2.
This FM sets out the principles and procedures to be applied in determining the
cost of resources used in an activity, with particular regard to the setting of
fees and charges for repayment work (ie work undertaken for another organisation
for which a charge is levied) and costing for market testing. Further guidance
and information can be found in the Costing Guide and the Fees and Charges Guide
(both published in 1992 by HM Treasury), copies of which are held in
Establishments' finance sections. Specific guidance on market testing is
available in The Government's Guide to Market Testing (HMSO, 1993). These
publications are still extant.
3.
The traditional definition of the total cost of resources used in providing a
particular activity is the Full Economic Cost (FEC). This will comprise both the
cash cost of the activity (eg pay costs of staff working on the activity) and
non-cash or notional costs, such as depreciation of plant and machinery. The FEC
of the activity should be determined in all cases.
4.
Attached at Annex A are the elements which make up the FEC of activities. They
may be divided into categories of direct costs and indirect costs (or
overheads):
Direct Costs:
These costs are normally directly attributable to activities through financial
accounting systems. The main items will be labour costs, materials and
services. These cash costs will generally be under the control of the
management currently providing the services. Establishments should ensure that
wherever possible and reasonable as much expenditure is attributed directly to
activities. This aids the production of accurate costings.
Indirect costs:
These costs are not easily attributable directly to particular outputs and
normally have to be apportioned by an appropriate method. Indirect costs will
include local support costs such as finance and personnel sections. The
attribution of indirect costs is currently being considered as part of the
introduction of RAB/ PUFFS2 Project and review of the PPARC DSY costing system
by Finance Officers. Conclusion to these exercises will form an update to this
FM when complete.
5.
It is the responsibility of each Establishment to determine the FEC of any
repayment activity. Local overheads should be apportioned in the most
appropriate manner, balancing the requirements of precision against the cost of
producing the data, but to ensure that cross-subsidisation between areas is kept
to a minimum.
6.
A significant part of indirect costs will be in respect of depreciation of Land
and Buildings and Plant and Machinery. All PPARC assets are recorded on the
Capital Assets Register, and depreciation is currently calculated annually at
the end of each financial year. In addition, the cost of capital on the current
written down value of the capital employed (6%) is to be included in the
costing. This will be the average of aggregate values on 1 April and 31 March in
the financial year of the net assets. Where equipment is leased, capital
equipment costs will comprise the rental and maintenance costs.
7.
The Employers' Superannuation Contribution (ESC) should be included in the FEC
at the current rate of 10.1% of pensionable pay (as at 1.4.99). (ESCs are the
employers contribution to the Research Council’s Pension Scheme and this
percentage is updated periodically based on actuarial forecasts.) Swindon Office
Personnel Group can advise on the current rate.
8.
Costings should be based on current actual costs and re-stated at future price
levels using the latest GDP
Deflators issued by HM Treasury. These are circulated to key personnel in
Swindon Office and Establishments on receipt from HM Treasury, by Planning and
Budgeting Group in Swindon Office, from whom further copies can be obtained if
necessary.
9.
The term "repayment work" means all work funded other than from the
Science Budget (SB) allocation from OST, ie from external income with the
exception of jointly-funded operations.
10.
PPARC’s policy is to encourage Establishments to undertake repayment work and
maximise the financial and scientific benefits that the work brings. However,
increased repayment work can cause problems in relation to SB funded priorities,
to other current repayment activities and to the planning of both - particularly
when income does not cover all the FEC of the work.
11.
It is necessary therefore to establish guidelines in respect of the repayment
activities that can be undertaken:
(a) the work must be
within the scope of PPARC's Charter and be appropriate to the skills and
interests of the Establishment involved;
(b) in all cases
there should be scientific and/or financial benefits to PPARC. Establishments
should not use SB resources to subsidise under-funded repayment activities,
except in the specific circumstances detailed in paragraph 14. For commercial
work, unless there are quantifiable benefits to PPARC, the customer must be
prepared to meet at least the FEC of the service, with PPARC’s aim being to
charge the highest price the market will bear;
(c) PPARC should not
normally undertake work for which ample capacity exists in the private sector.
12.
As with all public-funded bodies, PPARC is required to recoup the full cost of
providing goods and services from its customers in both the private and public
sectors. FEC should be determined as a basis for all charges for repayment work,
although the final charge for the work could be higher or lower.
13.
