Joint Astronomy Centre
Show document only
JAC Home
JCMT
UKIRT
Contact info
JAC Divisions
OMP
Outreach
Seminars
Staff-only Wiki
Weather
Web Cameras
____________________

FM 301

FM 301
Date of issue: 31 October 2000

ECONOMIC APPRAISAL OF PROJECTS IN PPARC

Contents

Paragraph 

Cancellation of previous FM 1
Purpose 2
What is economic appraisal? 3 - 4
When should a full economic appraisal be carried out? 5 - 8
What are the main stages which need to be carried out in conducting an economic appraisal?

9

Project appraisal and approval 9 - 36
    Step 1: Planning and project specification 10 - 11
    Step 2: Formulation of objectives 12 - 14
    Step 3: Generation of options 15 - 17
    Step 4: Selection of options 18 - 19
    Step 5: Appraisal of options 20
    Step 6: Presentation of results 21 - 24
    Step 7: Project approval 25 - 29
    Step 8: Monitoring and performance measurement 30 - 33
    Step 9: Post project evaluation and feedback 34 - 37
Conclusion 38
Queries 39
Net present value or cost (NPV or NPC) Annex A
Post project evaluation questionnaire Annex B
Bibliography Appendix A

CANCELLATION OF THE PREVIOUS FM

1.     This FM replaces PPARC FM 44 dated 1 September 1989 which is hereby cancelled.

PURPOSE

2.     This FM sets out the requirements for economic appraisal of large projects within PPARC and describes good practice in appraising cases for the approval of smaller projects. Further guidance can be found in Government Accounting Chapter 29 and the HM Treasury publication "Appraisal & Evaluation in Central Government" (The Green Book). The Green Book gives comprehensive guidance - Chapter 1 is a general introduction; Chapters 2 and 3 provide background for those who are new or have limited experience in this subject; Chapter 4 provides advice on technical matters and is aimed at those who undertake appraisal/evaluations. The guidance contained in this FM is intended as an overview, and detailed guidance should be sought from The Green Book, a copy of which is held in PPARC Finance Division, Swindon Office. (See Appendix A for information on how to obtain copies.) FM 303: Costing and Charging is also relevant.

INTRODUCTION

What is economic appraisal?

3.    Economic appraisal, also known as investment or option appraisal, is concerned with looking for the best value for money from the use of resources. The objective is to place the consideration of costs and benefits on a common basis in order that valid comparisons can be made between options.

4.    In any proposal to commit resources to a project there are always at least two options, one being the "do nothing/do minimum" option, which in itself may have significant cost implications; the other being the spending of significant sums in order to achieve a particular objective. There may be several further options as to how this might be done, for example: different levels of specification; different timescales; different locations; and purchase or lease. Although this FM is concerned mainly with the appraisal of capital projects, many of the principles can be applied equally well to research or development projects.

When should a full economic appraisal be carried out?

5.    All cases to commit sums of £100k, or more, to capital projects should be accompanied by a full statement of the economic appraisal. This requirement also applies to cases to enter into lease, rental or hire agreements where the total cost over the period of such an agreement is £100k or more. It applies equally to single purchases of £100k or more and a collection of purchases intended to provide a single facility of that value.

6.    This FM should be applied as far as possible to all agreements to commit PPARC to major expenditure. Where decisions are made to build an instrument at an HEI it can be accepted that the appraisal has, by implication, been done within the peer review process. However, where the work is likely to be carried out within PPARC, ie at an Establishment, then a fully documented economic appraisal should be carried out at the same time as the peer review process, to document that this is the most cost effective way in which to proceed. PPARC should be able to show that all options have been evaluated and the chosen way forward represents the best long term value.

7.    The same principles apply to the appraisal of cases to make lower value purchases, both capital and recurrent, and these principles should be considered when completing requisitions although it is not necessary to submit a full statement of economic appraisal with the requisition.

8.    The economic appraisal forms part of the case for proceeding with a project, and so should be retained on the official files for later review and inspection.

