 ETS PLANNING SCHEDULE:  April 2008  March / May

 

 

Monday

Tuesday

Wednesday

Thursday

Friday

 

 

 1

JCMT Closed - - - - - - >
SCUBA-2 Lift Prep - - X
Equipment Installation - X
Alignment  - - - - - - - - -X

 2

JCMT Closed - - - - - - >
SCUBA-2 Lift into JCMT - X

 3

JCMT Closed - - - - - - >
SCUBA-2
Fit Check & Alignment - >

 4

JCMT Closed - - - - - - >
SCUBA-2
Fit Check & Alignment - X


 7

JCMT Closed - - - - - - >
SCUBA-2
  Alignment - - >
  Frame Shimming

 8

JCMT Closed - - - - - - >
SCUBA-2
  Alignment - - >

 9

JCMT Closed - - - - - - >
SCUBA-2
  Alignment - - >

 10

JCMT Closed - - - - - - X
SCUBA-2
  Alignment - - X

 11

Contingency

 14

SCUBA-2 Disassembly - >
Alignment - - - - - - - >

 15

SCUBA-2 Disassembly - >
Alignment - - - - - - - >
Cryostat mounting
  brackets modification ->

 16

SCUBA-2 Assembly - >
Alignment - - - - - - - >
Cryostat mounting
  brackets modification -X

Turbo installation & traning-X
60k,4k rad shield removal
Mirror transportation
  bracket removal

Detectpr cpmtomiotu tests 450

 17

SCUBA-2 Disassembly - >
Alignment - - - - - - - >
Reconfigure DR
Detector continuity tests 850

 18

Contingency



 

 21

SCUBA-2 Assembly - >
DR install & training - ->
Cryostat grounding isolation->
60k filter removal & check
Compressor ship to JCMT
Array checks

 22

SCUBA-2 Assembly - ->
DR install & training - -X
Cryostat grounding isolation-X
CG array mounting
  in FPU & training - - ->
FPU assembly
1k box fit-up & training

 23

SCUBA-2 Assembly - ->


CG array mounting
  in FPU & training - - X
Shutter testing - - - ->
Compressor installation - ->

 24

SCUBA-2 Assembly - ->

He lines positioned
   on Control room


Shutter testing - - - >
Compressor installation - ->

 25

Contingency



 

 28

SCUBA-2 Assembly - ->
FPU mounting in 1k box -X
Festoon He line installation -X
Determine alignment laser
  adapter plate requirements-X
Control room roof
    railing installation - - - ->

Shutter testing - - X
Compressor installation - ->

 29

SCUBA-2 Assembly - ->
1k box installation
Move festoon hanger to
     gallery stow position -X
Instrument close-up - X
Control room roof
    railing installation  - - ->

Compressor installation - ->

 30

SCUBA-2 Assembly - ->
Services connection - -X
Continuity testing ->


Control room roof
    railing installation  - - ->


Compressor installation - -X

 

 

 

 

Contact: Marjorie Dougherty. Updated: Fri May 2 14:11:05 HST 2008