.
Present Value of Costs and Benefits - in order to make a fair comparison
between the cost and benefits of capital investment options, insofar as they
can be quantified in money values, it is necessary to discount these values to
the present day. This allows costs and benefits occurring at different rates
and at different times to be compared in a consistent way. A straightforward
method for doing this is explained in Annex A. Further information can be
found in The Green Book as referred to in the introduction to this FM. It
should be noted that discounting to present values has nothing to do with
inflation. Therefore it should not be confused with the procedure for
estimating costs at current prices and later, if projects are approved,
setting budgets at cash prices after allowing for estimates of future
inflation. This is explained further in paragraph 26.
g.
Uncertainty - the degrees of uncertainty contained in the estimated values of
costs and benefits must be considered. Options may need to be compared using
both pessimistic and optimistic assumptions about values. Does this alter the
rank order of the options?
h.
Project Management - consideration should be given at this stage to the method
by which the capital project is to be managed. If possible, one individual
should be assigned the lead responsibility for project management at this
stage in order that s/he acquires ownership of the project from the outset,
rather than being handed the task later and having to live with the
assumptions about costs, benefits and timescales made by others.
i.
Any other considerations - are there any other significant matters to be taken
into account? Will the project impact on any other area of PPARC? Have all the
genuinely interested parties been consulted? Have all staffing and personnel
issues been considered?
21.
Cases for capital investment projects and purchases costing up to £300k must be
presented to the relevant Establishment Director for approval. Those costing
more than £300k must be presented to the Chief Executive via the Head of
Finance, PPARC, for approval. In some circumstances it may be necessary to spend
money on initial feasibility studies before a case can be put up for approval.
This may be done within existing delegated authorities to approve expenditure,
but the cost must be included in the total project cost when it is submitted for
approval.
22.
The case must state, in a concise way, the outcome of the five steps outlined in
paragraphs 10 to 20 above, highlighting:
a. objectives;
b. options;
c. capital costs, and the availability of funds within cash
planning figures (see para 26);
d. running costs, and the availability of funds from
baseline budgets;
e. benefits;
f. timing;
g. the net present value or cost;
h. uncertainties;
i. any other considerations;
j. management, monitoring and evaluation arrangements (see
paragraphs 30 to 33 below).
23.
Conclusions should be expressed in terms of the option which provides the best
value for money in relation to the objectives, and how this option compares with
the other options.
24.
If the case runs to more than four sides of A4 excluding annexes an executive
summary should be provided.
25. Once
the project is approved it should proceed as quickly as possible. Undue delay
between approval and commencement could give rise to a situation where the
original ranking of options was no longer valid, for example in the case of a
purchase which had to be made in a foreign currency and so was sensitive to
changes in exchange rates.
26.
The economic appraisal will have been done at current prices, which will be
adequate for setting budgets if the project or purchase is to be completed in
the same financial year. Projects spanning more than one financial year must
therefore be re-estimated prior to approval in cash prices, that is the prices
which will actually apply when the bills are paid. Forecasts of future inflation
must be taken into account when establishing such allocations at cash prices
using HM Treasury GDP Deflators, available from PPARC Finance Division, Swindon
Office. In particular cases, such as building works, specialist advice might be
sought from consultants. For example, a capital building project estimated to
cost £1M at 2000/01 prices but spread over three years might require a cash
allocation determined as follows:
£k
FY:
00/01
01/02
02/03
Estimate at
current prices
200
700
100
Index of
forecast inflation
100
105.5
110.5
Cash allocation
200
740
110
This example shows
that the actual cash provision which would need to be made in the planning
figures should be £1.05M.
27.
Once a project has been approved the expectation is that it should be
completed within the cash limited allocation as determined in para 26. If at
any time it appears that a project cannot be completed within the approved
cash limit, it should be submitted for re-approval. (See para 30 FM 101:
Delegated Authority.)
28.
It is acceptable that in the financial planning of a project a reasonable
level of contingency should be built into the budget. This should be explicit
at the approval stage, and should be related to the degree of uncertainty
attached to a particular project. For example, the straightforward purchase of
an item which has a recommended retail price has little uncertainty and a
contingency is unlikely to be justified. Indeed, one might hope to purchase at
a discount. On the other hand, more complex projects such as the construction
of buildings often need contingency sums of the order of 2% to 5%.
Contingencies in excess of 5% imply a high degree of uncertainty and must be
fully justified at the approvals stage. Contingencies must not be used as a
cushion against poor estimation.