What are the main stages which need to be carried out in conducting an economic appraisal?

9.    There are nine basic steps to be carried out in an appraisal during the course of a project with the first seven being required before the project is started. These are:

1.  Planning and project specification
2.  Formulation of objectives
3.  Generation of options
4.  Selection of options
5.  Appraisal of options
6.  Presentation of results
7.  Project approval
8.  Monitoring and performance measurement
9.  Post project evaluation and feedback.

PROJECT APPRAISAL AND APPROVAL

Step 1 - Planning and Project Specification

10.    This part of the appraisal should set out the relationship of the capital project to the strategic plans and aims of the organisation. How will it contribute to the achievement of objectives within the area of science concerned? What are the specific areas of work which will benefit from this expenditure? Does the proposal have the support, at least in principle, of local senior management?

11.    On occasions the need for capital expenditure will have been generated by a particular event rather than as the result of following a particular plan. For example, buildings could be damaged by bad weather or equipment damaged by fire or vandalism. Nevertheless, the case for repairing the building or replacing the equipment must still be made in the context of the aims and objectives of the scientific programmes being supported. The question must be asked at this stage, and answered, about whether it is justifiable to replace equipment lost, or can the work proceed in other ways and the money spent more beneficially in some other area.

Step 2 - Formulation of Objectives

12.    The objectives supporting the case for capital expenditure must be clearly stated. They should be ends not means; specific not general; few and not overly complex; measurable and verifiable; and realistic within the resources likely to be available.

13.    The objectives must be consistent with PPARC’s plans and policies as well as legislation. For example, a case to purchase a large piece of equipment must consider health, safety and environmental issues. Can it be accommodated satisfactorily within existing buildings or other facilities?

14.    In formulating the objectives underlying the case for a capital project, conflicts may arise. These could be related to resource constraints, standards (internal or external), and procedures (internal or external). It is important that this part of the case makes any such conflicts explicit, so that they can be considered at the outset, and not later in the project life.

Step 3 - Generation of Options

15.    Having set the case in the context of the scientific needs and stated the objectives of the project, it is necessary to consider the options available. In the final case presented for approval it is not necessary to present every conceivable option as some may be capable of rejection at an early stage for obvious reasons. However, it is necessary to present a sufficient range of options to demonstrate that the preferred option represents best value for money.

16.    In considering the range of options it is necessary to ask:

        a.    What is implied by doing nothing or continuing as before?
        b.    Could the operation be ended or scaled down, releasing resources for other use?
        c.    Could the operation be of a different size or quality?
        d.    Could the project be accelerated, slowed down, or phased differently?
        e.    Are alternative locations possible?
        f.    Are there different ways of achieving the same objectives?
        g.    Are there choices of different levels of initial capital expenditure, and what effect do these have on lifetime running costs?
        h.    Are all the elements of the requirement equally important? Could some be removed to improve the effectiveness and efficiency of those remaining?
        i.   Could the operation be combined with another to advantage?
        j.    Could all or part of the operation be contracted out?

17.    For example, a large computer is becoming increasingly costly to maintain and is failing to meet the current and future scientific needs. The initial list of options might include:

        a.    shutting down the computer and discontinuing the service;
        b.    carrying on with the same equipment for another two or three years, accepting the higher maintenance
               costs (the "do nothing" option);
        c.    shutting down the computer and transferring the service to an external bureau;
        d.    shutting down the computer and transferring the services to other PPARC machines;
        e.    replacing the equipment in stages over a period of years;
        f.    replacing the entire configuration with newly purchased equipment;
        g.    replacing the entire configuration with leased equipment.