It is important to distinguish between costing and charging. The former is the
financial resources consumed to carry out an activity while the latter is the
price charged for the goods or service being supplied. The general aim should be
to charge as much as the market will bear and to maximise the benefits of
repayment work, both scientific and financial.
14.
Although the principle of testing how much the market will bear is relevant for
all types of repayment work, there will be activities for which it is
appropriate to charge less than FEC. These will include collaborative programmes
which are jointly funded by PPARC and other bodies. In other cases there will be
non-financial benefits to PPARC (eg where the work of the other bodies
complements the PPARC scientific programme) or its scientific community which
may also justify a lower charge but these should be considered carefully: any
charge below FEC is effectively a subsidy from SB programmes.
15.
For strictly commercial work the FEC also serves as a basis but the aim should
be to charge more if at all possible. In view of the unique nature of PPARC's
activities, the comparative market price may be difficult to determine and a
degree of judgement followed by negotiation will be required. The aim should be
to exploit the uniqueness of the service by setting a higher price for the work.
16.
Establishments must be cautious in what information is revealed to potential
customers. Staff should not, for example, reveal the content of this FM. Prices
should not be quoted for work until costings have been completed. In many cases
the market may bear a lot more than is thought initially and revealing FEC or a
minimum acceptable price would undermine negotiations. Establishment Directors
will be responsible for setting the negotiating brief but as a general guide, it
is recommended that an opening negotiating price should be set out as FEC plus
30%. Procurement staff have an important role to play in negotiations and should
be brought in at an early stage of the process.
17.
If the market price is less than the FEC of providing the work and there are no
other benefits to PPARC, then the activity is not viable and should not be
started.
18.
It is fairly common practice that potential customers will offer equipment,
staff resources etc in part or even full payment for repayment work. In these
circumstances, the resources offered need to be costed accordingly. When
equipment is provided that will become the property of PPARC on termination of
the repayment contract, the full cost of the equipment may be included in the
costing algorithm, providing it remains of value to PPARC. (Note: the cost to
PPARC of running or maintaining the equipment should also be taken into
consideration.) If reclaimed by the customer, only a relevant proportion of the
value should be used. Cases of this kind need to be judged on their merits
through a cost benefit analysis (see FM 301 Economic Appraisal).
19.
In accordance with HM Treasury rules, government departments should be charged
at FEC. However, in circumstances where government departments and private
sector customers might be in competition for the same PPARC service, the FEC
should reflect the market price, if the latter is higher. In these circumstances
it is considered reasonable to charge departments a price similar to those set
for the private sector.
20.
In these circumstances it may be difficult to use the procedure as described
above. Depending on whether the work falls in the commercial or collaborative
category, an estimate should be made of the amount of work which can be
afforded. This should then be costed in detail. If there is a difference from
the funds available then the amount of work should be adjusted up or down. The
important principle is that, if the budget is restricted, the work done and not
the price charged should be adjusted to fit.
21.
There may be occasions where FEC is not an appropriate basis for setting
charges:
(a) Excess capacity
Where the opportunity
cost (defined as the value of resources in their best alternative use) of
excess capacity is zero (eg under-utilised facilities or buildings which have
no other use and cannot be disposed of) it may be appropriate to reduce the
charge to a marginal costs basis although the aim should be to charge higher
in order to make a contribution to the fixed costs involved.
(b) Differential charging
In certain cases
charges may be made at less than FEC in respect of:
fluctuating demand:
where it is appropriate to charge less than FEC at off-peak periods. This
will normally be compensated by charging more at peak periods so that at
least the FEC is recovered over the accounting period.
incentive charging
:
this will normally be work of small value which may act as an incentive for
future business. This work may include feasibility studies.
In all cases,
justification for charging less than FEC must be fully documented.
22.
Work undertaken for the EC must be costed in accordance with the Commission's
regulations. The latest guidelines of which costs can be included in EC
contracts are detailed at Annex B. Further information on EC contracts can be
found at http://www.cordis.lu/fp5/financial-guides.htm
. EC contracts are usually collaborative with at least one other partner, and
the EC usually contributes up to 50% of the eligible costs. (The Full Cost Model
should be used as PPARC produces full annual accounts.)
23.
Proposals to undertake repayment work must conform to the guidance given in
paragraph 11 and be costed in accordance with the principles set out in
paragraph 4. In all cases, proposals seeking approval to provide repayment work
must at the same time seek approval in principle for the associated staffing
requirements.
24.
