ETS PLANNING SCHEDULE:  AUGUST 2007   July  / September

 

Mon

Tue

Wed

Thu

Fri

 

 

1

2

3

 

 



UKIRT SHUTDOWN- ->
WFCAM on telescope->
Mirror cooling lines installation>




UKIRT SHUTDOWN- -X
WFCAM on telescope->
Mirror cooling lines installation - ->





Mirror cooling lines installation ->

6

7

8

9

10



Mirror cooling lines installation ->



Mirror cooling lines installation ->



Mirror cooling lines installation ->



Mirror cooling lines installation ->



Mirror cooling lines installation ->

13

14

15

16

17



Mirror cooling lines installation ->
SCUBA-2 Integration
   Risk Meeting - SCC @ ATC


Mirror cooling lines installation ->



Mirror cooling lines installation ->



Mirror cooling lines installation ->

Statehood Day Holiday

20

21

22

23

24




Mirror cooling lines installation - ->



Mirror cooling lines installation - ->



Mirror cooling lines installation - ->



Mirror cooling lines installation ->



Mirror cooling lines installation ->

27

28

29

30

31



Mirror cooling lines installation ->
UIST array rotation - - - - >


Mirror cooling lines installation ->
UIST array rotation - - - - - - - ->


Mirror cooling lines installation ->
UIST array rotation - - - - - - - ->


Mirror cooling lines installation ->
UIST array rotation - - - - - - - -X



Mirror cooling lines installation ->

 
To be scheduled:    SCUBA-2 Infrastructure:            Railings:                                                   UKIRT:

                                  > Gallery cabling - TCC                  > Gallery                                                  M-1 Hardware - AJR
                                  > Chillers - TCC                               > Antenna/Carousel                              M-2 Silver coat - SCC
                                  > Computer Room - TCC            
RxW D/B Co-alignment - EGS              Widefield Screen - SCC

                                  > Link - AJR                                  Water Vapor Monitor - TCC   
                                  > Office conversion-MKD

Contact: Marjorie Dougherty. Updated: Tue Aug 7 14:10:47 HST 2007