Step 4 - Selection of Options

18.    It may well be possible to think of other options, some of which may be combinations of the operations a-g listed above. Even seven options are usually too many to be presented in detail, and in most cases three or four would be sufficient. Therefore, having established seven options, as in this example, it is sensible to carry out a crude sift in order to test them against the criteria upon which a final decision will be based. One technique which may be used is a simple weighting and ranking exercise. The procedure used is as follows:

        a.    Write down all criteria which are relevant to the decision as to which option to proceed with.
        b.    Exclude those criteria on which there is no difference between options.
        c.    Work through the criteria one by one, rating each option against each criterion on a scale of 100 or 10) points for the preferred option and zero for the least preferred, with intermediate scores for the relative to the extent to which they meet the criterion.
        d.    Weight the criteria according to importance by giving the least important criteria low weights and the most important high weights, say on a scale of 1 to 3.
        e.    Multiply the scores of each option against each criterion by the criterion weighting.
        f.    Add up the weighted scores of each option; the one with the highest score is the most preferred.
        g.    Test the sensitivity of this analysis by altering the scores or weightings, particularly where the numbers are open to doubt or disagreement.

19.    This exercise is best done by a small group of people who can then compare their conclusions and discuss the relative ranking of options. The likely outcome is that, in the example in paragraph 17, three or four of the options will be clearly unacceptable and so can be rejected at this stage, leaving perhaps three or four options which can be taken forward for more critical appraisal. It should be noted that up to this stage cost is not the determining factor as to whether a project should proceed, although it is possible that some options might be rejected at the crude sift as being unrealistically expensive.

Step 5 - Appraisal of Options

20.    Having short-listed three or four realistic options, with an absolute minimum of two, it is necessary to carry out a more detailed appraisal of each in order that the one which represents the best use of resources can be selected. The factors which need to be considered are:

a.    Capital Cost - the estimated capital cost of the option should be identified, at current prices. For projects spanning more than one year the annual incidence of expenditure should be forecast. Estimates must include any special procurement costs, consultants’ fees and VAT, together with any consequential capital costs such as the alteration of or addition to existing accommodation and services.

b.    Running Costs - the estimated annual incidence of recurrent costs or annual changes in recurrent costs should be identified, as should any savings which will result from the capital investment. These costs or savings should also be expressed at current prices. Such costs or savings might include staff, power requirements, maintenance, spares etc.

c.    Benefits - the main improvements and other benefits arising from the investment should be identified and related to the decision criteria established earlier (see paragraph 18). Quantitative estimates of the money values of the benefits, again at current prices, should be made wherever possible. Any objectives which cannot be achieved in full by each option should also be identified. Benefits might include the ability to attract additional repayment work.

d.    Unquantified Benefits - investments in scientific equipment and facilities often depend on projected benefits which are largely unquantifiable in money values. These should be identified as far as possible and explained in the context of the relevant scientific strategy, policies and objectives.

e.    Timing - the timing of the project and the expected benefits must be clear. In the case of equipment the expected lifetime and length of the requirement should be given.

f.    Present Value of Costs and Benefits - in order to make a fair comparison between the cost and benefits of capital investment options, insofar as they can be quantified in money values, it is necessary to discount these values to the present day. This allows costs and benefits occurring at different rates and at different times to be compared in a consistent way. A straightforward method for doing this is explained in Annex A. Further information can be found in The Green Book as referred to in the introduction to this FM. It should be noted that discounting to present values has nothing to do with inflation. Therefore it should not be confused with the procedure for estimating costs at current prices and later, if projects are approved, setting budgets at cash prices after allowing for estimates of future inflation. This is explained further in paragraph 26.

g.    Uncertainty - the degrees of uncertainty contained in the estimated values of costs and benefits must be considered. Options may need to be compared using both pessimistic and optimistic assumptions about values. Does this alter the rank order of the options?

h.    Project Management - consideration should be given at this stage to the method by which the capital project is to be managed. If possible, one individual should be assigned the lead responsibility for project management at this stage in order that s/he acquires ownership of the project from the outset, rather than being handed the task later and having to live with the assumptions about costs, benefits and timescales made by others.

i.    Any other considerations - are there any other significant matters to be taken into account? Will the project impact on any other area of PPARC? Have all the genuinely interested parties been consulted? Have all staffing and personnel issues been considered?