Establishment Directors are authorised to carry out work up to £300k per
project at FEC without reference to Swindon Office. Repayment work estimated to
cost in excess of this amount, or where additional advance funding is required,
must be referred in advance to the Director Administration through PPARC’s
Head of Finance, Swindon Office, for approval. Repayment work should not
normally exceed 10% of an Establishment’s annual SB allocation.
25.
The Director Administration’s approval should also be sought for projects
valued below £300k which:
(a) involve issues of
propriety;
(b) are major
departures from agreed policy;
(c) incur a
substantial financial risk;
(d) contain a
sensitive foreign policy aspect.
26.
Approval for repayment work should be obtained prior to entering into any formal
commitments to provide services or allocate resources. Where an initial process
of application and selection, which requires submission of a proposal for
funding, is involved, formal approval under the terms of the delegated powers
set out above will not normally be required at this stage but details of the
application must be notified to the appropriate person or body who would
otherwise be the approving authority.
27.
The approving officer should be provided with full details of the proposal under
the following headings:
(a)
Summary
of project:
background,
description, milestones, collaborators, intellectual property rights (eg
patents)
(b)
Personnel:
roles,
time allocation
(c)
Finance:
analysed
FEC of work, proposed price, justification for diversion from FEC,
sources of funding
(d)
Effect
on science programme:
eg
non-financial benefits to PPARC
28.
Proposals which require approval from the Director Administration should be sent
via PPARC’s Head of Finance, Swindon Office, who will advise the Director
Administration on the financial aspects of the proposal..
29.
The appropriate procurement personnel will prepare the formal offer (or tender)
which will form the basis of the contract for the repayment work. Procurement
staff should be consulted early in the negotiations with the prospective
customer to agree appropriate terms and conditions. The Head of Procurement is
also able to provide advice where necessary. Account will be taken of such
aspects as firm and variable elements in the price, payment arrangements
(including stage payments if required), any need for sub-contracts to be placed,
delivery, packaging, default, break, indemnities, confidentiality, publication
of results of research and exploitation and protection of any of PPARC’s
intellectual property.
30.
Annex B to this FM identifies the salient points in the form of a note on the
procedures for dealing with enquiries and requests for the provision of
repayment work.
31.
Where there is doubt, the responsibility for determining whether it is
appropriate for PPARC to undertake a proposed repayment service will rest with
the Director Administration.
32.
PPARC Finance Division, Swindon Office, will be responsible for the
implementation of costing policy and procedure across PPARC, and will carry out
"dipstick checks" on individual cases as appropriate. Establishments
will be responsible for setting the level of charges. Additional guidance can be
obtained from PPARC Finance Division, Swindon Office.
33.
The Head of Procurement will be the first reference point for questions on
contractual matters.
34.
Although the Government guidance on this subject is still extant, the pressure
on departments to market test services has been relaxed in recent years, to the
extent that is has become a departmental decision whether this option is
desirable or ultimately represents greater value for money. This section is
intended to provide guidance on the costing of in-house activities for the
purposes of market testing. The general principles set out herein build on the
advice in the HM Treasury's "The Government’s Guide to Market
Testing" (HMSO 1993). Additional guidance on this subject is available on
the HM Treasury Web Site: http://www.hm-treasury.gov.uk/index.html.
35.
When an activity is identified for market testing, and an in-house bid is to be
made, the following will be required:
(a)
the FEC of the current service;
(b)
the FEC of the in-house bid; and
(c)
the cost data for tender bid evaluation.
The need for accurate
costings is paramount for three reasons:
(a)
to ensure that bids submitted by the in-house team are not:
too high
(resulting in lost work)
too low
(resulting in inability to deliver Service Level Agreements);
(b)
to provide a reliable basis for tender bid evaluation;
(c)
to ensure a reliable basis for future calculations of efficiency savings.
36.
In principle the comparison between the cost of an in-house bid and a bought-in
service should be based on the FEC of each option. In practice, however, some
elements may be excluded from the in-house bid as they would remain as a cost
whether the service was provided in-house or by an outside supplier. These are
known as unavoidable costs and are explained in paragraph 40(a). As a first step
in the market testing costing exercise, the FEC of the existing in-house service
should, however, be ascertained.
37.
The FEC represents the total cost of resources used in providing a particular
activity and comprises both cash and non-cash (or notional) costs. These are
either directly attributable to services through financial accounting systems
or, in the case of overheads, apportioned between services by an appropriate
manner. Annex A lists the items of cost which make up the full cost.
