2.
This FM describes the procedures to be followed in drawing up agreements and
provides guidance on their drafting. This FM does not apply to contracts for the
purchase of goods or services (these are covered in detail in FM 401 or to
agreements associated with the purchase, lease, rental or sale of land and
buildings (these remain the responsibility of PPARC’s Legal Liaison Officer,
Personnel Group, Swindon Office).
3.
The term "agreement" is used within PPARC to describe the document
which sets out the terms on which a project is undertaken jointly with another
body or bodies (often PPARC’s foreign equivalents) where it is necessary to
set out unambiguously the aims of the collaboration and the respective
responsibilities of the parties to the collaboration. A typical agreement would
include details of funding arrangements, the provision of facilities, services,
staff effort and equipment and the management of the project. Examples of such
projects include joint funding for the support of research, development and use
of major facilities such as telescopes and particle accelerators.
4.
The terms "agreement" and "contract" are often used
interchangeably although this usage is not strictly correct; only legally
enforceable agreements may be described as contracts. A properly constructed
contract will always be legally enforceable whereas an agreement may not be. For
an agreement to be legally enforceable it must satisfy certain criteria and
these are set out in Annex A to this FM. In PPARC, the
term "contract" is usually used to describe a straightforward
buyer/seller relationship whilst the term "agreement" is usually used
to describe relationships with other non-commercial organisations where a range
of obligations are placed on both parties.
5.
Many different terms are used to describe collaboration agreements between PPARC
and its partners. Examples include: Letters of Agreement, Memorandum of
Understanding, Protocol, Statement of Intent, Heads of Agreement and Aide
Memoire. However, it should be noted that it is the terms of an agreement which
determines its legal enforceability, not its title so for the purposes of this
FM the term "agreement" will be used to cover all types.
6.
Those responsible for producing initial drafts of agreements should always
proceed on the basis that the resultant agreement will be legally enforceable.
If, as will almost always be the case, PPARC’s ability to fulfil its
obligations under an agreement is subject to availability of funding, staff
effort or equipment, the agreement should say so unambiguously and should commit
PPARC to perform only its "reasonable endeavours" (see Annex
B para 2).
7.
PPARC’s collaborators may suggest concluding a "Statement of Intent"
where it is thought necessary to agree certain principles and general
understandings in advance of a substantive main agreement. Such agreements are
often used to establish a framework under which a detailed substantive agreement
can be negotiated without formal commitment and in certain circumstances a
series of substantive agreements may be the final outcome. Great care must be
taken in drafting such agreements not to commit PPARC to anything other than an
undertaking to discuss the terms of a formal agreement at a later date.
8.
In certain circumstances it may be necessary to settle the major aspects of a
relationship in a substantive manner in advance of a detailed agreement which
covers every aspect of the collaboration. In such cases the initial agreement
may be presented to PPARC in the form of a "Heads of Agreement". This
type of agreement differs from a statement of intent in that formal commitments
will have been made in broad terms. This type of agreement implies that further
negotiations are necessary to establish the detailed nature of the relationship.
9.
A distinction needs to be drawn between inter-governmental and inter-agency
agreements. PPARC is able to enter into the latter type of agreement (eg
agreements with NWO) but not the former. Inter-agency agreements often follow on
from inter-governmental ones and it is usually appropriate to refer to the
inter-governmental agreement in the preamble to an inter-agency agreement.
However, where PPARC is required to advise on the contents of inter-governmental
agreements and to draft appropriate sections the principles of this FM apply.
10.
Before entering into any negotiation which might lead to an agreement being
concluded, those concerned must obtain the approval of the relevant Director (ie
the Establishment Director or the Director Programmes, as appropriate) to
proceed.
11.
Approval and authorisation of expenditure associated with a project to be
covered by an agreement, including allocation of in-house staff effort and
facilities, must be obtained in accordance with the procedures described in FM
101: Delegation of Financial Authority. Financial Propriety and Regularity
Section, PPARC Finance Division, Swindon Office (jill.drinkwater@pparc.ac.uk)
should be consulted if there are any queries concerning these aspects.