Step 6 - Presentation of Results

21.    Cases for capital investment projects and purchases costing up to £300k must be presented to the relevant Establishment Director for approval. Those costing more than £300k must be presented to the Chief Executive via the Head of Finance, PPARC, for approval. In some circumstances it may be necessary to spend money on initial feasibility studies before a case can be put up for approval. This may be done within existing delegated authorities to approve expenditure, but the cost must be included in the total project cost when it is submitted for approval.

22.    The case must state, in a concise way, the outcome of the five steps outlined in paragraphs 10 to 20 above, highlighting:


a.    objectives;
b.    options;
c.    capital costs, and the availability of funds within cash planning figures (see para 26);
d.    running costs, and the availability of funds from baseline budgets;
e.    benefits;
f.    timing;
g.    the net present value or cost;
h.    uncertainties;
i.    any other considerations;
j.    management, monitoring and evaluation arrangements (see paragraphs 30 to 33 below).
23.    Conclusions should be expressed in terms of the option which provides the best value for money in relation to the objectives, and how this option compares with the other options.

24.    If the case runs to more than four sides of A4 excluding annexes an executive summary should be provided.

Step 7 - Project Approval

25.    Once the project is approved it should proceed as quickly as possible. Undue delay between approval and commencement could give rise to a situation where the original ranking of options was no longer valid, for example in the case of a purchase which had to be made in a foreign currency and so was sensitive to changes in exchange rates.

26.    The economic appraisal will have been done at current prices, which will be adequate for setting budgets if the project or purchase is to be completed in the same financial year. Projects spanning more than one financial year must therefore be re-estimated prior to approval in cash prices, that is the prices which will actually apply when the bills are paid. Forecasts of future inflation must be taken into account when establishing such allocations at cash prices using HM Treasury GDP Deflators, available from PPARC Finance Division, Swindon Office. In particular cases, such as building works, specialist advice might be sought from consultants. For example, a capital building project estimated to cost £1M at 2000/01 prices but spread over three years might require a cash allocation determined as follows:

     

    £k

    FY:

    00/01

    01/02

    02/03

    Estimate at current prices

    200

    700

    100

    Index of forecast inflation

    100

    105.5

    110.5

    Cash allocation

    200

    740

    110

    This example shows that the actual cash provision which would need to be made in the planning figures should be £1.05M.

27.    Once a project has been approved the expectation is that it should be completed within the cash limited allocation as determined in para 26. If at any time it appears that a project cannot be completed within the approved cash limit, it should be submitted for re-approval. (See para 30 FM 101: Delegated Authority.)

28.    It is acceptable that in the financial planning of a project a reasonable level of contingency should be built into the budget. This should be explicit at the approval stage, and should be related to the degree of uncertainty attached to a particular project. For example, the straightforward purchase of an item which has a recommended retail price has little uncertainty and a contingency is unlikely to be justified. Indeed, one might hope to purchase at a discount. On the other hand, more complex projects such as the construction of buildings often need contingency sums of the order of 2% to 5%. Contingencies in excess of 5% imply a high degree of uncertainty and must be fully justified at the approvals stage. Contingencies must not be used as a cushion against poor estimation.

29.    Where it proves necessary to submit a case for re-approval, the reasons why extra costs need to be incurred should be fully explained, and the source of additional funds identified.

Step 8 - Monitoring and performance measurement

30.    The extent to which it is necessary to establish formal project management arrangements varies considerably according to the nature of the project. At one end of the scale a straightforward purchase requires someone to be clearly responsible for accepting delivery from the supplier, ensuring that the specification and other contract conditions have been met and, if satisfied, certifying either the invoice for payment or a Goods Received Note (GRN). At the other end of the scale, a complex project spanning a significant timescale requires formal project management arrangements to be put into place, involving the necessary management, professional and technical expertise. Levels of delegated authority should be explicitly stated, along with procedures for monitoring progress, authorising variations to contracts, authorising stage payments, and taking action should the project fail to achieve its targets. Project management is covered specifically in FM 302.

