1. This FM is intended to identify the key issues which need to be addressed
by management when considering new major projects (broadly those over £100k,
although many of the principles apply equally to all projects) and should be
read in conjunction with FM 301 (Economic Appraisal of Projects in PPARC).
Project management in PPARC is, where appropriate, to be conducted in line with
the PRINCE (Projects in a Controlled Environment) methodology, which is
summarised at Annex B to this FM. PRINCE sets out a good practice guide to
project management, which is widely used in the public and private sectors and
is endorsed by PPARC. Following PRINCE concepts does not guarantee a successful
project in itself, but puts in place the necessary stages which will limit
failure.
2. This FM covers Major Projects relating to PPARC assets and those relating
to scientific programme projects. As the nature of these projects differ this FM
has been split into two sections; with the first covering major projects
associated with the purchase or maintenance of major PPARC assets, (eg a new
building, computer system, remedial works to existing assets etc), and the
latter scientific programme projects. Delegation limits are detailed in FM
101.
3. Although local variations can apply to this FM, controls and good practice
should be maintained at all times. The summary of PRINCE methodology at Annex B
should be regarded as a guide to the principles concerned. Full training is
needed to obtain a detailed understanding and appreciation of the way this
methodology should be applied within PPARC.
4. Three key points are to be addressed before embarking on a project:
· ensure that there are in place suitable reporting/communication/control
systems and methods;
· identify the management resources required;
· commission those professional services required to implement the project and
obtain a suitable project manager and staff.
5. The need for clear and suitable reporting/communications/control systems
is identified in paragraphs 30 to 33 of FM 301 (Economic Appraisal of Projects
in PPARC). In particular, the need for clearly defined delegated authority is
emphasised. This must be fully documented in letters to those receiving the
delegated authority and must be understood by all parties.
6. The way in which such delegated authority will be exercised is also
important. The granting of such authority should be accompanied by agreement on
the resources necessary to manage the project. It is essential that such
resources are adequate. Where necessary independent advice should be sought.
7. It is also essential that the project management team contains the correct
mix of professional/technical/administration skills and clerical/secretarial
support. It is, however, a matter of judgement as to whether the project manager
(team leader) should be an appropriate professional (eg architect, engineer,
scientist) or an administrator. Either can be successful. The important
consideration is that the person selected should have recent experience of
successfully managing a comparable project, or recent experience of successfully
managing smaller projects and recent project management training. Where in-house
staff are to be appointed as project managers up-to-date training should be
provided. The alternative of contracting or seconding in an experienced project
manager should always be considered and such consideration recorded on the
project files.
8. The following key points should be addressed before embarking on the
detailed design and procurement of a project:
· define the need for the project;
· consult the end-user or customer during preparation;
· identify the best means of meeting the need, where possible establishing the
cost of each option;
· quantify all major value for money risks involved.
9. It is an important principle that the objectives of the project are
clearly stated and that these should be incorporated into the Statement of
Requirement (SoR). The SoR is not a detailed design, but it is the end-users'
specification of objectives which the design should achieve. Where appropriate,
it should include criteria for:
· reliability, including a statement of the environmental conditions and
mission against which such reliability is to be achieved;
· maintainability, including conditions and timescales under which such
maintenance is to be carried out;
· availability, taking account of the levels of reliability and maintainability
required; and
· quality assurance - the standard to be achieved during
construction/manufacture.
10. FM 301 (Economic Appraisal of Projects in PPARC) provides guidance on the
selection and evaluation of options, and the guidance contained therein should
be followed at this stage.
11. The consideration of reliability and maintainability should lead to an
assessment of whole life costs. At this stage as accurate an estimate as
possible should be made of the future annual costs of operating and maintaining
the facility, including the costs of any major mid-life refurbishment or
upgrade. Professional advice should be obtained if necessary. This is an
essential part of the economic appraisal and is also necessary to avoid the
over-commitment of "baseline" allocations.
12. Risk and uncertainty must be considered. In the type of projects normally
managed by PPARC it may or may not be appropriate to conduct statistical
analyses of risk, but it is important to consider and document risk and
uncertainty in a methodical way. For example, what are the risks and
uncertainties which might lead to the project failing to met its objectives, in
full or in part, and failing to be delivered within budget and on time? How will
such risk be allowed for and what contingencies, time and money, might be needed
in the project planning and management?
13. The need for pre-contract feasibility studies should always be
considered, even though this would often require the commitment of funds in
advance of money being allocated for, and might delay the start of, the main
project. Feasibility studies, possibly carried out by expert consultants, can
lead to the early identification of potential difficulties, can clarify the
precise requirements of the project, and so can lead to a better contract.
Adequate time should be allowed for such studies and for recommendations to be
included in the planning process. Even if the project does not eventually
proceed, reasonable expenditure on feasibility work is unlikely to attract
criticism.
14. There are a number of reasons for underestimating during the original
concept to pre-contract stages:
i) lack of experience and knowledge;
ii) reluctance to bid realistically in case the project is not approved;
iii) increasing sophistication as the SoR is developed;
iv) underestimate of risk;
v) poor professional advice;
vi) lack of market benchmarks;
vii) changing market conditions; and
viii) price inflation.
15. Reasons i) to iv) are within the control of those responsible for
directing the project, who should require estimates to be properly constructed
from a zero base, documented as fully as possible, and kept up to date. As
experience shows that original concept/'best guess' estimates are usually
substantial underestimates, a significant contingency should be added at that
stage. As the SoR develops, along with the feasibility and preliminary design
work, the estimate can be refined and the contingency progressively reduced as
uncertainty diminishes. It is important that the project manager establishes a
procedure for identifying changes to estimates and timing, records these and the
reasons and draws them to the attention of management.
16. Reasons v) to viii) are less easy to control or anticipate. Further,
independent advice might be obtainable, for example from another body with
experience of a similar project or by the use of project audit consultancies
(see paragraph 21). Redress for poor professional advice should, as far as
possible, be included in consultancy contracts.
17. Estimates of major project costs are published in the PPARC Operating
Plans, and when these relate to capital expenditure they are detailed in the DTI
Spending Plans and incorporated in the overall capital figures in the annual
Supply Estimates. These planned data are compared to actual performance annually
and significant variations require robust explanations. Major overspends or
project failures could result in the PPARC Accounting Officer (ie the Chief
Executive) being called to appear before a Public Accounts Committee.