12.
It will often be necessary to undertake an economic appraisal as part of the
approval and authorisation process. FM 301: Economic
Appraisal provides the necessary guidance. The Planning and Budgeting Group of
PPARC’s Finance Division, Swindon Office should be consulted for advice on
this aspect (paul.blackford@pparc.ac.uk)
.
13.
Notwithstanding that the financial elements of an agreement may be within an
Establishment Director’s normal delegated authority in relation to contracts
for the supply of goods or services, agreements may raise broader issues which
merit special consideration. Agreements with overseas government departments
will require referral to OST. It is therefore necessary for all proposals to
enter into agreements to be agreed by the Director Administration. Proposals
should, in the first instance, be referred to the Head of Finance, PPARC through
the Head of Procurement. Consultation must take place at the earliest
opportunity and in any case before texts are agreed with the other
bodies/organisations involved. Where the drafting of the agreement falls to
PPARC, the Head of Procurement must be consulted before the first draft is
circulated to anyone outside of PPARC. General advice on agreements may be
obtained at any time from the Head of Procurement.
14.
Notwithstanding the level at which approval and authorisation have been given,
agreements may only be signed by the Chief Executive, the Director
Administration, the Head of Finance, PPARC, or a person specifically nominated
by one of these officers for the purpose. Where appropriate, Procurement Group
will arrange for an Establishment Director to be given delegated authority on a
one-off basis to sign on behalf of PPARC. In all cases the final text of the
agreement must first have been approved by the Head of Finance, PPARC.
15.
Where a joint-funding agreement provides for support by PPARC through the
mechanism of PPARC’s Research Grants Scheme, the Grants Section of Central
Group, Swindon Office should be consulted in the normal way about Grant
Additional Conditions and revised administrative procedures. Copies of the text
of any Grant Additional Conditions agreed with the Grants Section should be made
available to the Head of Procurement at the earliest opportunity as these may
have a bearing on the wording of the agreement itself.
16.
A checklist to assist in identifying issues to be considered in drawing up an
agreement can be found at Annex B to this FM.
17.
Model clauses for use in agreements, to assist those involved in preparing first
drafts, are available from Procurement Group, PPARC Finance Division, Swindon
Office. The Head of Procurement will also be happy to draft suitable clauses to
meet requirements not covered in the model clauses.
18.
Agreements should be treated as confidential to the organisations involved and
care should be taken not to make the contents known to third parties without the
consent of the other parties.
19.
Any queries concerning the content or interpretation of this FM should be
referred to Tom Hinde, Head of Procurement, PPARC Finance Division, Swindon
Office, tel: 01793 442045, e-mail: tom.hinde@pparc.ac.uk
.
THE KEY ELEMENTS OF
AN AGREEMENT WHICH MAKE IT A LEGALLY ENFORCEABLE CONTRACT
1.
The key elements which an agreement must have to be a valid and legally
enforceable contract are:
An offer
Acceptance of that
offer
Consideration
An intention by all
the parties to the agreement to create legally binding obligations
The parties must
have the legal capacity to enter into a contract
The agreement must
be legal and capable of performance
The offer and
acceptance
2.
In the context of agreements governing the use of major facilities the offer
is made when the first party signs the agreement and despatches it to the other
party. Acceptance takes place when the other party signs the agreement. Acceptance
must be unconditional.
Consideration
3. Consideration
is the legal term for the benefit which each party to a
contract receives as a result of the performance of the contract. Money is only
one example of consideration. In the context of agreements entered into by PPARC,
other examples include goods such as instrumentation for PPARC’s telescopes
and access to major facilities (eg observing time, beam time).
Legally binding
obligations
4.