31.    It must be clear from the outset of each major capital project:

  • who has personal responsibility for the management of the project;
  • what level of delegated authority they hold to make decisions within the context of the project;
  • from whom they seek decisions in excess of their delegated authority;
  • from whom they obtain professional and technical advice (eg the architect on a building project or scientific expert for telescope design and build);
  • what are the relationships between the project manager and the other members of the management/consultancy team;
  • what the divisions of responsibility are between the contractor, any consultants, and the client/customer (PPARC as represented by the project manager); and
  • what is the programme for the completion of the project, along with intermediate targets.
32.    Throughout the project it is most important that proper systems of financial control exist in order that expenditure, commitments and estimates can be measured against available budgets, and that early warning is given of potential overspending in order that remedial action can be taken. The prime responsibility for such financial monitoring and control should rest with the project manager.

33.    This guidance does not extend to describing the techniques for project management. Advice on training in project management is available from the Research Councils’ Joint Training Service.

Step 9 - Post project evaluation and feedback

34.    The aim of evaluating a project after completion is to obtain the maximum benefit to PPARC of the experience gained in formulating, managing and implementing a project. It seeks to learn from things which went wrong, not to apportion blame. It seeks to record and promulgate good practice in order that this can be applied to future projects.

35.    It is not necessary to carry out post project evaluation on all projects. As a general rule, all capital projects with a capital value of £5m or more should be evaluated on completion, and a report prepared and made available to those who might be involved in such projects in future. Projects of total value in the range of £1m to £5m will be evaluated by questionnaire (see Annex B) which should be completed within three months of the project completion. On occasions this may result in the need to examine a particular project in greater detail. Projects with a total cost of less than £1m may be subject to dipstick tests, usually initiated by PPARC Finance Division, Swindon Office, to evaluate certain characteristics such as cost or time overruns.

36.    Programmes Directorate, in association with PPARC Finance Division, Swindon Office, will take the lead in initiating post project evaluations of larger projects, that is those costing £5m or more, and will agree the terms of reference of the evaluation with the managers concerned. Such an evaluation would normally take the following form:

  • define the objectives of the evaluation, ie the aspects of the project which are to be evaluated;
  • establish the original aims and objectives of the project (which should be clear from the original economic appraisal);
  • measure the implementation of the project against those aims and objectives; against the approved budget and timescale; against any other significant parameters;
  • report the results of the evaluation; and
  • promulgate the results and any recommendations.
37.    The potential value of a post project evaluation will only be realised if all matters of substance arising are widely disseminated to senior management and other staff who may be concerned in future with project planning and management.

CONCLUSION

38.    Good appraisal should lead to better decisions and better value for money. That not only gives the public, in terms of Science Budget expenditure, or the customer, in terms of repayment work, better returns for their money, but also leads to the more effective use of PPARC’s resources, which is of benefit to all its staff.

QUERIES

39.    Any queries concerning the content or interpretation of this FM should be referred to Paul Blackford, Planning & Budgeting, PPARC Finance Division, Swindon Office, tel: 01793 442062, e-mail: paul.blackford@pparc.ac.uk .

 

Paul Blackford
Planning & Budgeting
PPARC Finance Division, Swindon Office

 

Annex A to FM 301

NET PRESENT VALUE OR COST (NPV OR NPC)

1.     This annex describes, in simple terms, the method for calculating the NPV or NPC of the costs and benefits, or savings, associated with options which are being appraised. Further information on the method and the underlying economic theory may be found in Appraisal and Evaluation in Central Government (The Green Book).

2.    Most appraisals have to compare costs and benefits which occur at different times. Almost all expenditure proposals produce benefits later than costs. The choice is often between extra expenditure now or extra operating costs in later years.