29.
Where it proves necessary to submit a case for re-approval, the reasons why
extra costs need to be incurred should be fully explained, and the source of
additional funds identified.
30. The
extent to which it is necessary to establish formal project management
arrangements varies considerably according to the nature of the project. At one
end of the scale a straightforward purchase requires someone to be clearly
responsible for accepting delivery from the supplier, ensuring that the
specification and other contract conditions have been met and, if satisfied,
certifying either the invoice for payment or a Goods Received Note (GRN). At the
other end of the scale, a complex project spanning a significant timescale
requires formal project management arrangements to be put into place, involving
the necessary management, professional and technical expertise. Levels of
delegated authority should be explicitly stated, along with procedures for
monitoring progress, authorising variations to contracts, authorising stage
payments, and taking action should the project fail to achieve its targets.
Project management is covered specifically in FM
302.
31.
It must be clear from the outset of each major capital project:
who has personal
responsibility for the management of the project;
what level of
delegated authority they hold to make decisions within the context of the
project;
from whom they seek
decisions in excess of their delegated authority;
from whom they
obtain professional and technical advice (eg the architect on a building
project or scientific expert for telescope design and build);
what are the
relationships between the project manager and the other members of the
management/consultancy team;
what the divisions
of responsibility are between the contractor, any consultants, and the
client/customer (PPARC as represented by the project manager); and
what is the
programme for the completion of the project, along with intermediate
targets.
32.
Throughout the project it is most important that proper systems of financial
control exist in order that expenditure, commitments and estimates can be
measured against available budgets, and that early warning is given of potential
overspending in order that remedial action can be taken. The prime
responsibility for such financial monitoring and control should rest with the
project manager.
33.
This guidance does not extend to describing the techniques for project
management. Advice on training in project management is available from the
Research Councils’ Joint Training Service.
34. The
aim of evaluating a project after completion is to obtain the maximum benefit to
PPARC of the experience gained in formulating, managing and implementing a
project. It seeks to learn from things which went wrong, not to apportion blame.
It seeks to record and promulgate good practice in order that this can be
applied to future projects.
35.
It is not necessary to carry out post project evaluation on all projects. As a
general rule, all capital projects with a capital value of £5m or more should
be evaluated on completion, and a report prepared and made available to those
who might be involved in such projects in future. Projects of total value in the
range of £1m to £5m will be evaluated by questionnaire (see Annex
B) which
should be completed within three months of the project completion. On occasions
this may result in the need to examine a particular project in greater detail.
Projects with a total cost of less than £1m may be subject to dipstick tests,
usually initiated by PPARC Finance Division, Swindon Office, to evaluate certain
characteristics such as cost or time overruns.
36.
Programmes Directorate, in association with PPARC Finance Division, Swindon
Office, will take the lead in initiating post project evaluations of larger
projects, that is those costing £5m or more, and will agree the terms of
reference of the evaluation with the managers concerned. Such an evaluation
would normally take the following form:
define the
objectives of the evaluation, ie the aspects of the project which are to be
evaluated;
establish the
original aims and objectives of the project (which should be clear from the
original economic appraisal);
measure the
implementation of the project against those aims and objectives; against the
approved budget and timescale; against any other significant parameters;
report the results
of the evaluation; and
promulgate the
results and any recommendations.
37. The
potential value of a post project evaluation will only be realised if all
matters of substance arising are widely disseminated to senior management and
other staff who may be concerned in future with project planning and management.
38. Good
appraisal should lead to better decisions and better value for money. That not
only gives the public, in terms of Science Budget expenditure, or the customer,
in terms of repayment work, better returns for their money, but also leads to
the more effective use of PPARC’s resources, which is of benefit to all its
staff.
39.
Any queries concerning the content or interpretation of this FM should be
referred to Paul Blackford, Planning & Budgeting, PPARC Finance Division,
Swindon Office, tel: 01793 442062, e-mail: paul.blackford@pparc.ac.uk
.
Paul Blackford
Planning & Budgeting
PPARC Finance Division, Swindon Office
1.
This annex describes, in simple terms, the method for calculating the NPV or NPC
of the costs and benefits, or savings, associated with options which are being
appraised. Further information on the method and the underlying economic theory
may be found in Appraisal and Evaluation in Central Government (The Green Book).
2. Most
appraisals have to compare costs and benefits which occur at different times.
Almost all expenditure proposals produce benefits later than costs. The choice
is often between extra expenditure now or extra operating costs in later years.