18. Necessary professional advice and assistance should be sought and
commissioned. Where consultants are used, the PPARC should:
· decide their role and their relationship with the project manager, other
members of the project management team, other consultants, and the main
contractor and subcontractors;
· select consultants on technical merit, where appropriate drawing up
shortlists and ensuring a consistency of treatment of bids;
· draw up an appropriate agreement with the consultants.
19. The role of consultants may vary from project to project, ranging from
advice and design, through technical supervision, to full project management.
Consultants may complement the in-house team or replace them completely. The
objectives should be to achieve the optimum balance of in-house and bought-in
expertise and resources, and to follow current good practice. PPARC Finance
Division can provide access to guidance on good practice as promulgated by the
Office of Government Commerce (OGC). In any event, the role of consultants
should be clearly defined, in writing, at an early stage, and that role
communicated to all concerned with the project. Likewise, any change in their
role during the course of a project must be put in writing and communicated to
all concerned.
20. The selection of consultants should normally be by competitive tender.
Criteria for evaluating tenders should be established in advance of the receipt
of tenders, recorded and used by the tender board. Standard PPARC procedures for
competitive tendering should be followed.
21. All consultancy contracts for major projects should be drawn up and let
by Contracts staff in accordance with current best practice (OGC and other).
Evidence of the consultants' professional indemnity insurance must be obtained.
22. The use of audit consultants should be considered. Such consultants are
used to evaluate the completeness and validity of the work of the design
consultants, and possibly to comment on other aspects of the project, for
example the management arrangements. Their use is not appropriate to all
projects, but such independent advice can be important where a project is
complex, unusual, or contains a higher than normal degree of risk or
uncertainty.
23.A public sector organisation embarking on a project should:
- select a procurement strategy and decide how it should be administered,
taking account of the amount of input required by the organisation: the greater
the risk, the greater the input required;
- select the contractors best capable of delivering the service and accepting
the defined level of risk;
- aim to make no client changes once a particular design feature has been
decided, such changes are one of the major causes of cost overruns: the
elimination of change should be a prime objective;
- consider, with the advice of consultants and/or others, how the design and
construction phases are to be inter-related and who is to carry them out. Where
there would be a clear advantage in giving the design and construction to the
same contractor, this should be done;
- Ensure that, before a project is submitted for full approval, estimates of
cost and timescales are valid and up-to-date.
24. In selecting the strategy it is important to decide how much direct
control of the design and construction is necessary. Direct control consumes
considerable in-house resources, whereas contracting out consumes much less and
can achieve the same objective, provided the contract is tightly drawn with the
minimum of provisional sums and tough, but fair, liquidated damages payable by
the contractor for late delivery, failure to meet specifications etc. OGC
guidance on good practice should be observed.
25. There should be a strong presumption in favour of selecting contractors
for design and construction by a process of competitive tendering. The selection
process must, at the minimum, confirm with EU public procurement directives, but
in some cases it may be desirable to seek expressions of interest from a wider
field, for example by advertising in the appropriate trade press. In
short-listing contractors to be formally invited to tender for unusual projects,
it is important not to apply criteria which narrow the field too rapidly. For
example, where a special type of experience or expertise is required, potential
tenderers should be asked to explain how they would acquire and mobilise such
experience or expertise. They should then be judged against their responses
rather than being eliminated solely for the lack of a track record of similar
projects. Guidance on competitive tendering is contained in FM 401 and
procurement staff will administer the tendering process within delegated limits.
26. There are two different design and construction philosophies, either of
which can be valid in appropriate circumstances. The first, traditionally used
by PPARC on most projects, is to employ separate contractors for design and
construction. The advantages are that the design leads to a very tight
specification against which a fixed price construction contract can be achieved.
The disadvantages are that re-design work may be required during construction,
and errors in design may lead to additional cost claims from the construction
contractor.
27. The second is to let a single design and construct contract, using the
SoR as the contract specification. The advantage of this strategy is that it
leads naturally to much closer liaison between designer and builder and hence a
better chance of optimum solutions being developed. The disadvantage is that the
client cannot see exactly what is to be built prior to letting the main
contract. This may lead to increased pressure for client changes as the project
proceeds.
28. As a rule of thumb, separate design and construction contracts may offer
the best strategy for unusual, one-off projects, whilst combined design and
construction contracts may be more suitable for projects requiring a high
proportion of industry standard components or which follow closely on other
designs. However, in all projects both strategies must be considered and the
relative merits and drawbacks weighed up and documented before a decision is
made.
29. The greater the separation of project management, design and construction
functions, the more important it is to achieve absolute clarity as to where the
contractual responsibilities lie and the greater the task of ensuring good
communications are maintained between all concerned.
30. When managing the construction phase of a project the following should be
followed:
· draw up contract documents for the construction phase, including general
specifications and documentation of the scope of the work;
· award the construction contract after a review of suitable contractors and
their experience and capability to execute the contract;
· ensure contract conditions are appropriate and suitable.
31. In general, PPARC seeks to use well established forms of contract for
major projects. Even so, weaknesses can arise. When drafting contracts for major
projects, particular attention needs to be paid to:
· whether stage payments should be linked to measured work by the contractor
or to milestone events in the performance of the contract;
· the provisions, where appropriate, covering "availability, reliability
and maintainability" (see also paragraph 8);
· the requirement to specify that the contractor should hold appropriate
quality assurance certification;
· adequate safeguards in respect of sub-contractor liability for defects or
default; and
· contractors', particularly consultants', professional indemnity insurance.
32. In cases where it is not possible to achieve the ideal contractual
position for PPARC, for example because of the relative negotiating strength of
the potential contractor, the consideration of these and other factors should be
properly recorded on registered files.
33. On satisfactory completion of a project the work should be formally
accepted by the project manager. For example, the client might issue a
certificate of practical completion to the contractor. The procedure may vary
from project to project, but it is important that the project is formally
'closed off' by the project management team, and that client and customer
clearly understand the extent of any continuing commitments, for example during
a guarantee period.