Where an agreement has been reduced to writing, a general presumption exists
that the parties to that agreement intend to create legally binding
obligations. Where this is not the case it is important that an explicit and
unambiguous statement to this effect is included in the agreement. However, it
should be noted that such a statement may not in itself be sufficient to
persuade the Courts that there was no intention to create legal relations if the
wording of the rest of the agreement suggests otherwise.
Capacity
5. Capacity
is concerned with the legal authority to contract. In a business
context, only bodies which have what is known as "legal personality" (ie
corporate status) may make legally enforceable contracts although other bodies
may do so if they have been empowered to act on behalf of a body which does have
legal personality. As a corporate body PPARC is able to make enforceable
contracts. Whilst the Establishments are unable to enter into legally
enforceable contracts in their own right they are, of course, empowered to do so
on behalf of PPARC.
Capable of
performance
6.
To be legally enforceable an agreement must be capable of performance. It
must not be for an immoral or illegal purpose and cannot concern something that
would be impossible to achieve.
FURTHER GUIDANCE
7.
For further guidance on the principles involved see Section D of the DTI’s
Procurement Manual.
CHECK LIST OF ISSUES TO
BE CONSIDERED IN DRAWING UP AN AGREEMENT
Enforceability
1.
Is the agreement intended to be legally enforceable? If not, the wording should
make this clear. Such wording must be explicit, for example, stating that
neither party intends or wishes to create legally binding obligations
notwithstanding any apparent indications to the contrary contained elsewhere in
the agreement. It is not enough simply to state "this agreement will not be
legally binding" (in the event of a dispute between the parties, only the
Courts can decide whether or not a particular agreement is binding).
2.
Stating that the parties shall use their "best endeavours" to achieve
the objectives described will not necessarily result in an agreement being
regarded by the Courts as unenforceable. Indeed, in such a case the Courts would
examine the nature of each party’s efforts in order to establish whether those
efforts truly amounted to "best endeavours". The party whose
efforts were merely "good" as opposed to "best" could be
regarded as being in breach of contract. A better term to use would be
"reasonable endeavours". The word "reasonable" has been
tested in Court and is well understood.
Parties
3.
If the agreement is to be legally enforceable the parties must each have legal
personality. Where a PPARC Establishment is to take the leading role in the
performance of the agreement then the agreement should still name PPARC as one
of the parties but could reference the Establishment as in the following
example:
"This
Agreement is made between the XYZ Organisation of the United States of
America and the PPARC of the United Kingdom of Great Britain and Northern
Ireland acting through the UK Astronomy Technology Centre."
Definitions
4.
Any term which is given a special meaning within the context of the agreement
should be defined. Having been defined, the term should be given an initial
capital letter wherever it appears throughout the text. Acronyms and
abbreviations should also be defined.
Scope
5.
What is the aim or purpose of the agreement? This must be described
unambiguously.
Duration
6.
When is the agreement to start? When is it to end? Is the agreement intended to
cover work which has already started? Will the agreement be subject to review?
What are the possible consequences of each review? Might it be necessary to
bring the agreement to an end at an earlier date than originally envisaged
following a review? Might it become necessary to extend the agreement?
Termination
7.
Under what circumstances might it become necessary to terminate the agreement at
a date earlier than that envisaged in the duration clause (eg curtailment of
funding, increased costs, delay in completion of construction, lack of
scientific interest in use of the facility)? What period of notice would it be
reasonable for one party to give the other of its intention to terminate the
agreement? How will outstanding liabilities be treated? What are the
implications of early termination (eg refunds of sums already paid, access to
the other party's equipment, unused observing/beam time, demolition/disposal of
facilities, surrender of lease, restoration of site to former condition etc)?
Responsibilities
8.
The roles and responsibilities of each of the parties should be clearly and
unambiguously described and should be in sufficient detail to leave the reader
in no doubt as to the full extent of the obligations of each party especially
with regard to funding and provision of equipment or other resources.
Project Management
9.
