ETS PLANNING SCHEDULE:  MARCH 2007   February  / April

 

Mon

Tue

Wed

Thu

Fri

 

 

 

1

2

 

 

 

Restroom refurbish - >
RxW re-install ->


M1 mirror cooling: hoses->

Restroom refurbish - >
RxW re-install ->


M1 mirror cooling: hoses->

5

6

7

8

9

Gallery step ->
Restroom refurbish - >
RxW re-install ->



M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish ->
RxW re-install ->



M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - >
RxW re-install ->



M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - >
RxW recommission ->
HARP engineering- ->


M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - >
RxW recommission ->
HARP engineering- ->


M1 mirror cooling: hoses->

12

13

14

15

16

Gallery step - >
Restroom refurbish - >
RxW recommission ->
HARP engineering- ->



M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - >
RxW recommission ->
HARP engineering- ->



M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - >
RxW recommission ->
HARP engineering- ->


M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - >
RxW recommission ->
HARP engineering- ->




M1 mirror cooling: hoses->

Gallery step - >
Restroom refurbish - x
RxW recommission ->
HARP engineering- ->
C-mirror frame pre-align->

M1 mirror cooling: hoses->


20

21

22

23

Gallery step - >
RxW recommission ->
HARP engineering- ->
C-mirror frame pre-align->


M1 mirror cooling: hoses->


Gallery step - >
RxW recommission ->
HARP engineering- ->

C-mirror frame pre-align->

M1 mirror cooling: hoses->


Gallery step - >
RxW recommission -X
HARP engineering- ->
C-mirror frame pre-align->


M1 mirror cooling: hoses->

Galllery step - >
HARP engineering- ->
C-mirror frame pre-align->



M1 mirror cooling: hoses->

Gallery step - >
HARP engineering- ->

C-mirror frame pre-align->



M1 mirror cooling: hoses->

26

27

28

29

30

Prince Kuhio Day-Holiday

Gallery step - >
HARP engineering- ->
C-mirror frame pre-align->

WVM re-install ->

RxH re-install ->

 M1 mirror cooling: hoses->


Gallery step - >
HARP engineering- -X
C-mirrorframe pre-align->
WVM re-install ->
RxH re-install ->

M1 mirror cooling: hoses->


Gallery step - >
C-mirror frame pre-align->
WVM re-install ->

RxH re-install ->


M1 mirror cooling: hoses->

UKIRT AC replacement->
UIST Eng & Cool-down->

Gallery step - X
C-mirror frame pre-align->
WVM re-install - >

RxH re-install ->


M1 mirror cooling: hoses->

UKIRT AC replacement->
UIST Eng & cool-down->


 