34. The project management committee should carry out an evaluation at the
end of the project. The evaluation should measure the success of the project and
define and record the lessons learnt, in order to improve performance on
subsequent projects.
35. Post-project evaluation and feedback is a standard procedure in PPARC
(see FM 301 -Economic Appraisal of Projects in PPARC). This is an important
means of ensuring that lessons are learnt and are retained in the corporate
memory.
36. The evaluation should be carried out soon after project completion whilst
events are still fresh in people's minds. If a maintenance or guarantee period
is involved an interim evaluation should be carried out on practical completion
with a final evaluation at the end of such a period.
37. It is important that these strategies are considered afresh at the start
of each new project and that best advantage is taken of current available
guidance and best practice. Particular attention needs to be paid to the
following aspects:
· resources allocated to project management must be appropriate to the scale
and complexity of the project;
· the delegation and division of authority, both internally and between PPARC
and consultants, must be made clear and agreed in writing;
· project managers must be sufficiently experienced and trained;
· the Statement of Requirements must be clear and unambiguous and must contain
criteria for quality, performance and whole life costs;
· risk assessment must be methodical and well documented;
· formal competitive tendering must be used wherever possible;
· consultancy contracts must establish clearly each consultant's
responsibilities and liabilities;
· the need to use audit consultants must be considered in each project;
· the need for availability, reliability, maintainability and quality
assurances clauses in contracts must always be considered;
· cost estimating, both capital and whole life, must be methodical, based on
sound advice, and well documented.
38. The methodical application of the points identified in the checklist
(Annex A to this FM) to this paper should ensure that future projects are
managed to the best modern standards.
39. Two key points are to be addressed before embarking on a project:
· ensure that there are in place suitable reporting/communication/control
systems and methods;
· identify the management resources required;
40. The need for clear and suitable reporting/communications/control systems
is identified in paragraphs 30 to 33 of FM 301 (Economic Appraisal of Projects
in PPARC). In particular, the need for clearly defined delegated authority is
emphasised. This should be fully documented in letters to those receiving the
delegated authority and understood by all parties.
41. It is essential that the project management team contains the correct mix
of professional/technical/administration skills. And that that the people
selected should have recent experience of successfully managing a comparable
project, or recent experience of successfully managing smaller projects. See the
overview of PRINCE project management at Annex B.
· the proposed concept;
· scientific justification;
· key specifications and user requirements;
· major risks/technical difficulties with proposed solutions;
· costs for a design study and best estimates of total cash planned cost,
including contingency;
· a broad project plan, with key milestones, for the entire project.
43. It is an important principle that the objectives of the project are
clearly stated and that these should be incorporated into the Statement of
Requirement (SoR). The SoR is not a detailed design, but it is the end-users'
specification of objectives which the design should achieve.
Where appropriate, it should include criteria for:
· reliability, including a statement of the environmental conditions and
mission against which such reliability is to be achieved;
· maintainability, including conditions and timescales under which such
maintenance is to be carried out;
· availability, taking account of the levels of reliability and maintainability
required; and
· quality assurance, the standard to be achieved during
construction/manufacture.
44. FM 301 (Economic Appraisal of Projects in PPARC) provides guidance on the
selection and evaluation of options, and this should be followed at this stage.
45. Proposals for new facility instruments must be submitted to the relevant
Facility Board or Committee for prioritisation, and if agreed it will be
submitted, via the Facility Director, to the Ground Based Facility Committee for
inclusion in the relevant Operating Plan. It is the responsibility of the
Facility Director to agree the design and technical specification in
consultation with the relevant board or committee. Subsequent design studies
must be reported to the Facility Board/Committee. Details of the PPARC project
approval processes are contained in FM
101.
46. The consideration of reliability and maintainability should lead to an
assessment of whole life costs. At this stage as accurate an estimate as
possible should be made of the future annual costs of operating and maintaining
the facility, including the costs of any major mid-life refurbishment or
upgrade. Professional advice should be obtained if necessary. This is an
essential part of the economic appraisal and is also necessary to avoid the
over-commitment of "baseline" allocations.
47. Risk and uncertainty must be considered. In the type of projects normally
managed by PPARC it may or may not be appropriate to conduct statistical
analyses of risk, but it is important to consider and document risk and
uncertainty in a methodical way. For example, what are the risks and
uncertainties which might lead to the project failing to met its objectives, in
full or in part, and failing to be delivered within budget and on time? How will
such risk be allowed for and what contingencies, time and money, might be needed
in the project planning and management? Many scientific projects in PPARC will
be high risk by nature through charting new territory or operating in high risk
environments, however, this is not an excuse to avoid properly considering these
factors.
48. The need for feasibility studies should always be considered, even though
this would often require the commitment of funds in advance of money being
allocated for, and might delay the start of, the main project. Feasibility
studies, possibly carried out by 'experts', can lead to the early identification
of potential difficulties, can clarify the precise requirements of the project,
and so can lead to a better contract. Adequate time should be allowed for such
studies and for recommendations to be included in the planning process. Even if
the project does not eventually proceed, reasonable expenditure on feasibility
work is unlikely to attract criticism.
49. Consideration should be given to the possibility of external
participation in any instrumentation project, including international
collaboration.
Estimating cost and time
50. There are a number of reasons for underestimating during the original
concept to pre-contract stages:
i) lack of experience and knowledge;
ii) reluctance to bid realistically in case the project is not approved;
iii) increasing sophistication as the SoR is developed;
iv) underestimate of risk;
v) poor professional advice;
vi) lack of market benchmarks;
vii) changing market conditions; and
viii) price inflation.
51. Reasons i) to iv) are within the control of those responsible for
directing the project, who should require estimates to be properly constructed
from a zero base, documented as fully as possible, and kept up to date. As
experience shows that original concept "best guess" estimates are
usually substantial underestimates, a significant contingency should be added at
that stage. As the SoR develops, along with the feasibility and preliminary
design work, the estimate can be refined and the contingency progressively
reduced as uncertainty diminishes. It is important that the project manager
establishes a procedure for identifying changes to estimates and timing, records
these and the reasons and draws them to the attention of management.
52. Reasons v) to viii) are less easy to control or anticipate. Further,
independent advice might be obtainable, for example from another body with
experience of a similar.