How is the project to be managed and by whom? If a management committee is to be
set up, how will its membership be determined, when and how frequently will it
meet and to whom will it report? Ideally its terms of reference should be
incorporated into the agreement as an appendix. The Propriety and Regulatory
Section of PPARC’s Finance Division, Swindon Office, can advise on suitable
terms of reference for project management committees and must be consulted if it
is intended to set up a body with any peer review functions or delegated powers.
(See also FM 302: Project Management.)
Facilities
10.
Are PPARC facilities (eg workshops, telescope instrumentation, computers) to be
made available to other parties and, if so, on what basis? Is this in accordance
with the rules of that facility? Are any special costing dispensations or waiver
of charges sought? If so, the Accounting Section of PPARC’s Finance Division,
Swindon Office, must be consulted.
11.
Is a new facility to be built? Will its capacity be fully utilised? By what
mechanism will access to the facility be approved?
Equipment
12.
Is design or construction of equipment or instrumentation involved? What is the
timescale for its provision? Is the delivery date critical (eg is it tied to a
satellite launch date)? Have the responsibilities for supervision of the work
been clearly defined? What standards are to be used? If reference is made to
other documents (eg specifications and/or drawings) the version, the full title,
reference number and date of issue should be stated.
13.
Will acceptance tests be required? If so, how and where will these be conducted?
Who will supervise the tests?
14.
Who will own the equipment/instrumentation (a) during the currency of the
agreement and (b) following expiry of the agreement?
15.
Is the equipment/instrumentation to become an integral part of some other
facility? If so, what are the implications for the integrity of the facility in
the event that the equipment/instrumentation is removed at a later date?
16.
Who will be permitted to use the equipment/instrumentation and on what terms?
How is access time to be allocated?
17.
Will any of the parties (or their nominees eg PPARC’s Research Grant holders)
wish/need to install their own equipment at a facility forming the subject
matter of the agreement? If so, who is to take responsibility for any damage
caused to the facility during installation and/or removal of such equipment?
What are the terms and conditions governing installation and removal of such
equipment? How will the terms and conditions be made known to individual
researchers?
Personnel
18.
What personnel are required to carry out the work, operate the facility etc? Who
will employ these personnel? How will they be recruited and by whom? Who needs
to be involved in the selection of candidates? If PPARC in-house staff effort is
to be used, is this expected to be available at the right level and at the right
time?
Funding
19.
Who is to pay for what? What is the total value of PPARC's contribution
(including, where relevant, staff effort, equipment, beam time/observing time
etc, cash provided to the other party)? What is the total value of the
contribution(s) of the other party/parties? Has an economic appraisal been
carried out (see FM 301)? Is the budget determined in
cash planning terms? What method and frequency of payment is envisaged? In which
currency are payments to be made? What scope is there for variation in prices?
Will provision need to be made for variations in exchange rates? Will prices
need to be indexed linked and, if so, to which indices?
Site
20.
Who will own the site on which the facility forming the subject matter of the
agreement is located? (PPARC’s Legal Liaison Officer, Personnel Group, Swindon
Office, must be consulted where it is intended to acquire either land or
buildings for the purpose.) If a building is to be erected or made available,
who will own it and on what terms will it be made available to others including
third parties?
21.
Where an existing site is to be used, which party is to take responsibility for
negotiating terms of access with the owners? What involvement will the other
party/parties wish to have in this process?
Confidentiality
22.
What arrangements will be required in order to prevent unauthorised disclosure
of confidential material supplied by one party to another? In what
circumstances, if any, might it be necessary to disclose such material to third
parties (including the media)?
Intellectual
Property Rights
23.
Will it be necessary for any of the parties to disclose background intellectual
property (ie intellectual property which exists prior to commencement of the
agreement or which is developed outside of the scope of the agreement) to one
another during the performance of the agreement? Who will own intellectual
property developed by the parties during the performance of the agreement (ie
foreground intellectual property). What rights will the other parties
require/wish to have in respect of foreground intellectual property? On what
terms will third parties be permitted to use foreground intellectual property?