38.
Costing of in-house bids for market testing requires as much precision as
possible. Establishments should ensure that as much expenditure as possible is
attributed directly to activities. Staff effort accounting systems should be
used to identify staff effort on activities. Full project cost accounting is
already available at Establishments and will be introduced in Swindon Office as
part of the PUFFS2 financial project.
39.
The assessment of FEC applies equally to an activity which is an output of the
Establishment (eg research grant processing or instrument development) as it
does to one which is a support activity (eg secretarial support) to one or more
output activities. The range of overhead costs appropriate to a support activity
may well differ from those appropriate to an output activity. For example, a
policy unit might provide an input to grant processing activity but not
secretarial services, whereas both would attract a share of costs from the
personnel section.
40.
As part of the evaluation process, it will be necessary to make adjustments to
the FEC of activities in order for in-house bids to be on a common footing. For
example, in-house bids should not include activities and support services which
would still be needed if outside contractors were employed. Establishments are
required to take account of the following elements:
(a) Unavoidable
Costs
These are likely to
be costs which form part of the FEC of an activity, but would be common
whether the service was provided in-house or by an outside supplier. As an
example, the cost of internal audit services may not necessarily change
because of a decision to move an activity to an external contractor. Similar
considerations could apply in the case of policy and senior management time.
These are termed "unavoidable costs" and need to be excluded from
in-house costs in order to be comparable with external bids. A significant
part of the central overheads are likely to be unavoidable costs and these
will be deducted at source from the sums which will be communicated to
Establishments for inclusion in the costings. However, there may well be other
unavoidable costs at both Swindon Office and Establishment level, the
treatment of which may depend upon the unit being costed; these should be
dealt with at the evaluation stage. Establishments will therefore be required
to identify separately in their costings those elements which it believes fall
in the category of unavoidable costs.
(b) Other
Modifications
There could be
reductions from the FEC to reflect instances of temporary spare capacity or
loss of economies of scale which might arise if an in-house bid was
unsuccessful. The timing of when resources could either be re-deployed or
relinquished will be a crucial factor in these cases. If staff numbers,
accommodation, etc could be immediately reduced or transferred to other
activities, the FEC (ie the opportunity cost) should remain in the in-house
bid. However, in other cases it may not be possible to dispose of surplus
accommodation or plant and machinery; nor might there be alternative uses for
it. In these circumstances the savings would not materialise until the
buildings needed replacement. To include this in the opportunity cost of the
in-house bid could leave PPARC with higher total costs if a contractor's bid
was acceptable. (See the HM Treasury publication "Appraisal &
Evaluation in Central Government", also known as "The Green
Book", paragraphs 4.12 to 4.15 for further guidance concerning
"opportunity costs".)
The position is
unlikely to be clear-cut and there may be other relevant factors which need to
be taken into consideration. For example, a reduction in direct staff may
result in a reduction of workload for support areas, eg personnel. Although
this is unlikely to have an immediate effect on the staff numbers (or costs)
in those support sections, if there were other changes taking place from a
dynamic programme of market testing, the effects of successful external bids
could be accumulated to produce changes to the staffing of that activity. This
would result in a reduction of overhead costs.
(c) Sunk
Costs
When costing an
in-house bid, any previous expenditure which would have no realisable value
should not normally be included and should be regarded as a sunk cost. For
example, any consultancy costs of developing an in-house bid for market
testing should not be treated as part of the cost of the in-house activity,
given that the decision on whether or not to contract out would be taken after
completion of the bid. However, any future consultancy costs of assisting the
in-house operation if the bid was successful should be included.
(d) Costing
for equipment
Where the in-house
team use existing equipment which has no alternative use, and which would not
be due for replacement until after the expiry of the first contract period,
the value placed on the equipment for purposes of depreciation and interest on
capital should reflect this situation:
(i)
where the in-house team was the sole user and the equipment would be
disposed of if the in-house bid was unsuccessful, the valuation to be used
for purposes of depreciation and interest on capital could be based on the
recoverable amount rather than net current replacement cost;
(ii)
if the equipment was shared with other users there would be some spare
capacity until it was due for replacement. If the equipment would last
longer as a result of the in-house team not using it, the total of
depreciation and interest on capital of that equipment would reduce. That
reduction could be used as the amount to include in the in-house bid. If use
by the in-house team had no effect on the timing of replacement, the amount
of depreciation and interest on capital would be nil.