53. In line with FM 101 submission for approval must:
· State the objective;
· Show the timetable to include milestones and completion date;
· Show that the most effective means of achieving the objective has been chosen
by undertaking an economic appraisal (ref FM
301) where possible;
· Show all the internal and external costs and implications in sufficient
detail to enable an informed decision to be made.
54. The outcome of the design study must be reported to the Facility
Board/Committee. The report should include a draft budget, with more accurate
costings, together with a formal project plan including science requirements,
milestones and a cash limited cost profile.
55. Estimates of major project costs are published in the PPARC Operating
Plans, and when these relate to capital expenditure they are detailed in the DTI
Spending Plans and incorporated in the overall capital figures in the annual
Supply Estimates. These planned data are compared to actual performance annually
and significant variations require robust explanations. Major overspends or
project failures could result in the PPARC Accounting Officer (ie the Chief
Executive) being called to appear before a Public Accounts Committee.
56.
A public sector organisation embarking on a project should:
- select a project strategy and decide how it should be administered, taking
account of the amount of input required by the organisation: the greater the
risk, the greater the input required;
- select the organisation best capable of delivering the goods/service and
accepting the defined level of risk;
- aim to make no client changes once a particular design feature has been
decided, such changes are one of the major causes of cost overruns: the
elimination of change should be a prime objective;
- consider, with expert advice, how the design and build phases are to be
inter-related and who is to carry them out;
- Ensure that, before a project is submitted for full approval, estimates of
cost and timescales are valid and up-to-date.
57. In selecting the strategy it is important to decide, where applicable,
how much direct control of the design and construction is necessary.
58. There are two different design and construction philosophies, either of
which can be valid in appropriate circumstances. The first is to adopt separate
design and construction. The advantages are that the design leads to a very
tight specification against which a fixed price construction contract can be
achieved. The disadvantages are that re-design work may be required during
construction, and errors in design will lead to claims from the construction
contractor.
59. The second is a single design and build contract/agreement, using the
Statement of Requirements as the contract specification. The advantage of this
strategy is that it leads naturally to much closer liaison between designer and
builder and hence a better chance of optimum solutions being developed. The
disadvantage is that the client cannot see exactly what is to be built prior to
letting the main contract. This may lead to increased pressure for client
changes as the project proceeds.
60. As a rule of thumb, separate design and construction contracts/agreements
may offer the best strategy for unusual, one-off projects, whilst combined
design and construction contracts may be more suitable for projects requiring a
high proportion of industry standard components or which follow closely on other
designs. However, in all projects both strategies must be considered and the
relative merits and drawbacks weighed up and documented before a decision is
made.
61. The greater the separation of project management, design and construction
functions, the more important it is to achieve absolute clarity as to where the
contractual responsibilities lie and the greater the task of ensuring good
communications are maintained between all concerned.
Project Build
62. In general, PPARC seeks to use well established organisations for major
projects. Even so, weaknesses can arise. Particular attention needs to be paid
to:
· whether agreements should require stage payments linked to measured work
or to milestone events in the performance of the agreement;
· the provisions, where appropriate, covering "availability, reliability
and maintainability",
· adequate safeguards in respect of sub-contractor liability for defects or
default;
· where relevant, contractors', particularly consultants', professional
indemnity insurance.
63. Any factors relating to the project which could potentially affect the
outcome should be properly recorded on registered files.
64. If, during the course of the project, the contingency sum which was built
into the original project costing needs to be utilised then a case for release
must be made to the Director Science. This needs to address the alternatives and
consequences should contingency funds not be released, which may include
descoping the project (see FM
101).
65. On satisfactory completion of a project the work should be formally
accepted by the project manager. The procedure may vary from project to project,
but it is important that the project is formally 'closed off' by the project
management team, and that client and customer clearly understand the extent of
any continuing commitments.
Evaluation
66. The project management committee should carry out an evaluation at the
end of the project. The evaluation should measure the success of the project and
define and record the lessons learnt, in order to improve performance on
subsequent projects.
67. Post-project evaluation and feedback is a standard procedure in PPARC
(see FM 301 -Economic Appraisal of Projects in PPARC). This is an important
means of ensuring that lessons are learnt and are retained in the corporate
memory.
68. The evaluation should be carried out soon after project completion whilst
events are still fresh in people's minds. If a maintenance or guarantee period
is involved an interim evaluation should be carried out on practical completion
with a final evaluation at the end of such a period.
Conclusions
69. It is important that these strategies are considered afresh at the start
of each new project and that best advantage is taken of current available
guidance and best practice. Particular attention needs to be paid to the
following aspects:
· resources allocated to project management must be appropriate to the scale
and complexity of the project;
· the delegation and division of authority, both internally and between PPARC
and consultants, must be made clear and agreed in writing;
· project managers must be sufficiently experienced and trained;
· the Statement of Requirements must be clear and unambiguous and must contain
criteria for quality, performance and whole life costs;
· risk assessment must be methodical and well documented;
· formal competitive tendering must be used wherever possible;
· consultancy contracts must establish clearly each consultant's
responsibilities and liabilities;
· the need to use audit consultants must be considered in each project;
· the need for availability, reliability, maintainability and quality
assurances clauses in contracts must always be considered;
· cost estimating, both capital and whole life, must be methodical, based on
sound advice, and well documented.
70. Annex A lists the points which need to be addressed as part of managing
projects. Some points will clearly relate to non science programme projects
only.
71. Any queries concerning the content or interpretation of this FM should be
referred to Paul Blackford, Head of Planning & Budgeting, PPARC Finance
Division, Swindon Office, tel: 01793 442062, e-mail: paul.blackford@pparc.ac.uk.
David Bennett
Paul Blackford
PPARC Finance Division, Swindon Office
- have all the guidance and rules in FM 301 (Economic Appraisal of Projects
in PPARC) been correctly applied;
- are the planned project management resources adequate?
- is the proposed project manager suitably experienced and trained?
- has a proper comparison been done of the relative merits of an in-house
project manager and one contracted/seconded in?
Pre-contract consideration: deciding what to build
- has a full Statement of Requirements (SoR) been drawn up?
- does the SoR contain appropriate criteria for reliability, maintainability,
availability and quality assurance?