3.    Normally people prefer to receive cash sooner rather than later and to pay bills later rather than sooner. This is true even in the absence of inflation. For an individual this preference might be measured by the real interest rate on money lent or borrowed. In the public sector too, more weight is given to earlier rather than later costs and benefits. This is done by applying a discount rate to the costs and benefits. The discount rate defines how rapidly the value today of a future real pound sterling falls away through time, just as a real rate of interest determines how fast the value of a pound sterling invested now will increase.

4.    It might be argued that because PPARC cannot invest its cash the discount rate should be zero. That would be wrong. PPARC’s budget, by and large, depends on the current and future pressures on general public expenditure. The marginal cost of carrying out a project, as opposed to not carrying it out, is therefore reflected in the Public Sector Borrowing Requirement (PSBR). This means that money spent today costs more than money spent at some future date. The current Government policy is only to borrow centrally only to fund capital investment - recurrent expenditure being met from revenue, eg taxes.

5.    The discount rate to be used in most PPARC appraisals is 6%. Therefore, taking the base year as 0, the present value of £1 in year 1 is:

    £1   x    1       =   £0.943
              1.06
    and in year 2:
    £1   x    1        =   £0.890
              1.062
    and in year 3:
    £1   x     1       =   £0.840
               1.063
    and so on. Discount factors are given in Table 1 to this Annex.

6.    The method can best be illustrated by a simple example. Suppose that a research programme will generate data which needs to be analysed. Over the seven-year life of the project/programme it is estimated that it would cost £70k a year to have these analyses carried out by an external agency. That is Option A. The other option, B, is to purchase the necessary equipment and carry out the analyses in house. The equipment, including installation, would cost £200k and would have a useful life of seven years. Accommodation is available. The recurrent costs, at current prices, would be £20k a year for software licence fees, power, maintenance and materials, and 30% of a programmer’s time, say £10k a year including national insurance and superannuation. Option B generates no other overheads.

7.    The NPC of Option A would therefore be:

    Year

    Costs

    Discount Factor

    NPC

    Cumulative NPC

    0

    0

    1.000

    0

    0

    1

    70

    0.943

    66

    66

    2

    70

    0.890

    62

    128

    3

    70

    0.840

    59

    187

    4

    70

    0.792

    55

    243

    5

    70

    0.747

    52

    295

    6

    70

    0.705

    49

    344

    7

    70

    0.665

    47

    391

    Therefore the NPC (or negative NPV) of Option A is £391k.

8.    A similar calculation can then be carried out for Option B:

    Year

    Costs

    Discount Factor

    NPC

    Cumulative NPC

    0

    200

    1.000

    200

    200

    1

    30

    0.943

    28

    228

    2

    30

    0.890

    27

    255

    3

    30

    0.840

    25

    280

    4

    30

    0.792

    24

    304

    5

    30

    0.747

    22

    326

    6

    30

    0.705

    21

    348

    7

    30

    0.665

    20

    367

    Therefore the NPC of Option B is £367k.

9.    On the basis of this appraisal, if all else is equal, Option B would be selected on the grounds that the NPC was lower. In practice, of course, many other factors may have arisen during the appraisal which could weight the decision in the other direction. From an expenditure point of view Option B is cheaper, at current prices, but in practice it may prove difficult to create the £200k cash allocation needed in year 0. If PPARC was already spending money on Option A, then in considering the alternative Option B the two options could be combined with the cessation of A being shown as savings against B. The net result would be that Option B would have a NPV of £24k, that is £391k - £367k.

10.    The costs and benefits of alternative proposals can be properly compared only if they cover the same time period. For example, if comparing the construction of a building with a 60 year life with one having a 20 year life, one should either assume that the latter will be replaced twice during the 60 years, or alternatively one should show the residual value of the 60 year building as a benefit at the end of 20 years. In such cases further advice should be sought from PPARC Finance Division, Swindon Office.