24.
What arrangements will apply in respect of intellectual property arising from
use (as opposed to the design, development and construction) of the
facility/instrumentation forming the subject matter of the agreement by
researchers? Will any special Research Grant conditions be required?
Data
25.
Who will own experimental data obtained by researchers using the
facility/instrumentation forming the subject matter of the agreement? Will
researchers be required to make the said data available for deposit in a common
archive? If so, when? Who controls access to that archive? On what terms is
access to the common archive permitted?
Publications
26.
What arrangements are needed for publicity concerning the subject matter of the
agreement (eg mutual agreement of text and date of release)?
27.
What restrictions (if any) will be necessary on publication of results obtained
by researchers using the facility/instrumentation forming the subject matter of
the agreement?
Liability
28.
Who will take responsibility for damage to the parties' property and/or that of
third parties and/or injury to persons caused during the performance of the
agreement? (PPARC's policy in respect of damage to property and injury to
persons is to disclaim liability for any damage or injury except that caused by
PPARC's own negligence.)
29.
What risks are associated with performance of the agreement and, where relevant,
use of facilities by third parties? Will access to the facilities be restricted
to academics? (Where time on a facility is sold to commercial researchers it may
be appropriate to take out insurance and charge the cost to the user.)
Indemnities
30.
Is the risk of damage or injury such that it is considered necessary to seek an
indemnity from the other party/parties in order to protect PPARC from claims
brought by third parties in respect of injury or damage caused by the other
party/parties or their researchers and/or to enable PPARC to recover its losses
in the event of damage being caused to PPARC property? Have the other parties
indicated that they will look to PPARC to indemnify them in respect of claims
brought by third parties in respect of injury or damage caused by PPARC or its
researchers? (PPARC's policy is to resist granting indemnities to other bodies,
particularly in the context of a collaboration involving organisations of an
academic character.) If the agreement is concerned with the development of an
existing PPARC facility what arrangements have been concluded in the past with
previous collaborators concerning liability for injury and damage?
31.
Where required, model indemnity clauses can be supplied by Procurement Group,
Swindon Office.
Disputes
32.
How is it envisaged that disputes will be handled? Where the parties wish to
avoid the expense of going to court to resolve a dispute, the agreement should
include provision for arbitration. The arbitration clause will need to stipulate
how many arbiters are to be appointed by each party and whether an independent
chairman is to be appointed and, if so, how that person is to be appointed in
the event that the arbiters fail to reach mutual agreement on the appointment.
The clause also needs to define the arbitration procedure to be adopted.
Amendments
33.
Unless an agreement contains a provision which expressly prohibits amendments,
there is a presumption that any agreement may be amended by the mutual agreement
of the parties. Whilst it is, therefore, unnecessary to state that the agreement
may be amended by the mutual agreement of the parties there is nothing to be
lost in doing so. All amendments should be made in writing and the wording to be
used should be approved by the Head of Finance, PPARC, or a suitably authorised
member of his staff.
Notices
34.
The agreement will need to specify the acceptable methods for the serving of any
notices which may be required under the agreement (eg notice of termination)
together with the relevant addresses. The terms of any notices must be agreed
with the Head of Finance, PPARC, or a suitably authorised member of his staff.
Law
35.
Which country's law is intended to apply to the agreement and in which country's
courts is it envisaged that proceedings would be brought? (As a matter of policy
PPARC prefers, for obvious reasons, that any agreement to which it is a party is
made subject to English law and the jurisdiction of the English Courts. However,
it may be difficult to persuade foreign organisations to agree to this
particularly where the facility forming the subject matter of the agreement is
located abroad.) Whilst the choice of law to apply to any contract is a matter
for agreement between the contracting parties, as a rule of thumb it would be
reasonable to expect the law of the country with which the agreement has the
closest connection to be chosen as the relevant law.