- have all reasonable options, including that of not proceeding, been
evaluated?
- have whole life costs been identified and evaluated?
- have risks and uncertainty been properly analysed?
- has adequate feasibility work been carried out?
Estimates of Cost and Time
- does the original estimate have a justifiable basis, supported by
independent advice where appropriate?
- does the estimate take reasonable account, by inclusion of contingencies,
of risk and uncertainty?
- has the estimate been regularly updated, with professional advice, as the
SoR and specification/design developed?
- has the project been subject to independent audit?
Employment of Consultants
- has the role of consultants been fully defined and communicated to all
concerned?
- does that role follow current guidance on good practice for the type of
project?
- have the consultants been selected by competitive tender? If not, why not?
- have consultancy contracts been properly drawn up and let?
- does the consultant hold adequate professional indemnity insurance?
- has the use of audit consultants been considered/have audit consultants
been employed? With what results?
Procurement Strategy
- is the procurement strategy manageable and appropriate to the objectives of
the project? Does it conform with recommended good practice?
- does the selection of contractors result from competition?
- is the "no client changes" rule being rigorously applied?
- have the options for the separation or combination of design and
construction contracts been properly considered?
Project Build
- does the contract comply with current guidance (OGC etc) on best practice?
- has any divergence from best practice been considered by the Head of
Procurement and agreed by the PPARC Head of Finance and the reasons properly
recorded?
1.1 What is a Project?
1.2 Types of Project
1.3 Project Failures
2. The PRINCE Methodology
2.1 PRINCE Background
2.2 Scope of PRINCE
2.3 PRINCE in Context
2.4 PRINCE Elements
2.4.1 Interests
2.4.2 Business Case
2.4.3 Project Organisation
2.4.4 Product-Based Approach
2.4.5 Tolerance
2.4.6 Project Phases
2.5 Processes and Components
2.5.1 PRINCE Processes
2.5.2 PRINCE Components
3. Process Overview
3.1 The Process Model
3.2 Summary of the Processes
3.2.1 Directing a Project
3.2.2 Starting up a Project
3.2.3 Initiating a Project
3.2.4 Managing Stage Boundaries
3.2.5 Controlling a Stage
3.2.6 Managing Product Delivery
3.2.7 Closing a Project
3.2.8 Planning
PRINCE Project Management - An Overview
1. Introduction
1.1 What is a Project?
PRINCE defines a project as:
A management environment that is created for the purpose of delivering one or
more business products according to a specified business case.
A PRINCE project would have the following characteristics:
- a finite and defined lifetime
- business products that are defined and measurable
- a corresponding set of activities that will achieve the business products
- a determined set of resources
- an organisational structure, including defined responsibilities, that manages
the project.
Any project will fall within a specific business context; it may be
stand-alone, one of a sequence of related projects, or part of a programme or
corporate strategy.
Since a project is, by definition, a temporary structure created to achieve a
particular business benefit or objective, it is disbanded once the work is
completed.
A project has a life cycle, namely the path and sequence of activities needed
to produce the final business product. The product will also have its own life
cycle, which will normally extend beyond the end of the project that produces
it. The two life cycles should not be confused; they are shown in Figure 1.
PRINCE (PRojects IN a Controlled Environment) covers the project life cycle plus
some of the pre-project preparation.
Figure 1 Product and project life cycles
1.2 Types of Project
All projects are different, but they can generally be classified into one of
four categories, as shown in Table 1.
Project
Categories
Do we know what we are trying to achieve?
Yes
No
Do we know how to go about it?
Yes
Closed
Semi-open
No
Semi-closed
Open
Table 1 Categories of Project
The characteristics of the projects are summarised as follows.
1) Closed projects occur when an organisation is undertaking a task that is
well defined and is familiar with the approach to it. It will quite often have
been undertaken previously and procedures describing the approach and past
experiences may well exist. Typical examples could be: a construction company
putting up another building; a computer service organisation installing a new
computer system; a pharmaceutical company undertaking drug trials of a new
product.
Since closed projects are well defined, they are often large and complex with
a great many dependencies. The challenge is normally to complete the job
quicker, more effectively or with fewer resources.
2) Semi-closed projects involve a very well defined goal but little knowledge
of how to achieve it. An example could be the implementation of a management
information system, giving senior staff all the information they need at the
touch of a button.
One way to tackle semi-closed projects can be to have a number of parallel
"solution seekers" who then pool experiences.
3) Semi-open projects are characterised by a good understanding of the way in
which the job should be done, but only a hazy idea of the ultimate goal.
Examples would include developing completely new products or finding uses for a
new technology. Scientific research will often fall into this category.
Since the approach is well known it can be tempting to put too much effort
into defining and planning, rather than searching for the goal. In the IT
environment, modern prototyping methods (such as Rapid Application Development)
are particularly useful for this type of project.
4) Open projects occur when an organisation is unsure both of what should be
done and how it is to be carried out. They often come about when a business is
attempting to do something it has never done before and can arise from a change
to the external business, political or legislative environment, or from
implementing a new part of its own strategy.
Organisational change can fall into this category, such as implementing a
Quality Improvement programme. Another example would be developing a new product
for a market an organisation has not sold into before. The way to succeed in
open projects is to proceed very slowly, evaluating and reviewing after each
step.
PRINCE can handle all types of project, though the way in which the method is
applied will vary.
1.3 Project Failures
It is a fact that projects often fail. While they may start out from some
perceived business need, the need and objective can become blurred and confused
as time goes on. A project may end up not delivering what was expected and the
investment made may produce few benefits.
Projects often fail, not through ineffectiveness of people, but because of
the complexity of managing a project. A survey found that 80% of the reasons for
project failure were management, rather than technical.
Some problems typically encountered include:
- impossible constraints on time and/or budget;
- lack of a defined business case;
- unclear scope and objectives for the project;
- poor understanding of quality requirements;
- poor communication between those involved;
- conflicts of interest between project and line management;
- resources not made available in a timely fashion, or suddenly withdrawn;
- lack of commitment;
- inadequate planning, or lack of planning skills;
- inadequate monitoring and control;
- no objective assessment of project completion;
- no defined approach to managing change;
An organisation can minimise the problems causing project failure by adopting
a methodology for managing projects. A methodology will seek to provide answers
to the questions "what is to be produced?", "by whom?",
"how and when will it be done?" and "why are we doing it?".