 

Annex A to FM 301
Table 1

                                PRESENT VALUE OF £1

Year

Discount factor
@ 6%

Discount rate
% @ 6%

1

0.9434

 

2

0.8900

1.8334

3

0.8396

2.6730

4

0.7921

3.4651

5

0.7473

4.2124

6

0.7050

4.9173

7

0.6651

5.5824

8

0.6274

6.2098

9

0.5919

6.8017

10

0.5584

7.3601

     

11

0.5268

7.8869

12

0.4970

8.3838

13

0.4688

8.8527

14

0.4423

9.2950

15

0.4173

9.7122

16

0.3936

10.1059

17

0.3714

10.4773

18

0.3503

10.8276

19

0.3305

11.1581

20

0.3118

11.4699

     

21

0.2942

11.7641

22

0.2775

12.0416

23

0.2618

12.3034

24

0.2470

12.5504

25

0.2330

12.7834

 

Annex B to FM 301

PARTICLE PHYSICS AND ASTRONOMY RESEARCH COUNCIL

POST PROJECT EVALUATION QUESTIONNAIRE

__________________________________________________________________________

1.    Project details:

Name of Project _____________________________________________________________

Site _______________________________________________________________________

Approved Budget £k _______________________ Date of approval_____________________

Planned completion date (at time of project approval) _________________________________

Project manager/institute contact _________________________________________________

__________________________________________________________________________

2.    Project Description:

Please give a brief description of the project, together with its aims and objectives.

     

     

     

     

_________________________________________________________________________

3.    Project Outturn:

Was the project completed within the originally approved budget?         YES/NO

If the answer is No, please provide a brief account of the reasons why the project costs exceeded the originally approved budget.

 

 

 

_________________________________________________________________________

4.     Was the project completed within the original time-scale?         YES/NO

If No, please state the main factors which caused target date(s) to be missed.

 

 

 

 

________________________________________________________________________

5.    Does the outcome of the project meet the original specification and satisfy the aims and objectives stated in the original case in all significant respects?

    YES/NO

    If No, please explain the significant shortcomings.

     

     

     

     

________________________________________________________________________

6.    Throughout the project was the quality of professional input and advice satisfactory? Consider here inputs received from external consultants, Programmes Directorate, Finance Division including Procurement Group etc. If necessary rate different inputs separately.

Very satisfactory             [    ]

Fairly satisfactory            [    ]

Not very satisfactory       [    ]

Unsatisfactory                 [    ]

If "Not very" or "Unsatisfactory", please explain serious shortcomings. What steps were taken during the project to overcome such shortcomings? Where appropriate, has any contractual penalty been applied?

 

 

 

 

________________________________________________________________________

7.     If the project was carried out wholly or partly by contractors, was their performance:

Very satisfactory             [    ]

Fairly satisfactory            [    ]

Not very satisfactory       [    ]

Unsatisfactory                 [    ]

If "Not very" or "Unsatisfactory", please explain the major shortcomings, the steps taken to rectify these, and any contractual penalties applied.

 

 

 

 

________________________________________________________________________

8.     Were the overall project management and implementation arrangements satisfactory? 

        YES/NO

If No, what improvements should be made for similar projects in future?

 

 

 

________________________________________________________________________

9.     Please add any general comments which might help in the planning, appraisal and implementation of similar projects in future.

 

 

 

 

_________________________________________________________________________

Signed _____________________________________________ Date __________________

Name (block capitals) ___________________________________________ Grade _______

Job Title __________________________________________________________________

 

Appendix A to FM 301

BIBLIOGRAPHY

Appraisal & Evaluation in Central Government: the Green Book, 1997 ISBN: 011 560034 5
may be purchased direct from:

The Stationery Office
PO Box 276, London SW8 5DT
Telephone orders: 0171873 9090;
Enquiries: 01718730011

or from Stationery Office Bookshops or other accredited agents.

Last updated: 29 June 2001

Contact: Christine Campbell. Updated: Mon Dec 31 10:13:37 HST 2001

Return to top ^