3.
Normally people prefer to receive cash sooner rather than later and to pay bills
later rather than sooner. This is true even in the absence of inflation. For an
individual this preference might be measured by the real interest rate on money
lent or borrowed. In the public sector too, more weight is given to earlier
rather than later costs and benefits. This is done by applying a discount rate
to the costs and benefits. The discount rate defines how rapidly the value today
of a future real pound sterling falls away through time, just as a real rate of
interest determines how fast the value of a pound sterling invested now will
increase.
4. It
might be argued that because PPARC cannot invest its cash the discount rate
should be zero. That would be wrong. PPARC’s budget, by and large, depends on
the current and future pressures on general public expenditure. The marginal
cost of carrying out a project, as opposed to not carrying it out, is therefore
reflected in the Public Sector Borrowing Requirement (PSBR). This means that
money spent today costs more than money spent at some future date. The current
Government policy is only to borrow centrally only to fund capital investment -
recurrent expenditure being met from revenue, eg taxes.
5.
The discount rate to be used in most PPARC appraisals is 6%. Therefore, taking
the base year as 0, the present value of £1 in year 1 is:
£1
x 1 =
£0.943
1.06
and in year 2:
£1 x 1
= £0.890
1.062
and in year 3:
£1 x 1
= £0.840
1.063
and so on. Discount factors are given in Table 1 to this Annex.
6. The
method can best be illustrated by a simple example. Suppose that a research
programme will generate data which needs to be analysed. Over the seven-year
life of the project/programme it is estimated that it would cost £70k a year to
have these analyses carried out by an external agency. That is Option A. The
other option, B, is to purchase the necessary equipment and carry out the
analyses in house. The equipment, including installation, would cost £200k and
would have a useful life of seven years. Accommodation is available. The
recurrent costs, at current prices, would be £20k a year for software licence
fees, power, maintenance and materials, and 30% of a programmer’s time, say
£10k a year including national insurance and superannuation. Option B generates
no other overheads.
7.
The NPC of Option A would therefore be:
Year
Costs
Discount
Factor
NPC
Cumulative
NPC
0
0
1.000
0
0
1
70
0.943
66
66
2
70
0.890
62
128
3
70
0.840
59
187
4
70
0.792
55
243
5
70
0.747
52
295
6
70
0.705
49
344
7
70
0.665
47
391
Therefore the NPC (or
negative NPV) of Option A is £391k.
8. A
similar calculation can then be carried out for Option B:
Year
Costs
Discount
Factor
NPC
Cumulative
NPC
0
200
1.000
200
200
1
30
0.943
28
228
2
30
0.890
27
255
3
30
0.840
25
280
4
30
0.792
24
304
5
30
0.747
22
326
6
30
0.705
21
348
7
30
0.665
20
367
Therefore the NPC of
Option B is £367k.
9. On
the basis of this appraisal, if all else is equal, Option B would be selected
on the grounds that the NPC was lower. In practice, of course, many other
factors may have arisen during the appraisal which could weight the decision
in the other direction. From an expenditure point of view Option B is cheaper,
at current prices, but in practice it may prove difficult to create the £200k
cash allocation needed in year 0. If PPARC was already spending money on
Option A, then in considering the alternative Option B the two options could
be combined with the cessation of A being shown as savings against B. The net
result would be that Option B would have a NPV of £24k, that is £391k
- £367k.
10.
The costs and benefits of alternative proposals can be properly compared only
if they cover the same time period. For example, if comparing the construction
of a building with a 60 year life with one having a 20 year life, one should
either assume that the latter will be replaced twice during the 60 years, or
alternatively one should show the residual value of the 60 year building as a
benefit at the end of 20 years. In such cases further advice should be sought
from PPARC Finance Division, Swindon Office.
5. Does
the outcome of the project meet the original specification and satisfy the aims
and objectives stated in the original case in all significant respects?
YES/NO
If No, please explain
the significant shortcomings.
6.
Throughout the project was the quality of professional input and advice
satisfactory? Consider here inputs received from external consultants,
Programmes Directorate, Finance Division including Procurement Group etc. If
necessary rate different inputs separately.
Very
satisfactory
[ ]
Fairly
satisfactory
[ ]
Not very
satisfactory [ ]
Unsatisfactory
[ ]
If "Not
very" or "Unsatisfactory", please explain serious shortcomings.
What steps were taken during the project to overcome such shortcomings? Where
appropriate, has any contractual penalty been applied?