Furthermore, it will seek to provide these answers in a clear, unambiguous form
that can be documented, understood, agreed by all concerned, and followed. The
PRINCE methodology has been developed with this in mind.
Note that it is possible for a project to 'fail' in terms of its final
outcome, but be classed a success in terms of project management. This type of
situation can arise, for example, when during the lifetime of the project the
reason for undertaking it ceases to be valid; organisational and political
changes, or technological advances are common causes for this to occur. In such
situations the right approach will be to abort a project, so that resources of
staff time and money are not wasted.
2. The PRINCE Methodology
2.1 PRINCE Background
PRINCE has been evolving and developing in both private and public sectors
since the late nineteen-seventies, and is therefore a well proven method. PRINCE
was launched officially in 1989 and is owned by the CCTA (Central Computer &
Telecommunications Agency). It is publicly available; any organisation may
therefore use it without license or payment.
Experience with the initial published version of PRINCE proved its strengths,
but also showed a number of areas that needed improvement. These included an
orientation towards IT, a prescriptive manner for particular management
techniques and an overly bureaucratic approach (although the latter is more a
question of implementation than actuality). A new version (PRINCE II) has been
developed which builds on the strengths of PRINCE I while overcoming its
deficiencies. The new version was developed by a group of consultant
organisations, with HMSO and IBM responsible for its publication (for the paper
and on-line versions respectively).
2.2 Scope of PRINCE
PRINCE is not intended to cover all subjects relevant to project management,
since some aspects lie more properly in other areas, such as Programme
Management. In addition, there are a number of existing and proven methods which
cover certain aspects of project management, such as:
a) people management techniques (motivation, delegation and leadership),
b) generic planning techniques such as Critical Path Analysis and Gantt charts,
c) risk management techniques,
d) corporate-level quality management and
e) budgetary control.
The techniques and tools needed will vary according to the business
environment and the type of project.
PRINCE draws a real distinction between management of a project and the
technical work done to produce the required product or outcome. PRINCE covers
the management of the project and its resources, but does not address the
specialist techniques involved in creating products; this is covered by other
methods, to which PRINCE must interface.
Another area of concern often lies with procurements. While the contracting
process does not form one of the elements of PRINCE, since contracting and
procurement can be thought of as technical activities, they can be managed under
the PRINCE umbrella. Where a procurement forms part of a PRINCE project, it will
be important to ensure that project documentation is in line with contractual
requirements.
2.3 PRINCE in Context
PRINCE has been designed for use on any project and in any environment. It
contains all the necessary concepts and management processes that are required
for a properly run and managed project. However, it is important to realise that
the way in which PRINCE is applied will vary considerably and the method should
therefore be tailored to suit both the organisation and a particular project.
Appropriate tailoring is critical to the effectiveness of the method.
PRINCE projects focus on the production and delivery of specified products to
satisfy a specified business case. There will be higher level issues, such as
managing programmes, which will need to be handled by other methods. Similarly
there are lower level techniques for managing particular tasks. PRINCE occupies
the ground in between these two extremes.
A project can rarely be undertaken in isolation and will be subject to
dependencies. There will be outputs from one project required for another. There
may be shared resources required by a number of projects. PRINCE emphasises the
products that a project is required to deliver, thereby forming a sound basis
for the identification and management of dependencies and the definition of
project boundaries.
2.4 PRINCE Elements
2.4.1 Interests
Within any project there are number of groups with an interest in its
outcome. These include:
1) Customers who have commissioned the work and will benefit from the end
result. This is sometimes known as the Business interest.
2) Users who will use or operate the final product. These are often drawn
from the same group as Customers.
3) Suppliers who provide the special skills and/or resources to the project,
or provide goods or services. These can be drawn from a Technical department
within the Customer's organisation.
In addition there may be sub-contractors who provide products or services to
the suppliers. PRINCE recognises the different interests and requires that they
are all considered and protected at each stage of a project. Figure 2 shows the
partnership of these interests.
Figure 2 Principal Project Interests
The Customer/Supplier environment assumes that there will be a Customer who
specifies the required outcome, uses the final products and, normally, funds the
work, while a Supplier provides the skills and resources to achieve that
outcome. PRINCE has been developed from the point of view that these two parties
are drawn from separately managed enterprises and sometimes from commercially
separate organisations. Where both are drawn from a single organisation, the
composition of the Project Board will be influenced.
Regardless of the composition of the team undertaking the work, the Customer
should always be involved throughout the project, particularly in the creation
and the verification of products.
2.4.2 Business Case
A requirement of PRINCE is that the business benefits to be obtained are
defined in advance and considered throughout the project. The benefits are
stated in the Business Case, which forms part of the project Initiation
Document. If for some reason the benefits cease to be achievable, it will often
be more cost-effective to cancel the project than continue with it. Benefits can
take many different forms:
a) financial, in the form of additional revenue or to avoid costs (or
possibly even to ensure survival!);
b) strategic, by providing a platform on which to move towards an organisation's
strategic aims;
c) legislative, by fulfilling some obligation set out by government or company
policy.
Throughout a PRINCE project, the Business Case is reviewed and progress
measured against the defined benefits. During the lifetime of a project
opportunity may arise to generate additional benefits that may enhance the final
product, or provide improvements to other projects. However, any deviations from
the initial Business Case must be strictly controlled by the Project Board.
2.4.3 Project Organisation
An overall objective of PRINCE is to have the right people involved in a
project at the right time. The organisational structure therefore needs to be
defined and responsibilities allocated at a level commensurate with authority.
Figure 3 shows the general organisational structure of a PRINCE project.
The Project Board are owners of the project; they are responsible for the
project's success or failure. It will report normally to the corporate or
programme management.
Below the Board is the Project Manager, possibly supported by a series of
specialist team managers (or stage Managers). The Project Manager is responsible
to the Project Board for all aspects of the project on an on-going day to day
basis. Overall their function is to plan the project and to ensure that project
products are delivered to the Board on time, within budget, to the required
quality levels and satisfying the Business Case.