41.
As with unavoidable costs, Establishments will be best placed to determine when
modifications to the FEC of in-house activities are appropriate. Full details
should be provided by Establishments for these to be considered at the
evaluation stage.
43.
To recap from the foregoing paragraphs, the costing of activities subject to
market testing should be as follows:
(a) Existing
in-house service
(i) The FEC of the
existing in-house service (in order for PPARC to monitor the efficiency
savings on the areas market tested)
(b) Proposed
in-house service
(i) FEC
(ii) Less
unavoidable elements of operating service
(iii) Less
modifications to FEC
(iv) Below the
line: transfer and redundancy costs if in-house bid unsuccessful.
44.
In the evaluation process, cost comparisons will be made on figures expressed in
real terms. In-house bids should therefore be set out at constant price levels
of the first year of the contract period. GDP deflators should be used to bring
this to this price level. Current versions of these deflators are circulated to
key personnel in Swindon Office and at the Establishments, but can also be
obtained from Planning and Budgeting Group, PPARC Finance Division, Swindon
Office.
45. The
methodology to be used to compare in-house costs with contractors' tenders are
detailed in FM 301, Economic Appraisal of Projects in PPARC.
46.
In order to maintain a common approach across PPARC, costings of in-house bids
should be agreed with the PPARC Head of Finance, Swindon Office. All costing
elements should be clearly identified. This should be done before the evaluation
process to allow any amendments to be incorporated in the in-house bid.
47.
Any queries concerning the content or interpretation of this FM should be
referred to Paul Blackford, Planning & Budgeting, PPARC Finance Division,
Swindon Office, tel: 01793 442062, e-mail: paul.blackford@pparc.ac.uk.
Paul Blackford
Planning & Budgeting
PPARC Finance Division, Swindon Office
LIST OF ELEMENTS WHICH
COMPRISE THE FULL ECONOMIC COST OF AN ACTIVITY
The following is a list
of the more common items which comprise the FEC of an activity. Decisions
regarding cost apportionment are matters of judgement within Establishments.
A. CASH COSTS
Accommodation
Costs
-
Depreciation
of freehold and leasehold properties
-
Charges
for rented properties
-
Furniture
and fittings
-
Maintenance
-
Utilities
-
Contributions
in lieu of rates
Capitalised
Costs
-
Expenditure
capitalised and written off over a number of accounting periods (eg
production plant and machinery)
Bad
Debts
-
These
should be written off during the year and treated as a cost for the year
Common
Services
(Central and local)
-
Finance
and accounting
-
Legal
-
Personnel
-
Messengers
-
Reprographics
-
Secretarial
-
Security
[Local
costs may be either directly charged to activities or, as overheads,
apportioned between Establishments and/or activities.]
Depreciation
-
Depreciation
of other fixed assets, ie plant and machinery
Disposal
of Fixed Assets
-
The
surplus (residual value) or loss (cash cost) incurred on disposal
Insurance
-
Premiums
paid for commercial insurance cover (where applicable)
Office
Services
-
Maintenance
of office equipment, including computer systems
-
Postage
-
Printing
-
Telecommunications
Pay
Costs
-
Employers'
NI and Employer’s Superannuation Contributions
-
Gross
salaries and wages
-
Overtime
Personnel
overheads
-
Travel
and Subsistence
Stocks
and raw materials
-
Consumables
and equipment under £3k
-
Items
issued from store for use
-
Items
purchased for immediate use
Sub-contracted
items/services
-
Services
bought from external suppliers, including consultancy and professional
services
B.
NON-CASH
COSTS
Allied
services
-
'Free'
services from other departments must be valued and included in the cost
Cost
of capital
-
Public
sector bodies are required to effect a return (6%) on capital employed
(net). This is a measure of the cost to the economy of capital locked up
in public sector bodies. Costs should include a 6% return on the current
written down value of the capital employed
Insurance
-
Notional
cost of premiums where PPARC bears own risks.
The Fifth Framework
Programme focuses on Community activities in the field of research,
technological development and demonstration (RTD) for the period 1998 to 2002
GUIDELINES ON MAJOR
FINANCIAL PROVISIONS FOR COST REIMBURSEMENT CONTRACTS FOR RESEARCH AND
TECHNOLOGICAL DEVELOPMENT PROJECTS, DEMONSTRATION PROJECTS AND COMBINED PROJECTS