The Specialist Teams are made up of a mixture of users and technical experts,
creating the technical end products. Since projects will sometimes involve
external contractors it may be that these teams are drawn from the supplier.
The Project Assurance Team (PAT) does not have executive power. They are
there to provide confidence to the Project Board. Board members are very
unlikely to have time to devote to detailed assurance (eg of quality) and this
function is usefully delegated.
Project Support is there to provide a centre of excellence in project
management to assist the Project Manager. Its function can vary and could
include supporting project management tools, providing configuration management,
processing requests for change, assisting in drawing up plans, helping with
estimation and acting as a repository for historical project information.
Ideally it would be concentrated in a Project Support Office.
For the duration of the project these reporting lines exist within a matrix
management framework. Each member retains their normal line management boss for
the purposes of personnel administration and allocation of non-project work, but
is responsible to the project boss for project work.
2.4.4 Product-Based Approach
PRINCE employs the Product-Based Planning technique, which focuses on what
has to be produced rather than what needs to be done. It involves three
elements:
i) the Product Breakdown Structure, in which the end business product is
broken down, in a hierarchical form, into its component products;
ii) the Product Flow Diagram which shows the order of producing the individual
products;
iii) Product Descriptions that provide detailed definitions of the products,
including their quality criteria, form, composition and who is responsible for
producing them.
The product based planning technique allows the project to define in clear
terms the quality criteria to which each product must conform. Means of testing
quality need to be built into the management process of a project. PRINCE
describes one technique, Quality Review, that may be used, but other techniques
may be appropriate to use either in addition or as alternatives. Whatever
methods are chosen the Quality plans must state what they are, when and how they
will be applied and by whom.
2.4.5 Tolerance
No project ever goes completely to plan. Some things will go a little slower
than planned, or cost a little more. Other things will go quicker, cost a little
less. These little variations will occur all the way through a plan. Although
the Project Board will agreed a plan with the Project Manager, it does not want
the Project Manager to be constantly seeking its authority to spend an
additional pound, or report that the plan is one day behind schedule. On the
other hand, the Project Board does not want progress to deviate wildly from the
plan without being told and being able to react. The dividing line between
differences which are permissible and those which require Project Board
intervention is called Tolerance.
The two standard elements to tolerance are time and cost, although scope and
quality are other possible options. Tolerance is the permissible deviation from
a Stage or Project Plan without bringing the deviation to the attention of the
Project Board (or higher authority if the deviation is at project level).
Separate tolerance figures should be given for time and cost.
2.4.6 Project Phases
PRINCE allows a project to be divided into a number of stages, each of which
forms a separate entity for management purposes. Each stage has a defined set of
products (or outcomes), a lifespan, resources and an organisation structure. The
completion of each stage is determined by the satisfactory delivery of the
appropriate products. Stage boundaries are chosen to suit the project and can
depend on:
a) the order of delivery of products;
b) grouping of products into self-consistent sets; and
c) the natural decision points in a project (eg corresponding to a tender
evaluation).
Whatever the size of the project, PRINCE defines a Project Initiation Stage,
during which the project is accurately defined and planned. The Initiation Stage
concludes with a management review during which the viability of the project is
assessed and, if appropriate, authorisation given to proceed with the project.
This avoids making unnecessary commitment of resources. The principal
documentation to come out of this stage is the Project Initiation Document, or
PID, which contains complete details of the project, including business case,
plans, quality strategy, the organisation etc.
In certain situations, a Feasibility study may be required as a precursor to
a project. This would investigate the situation and determine options for the
way forward. Under PRINCE such a study would normally be handled as a distinct
project; the main project would then follow on after a conscious (and informed)
management decision.
A project has a limited lifetime and so PRINCE defines a final phase, Project
Closure, which closes down a project, captures any useful historical data,
documents any lessons that can be learned for the future and accepts the final
business product.
Between project initiation and closure there will be one or more management
stages during which work will be carried out to produce the required products.
During stages the progress will be monitored continuously to ensure that the
project is proceeding according to the agreed plan and that changes affecting
project outputs are controlled. If more than one stage is involved some
management effort will be expended in managing the boundaries.
2.5 Processes and Components
2.5.1 PRINCE Processes
PRINCE is a process-based approach to project management, where the processes
define the activities to be carried out during the project. In addition, PRINCE
defines a number of components that need to be considered within each of the
activities. The relationships in the PRINCE Process Model are shown in Table 2.
Level
Item
Description
1
Component
Fundamental elements that must be considered at each phase of the project
2
Process
Activities that need to be performed during a project
3
Technique
Individual tools which may be used to carry out the processes
4
Product Outline
A set of templates, descriptions etc that support the techniques
Table 2 PRINCE Process Model
Apart from one or two exceptions, PRINCE is not prescriptive with regard to
the Techniques and their supporting Product Outlines. Users of the method are
free to select the tools that are most appropriate for their organisations and
the project in hand. With the emphasis of PRINCE on tailoring, an organisation
can therefore make use of any techniques with which it is familiar, provided
that such techniques are compatible with PRINCE. The major exception is Product
Based Planning; this technique is one of the cornerstones of PRINCE.
Figure 4 shows the eight PRINCE processes, which range from getting the
project started correctly, through controlling the progress of the project to
its completion. The common Planning process is used by many of the other
processes.
Throughout the process model there are management inputs and outputs of each
process. PRINCE is a product based method, so each product is identified,
defined and its delivery controlled. Naturally, responsibilities for each
process and product must be defined.
- organisation
- planning
- controls
- stages
- management of risk
- quality on a project environment
- configuration management
- change control
Each component needs to be considered to a greater or lesser extent within
each of the individual processes. Many of these components have already been
described in Chapter 2.
A project, by its nature, needs to be set up to handle change since the
future is always less predictable than with routine work. Also, since projects
can be large and complex, or deal with new or unusual factors, risk must be
considered as part of the project management.
During a project the specification of products will invariably need to
change. Such changes need to be controlled as they can destroy the project's
overall chance of success. Controlling changes is linked to version control,
which PRINCE handles as Configuration Management. Configuration Management
focuses on controlling the products being delivered, knowing at what stage and
version they are at any time, who is working on them and why.
3. Process Overview
3.1 The Process Model
PRINCE identifies eight processes which need to be undertaken when managing a
project namely:
- Starting up a Project
- Initiating a Project
- Directing a Project
- Controlling a Stage
- Managing Product Delivery
- Managing Stage Boundaries
- Closing a Project
- Planning.
Planning is a process used throughout a project. These processes have inputs
and outputs, and interact with each other. Figure 6 shows the processes
diagrammatically, together with typical input and output
products.
These processes link to a range of project management techniques, some of
which are specific PRINCE techniques, and some of which are generic and
generally used techniques.
Project management is seldom straightforward enough to be a simple, linear
process. In a PRINCE context, there are essentially five parallel process levels
to take into account, as shown in Figure 6. The first four of these are
management process levels, while the fifth is of a 'technical' nature.
Programme Management Customer only
Directing a Project
Managing a Project Customer and Supplier/Technical
Managing Product Delivery
Developing Products Customer or Supplier/Technical
a) At the highest level is programme management. While it is not part of
project management as such, programme management is important, as it will often
set the context for one or more projects. It is also worth noting that the type
of programme management in use within a particular business or organisation may
consist of more than one process level. It may also be applied with variable
degrees of formality. Figure 6 suggests that this is a ?Customer only? domain.
However, there may be certain circumstances where the Supplier takes some
programme management responsibility.
b) Within the project itself the highest level is Directing a Project (the
Project Board work). At this level a minimum of management effort is expended.
c) At the level of Managing a Project the majority of management effort is
expended.
d) At the lowest management level, Managing Product Delivery would be handled
by Team Leaders.
e) Below this, Developing Products (which is not part of project management)
carries out the tasks which produce the project's interim and final products.
There are two major ways in which these levels interact. These are:
i) The higher level processes exercise control over the lower levels.
ii) The output of the lower level processes provides the input which allows
the higher level processes to function effectively.
3.2 Summary of the Processes
3.2.1 Directing a Project
Directing a Project runs from the start-up of the project until its closure
and is aimed at the Project Board. The Project Board manages by exception,
monitors via reports and controls through a number of decision points.
The key processes for the Project Board break into four main areas:
- Initiation (starting the project off on the right foot);
- Stage boundaries (committing more resources after checking results so far);
- Ad hoc direction (monitoring progress, providing advice and guidance,
reacting to exception situations);
- Project closure (confirming the project outcome and bringing the project to a
controlled close).
This process does not cover the day-to-day activities of the Project Manager.
3.2.2 Starting up a Project
This is the first process in PRINCE. It is a pre-project process, designed to
ensure that the prerequisites for initiating the project are in place. The
process expects the existence of a Project Mandate which defines in high level
terms the reason for the project and what outcome is sought. This process should
be very short but should often include some form of feasibility study.
The work of the process is built around the production of three elements:
- ensuring that the information required for the Project Brief is available;
- designing and appointing the Project Management Team;
- creating the Initiation Stage Plan.
3.2.3 Initiating a Project
The objectives of Initiating a Project are to:
- agree whether or not there is sufficient justification to proceed with the
project;
- establish a stable management basis on which to proceed;
- document and confirm that an acceptable Business Case exists for the project;
- ensure a firm and accepted foundation to the project prior to commencement of
the work;
- agree to the commitment of resources for the first stage of the project;
- enable and encourage the Project Board to take ownership of the project;
- provide the baseline for the decision-making processes required during the
project's life;
- ensure that the investment of time and effort required by the project is made
wisely, taking account of the risks to the project.
3.2.4 Managing Stage Boundaries
This process provides the Project Board with key decision points on whether
to continue with the project or not. The objectives of the process are to:
- assure the Project Board that all deliverables planned in the current Stage
Plan have been completed as defined;
- provide the information needed for the Project Board to assess the continuing
viability of the project;
- provide the Project Board with information needed to approve the current
stage's completion and authorise the start of the next stage, together with its
delegated tolerance level;
- record any measurements or lessons which can help later stages of this project
and/or other projects.
3.2.5 Controlling a Stage
This process describes the monitoring and control activities of the Project
Manager involved in ensuring that a stage stays on course and reacts to
unexpected events. The process forms the core of the Project Manager's effort on
the project, being the process which handles day-to-day management of the
project.
Throughout a stage there will be a cycle consisting of:
- authorising work to be done;
- gathering progress information about that work;
- watching for changes;
- reviewing the situation;
- reporting;
- taking any necessary corrective action.
This process covers these activities, together with the on-going work of risk
management and change control.
3.2.6 Managing Product Delivery
The objective of this process is to ensure that planned products are created
and delivered by:
- making certain that work on products allocated to the team is effectively
authorised and agreed;
- accepting and checking Work Packages;
- ensuring that work conforms to the requirements of interfaces identified in
the Work Package;
- ensuring that the work is done;
- assessing work progress and forecasts regularly;
- ensuring that completed products meet quality criteria;
- obtaining approval for the completed products.
3.2.7 Closing a Project
The purpose of this process is to execute a controlled close to the project.
The process covers the Project Manager's work to wrap up the project either at
its end or at premature close. Most of the work is to prepare input to the
Project Board to obtain its confirmation that the project may close.
The objectives of Closing a Project are, therefore, to:
- check the extent to which the objectives or aims set out in the Project
Initiation Document have been met;
- confirm the extent of the fulfilment of the Project Initiation Document and
the Customer's satisfaction with the deliverables;
- obtain formal acceptance of the deliverables;
- ensure to what extent all expected products have been handed over and accepted
by the Customer;
- confirm that maintenance and operation arrangements are in place (where
appropriate);
- make any recommendations for follow-on actions;
- capture lessons resulting from the project and complete the Lessons Learned
Report;
- prepare an End Project Report;
- notify the host organisation of the intention to disband the project
organisation and resources.
3.2.8 Planning
Planning is a repeatable process, and plays an important role in other
processes, the main ones being:
- Planning an Initiation Stage;
- Planning a Project;
- Planning a Stage;
- Producing an Exception Plan.
PRINCE provides a product-based start to the planning activity. It also
provides a planning framework which can be applied to any type of project. This
involves:
- establishing what products are needed;`
- determining the sequence in which each product should be produced;
- defining the form and content of each product;
- resolving what activities are necessary for their creation and delivery.