Monday
|
Tuesday
|
Wednesday
|
Thursday
|
Friday
|
|
|
1
JCMT
Closed - - - - - - >
SCUBA-2 Lift Prep - - X
Equipment Installation - X
Alignment - - - - - - - - -X |
2
JCMT
Closed - - - - - - >
SCUBA-2 Lift into JCMT - X |
3
JCMT
Closed - - - - - - >
SCUBA-2
Fit Check & Alignment - > |
4
JCMT
Closed - - - - - - >
SCUBA-2
Fit Check & Alignment - X
|
|
7
JCMT
Closed - - - - - - >
SCUBA-2
Alignment - - >
Frame Shimming
|
8
JCMT
Closed - - - - - - >
SCUBA-2
Alignment - - > |
9
JCMT
Closed - - - - - - >
SCUBA-2
Alignment - - > |
10
JCMT
Closed - - - - - - X
SCUBA-2
Alignment - - X |
11
Contingency
|
|
14
SCUBA-2
Disassembly - >
Alignment - - - - - - - >
|
15
SCUBA-2
Disassembly - >
Alignment - - - - - - - >
Cryostat
mounting
brackets modification
->
|
16
SCUBA-2
Assembly - >
Alignment - - - - - - - >
Cryostat mounting
brackets modification -X
Turbo
installation & traning-X
60k,4k rad shield removal
Mirror transportation
bracket removal
Detectpr cpmtomiotu tests 450
|
17
SCUBA-2 Disassembly - >
Alignment - - - - - - - >
Reconfigure DR
Detector continuity tests 850 |
18
Contingency
|
|
21
SCUBA-2
Assembly - >
DR install & training - ->
Cryostat
grounding isolation->
60k filter removal & check
Compressor ship to JCMT
Array checks |
22
SCUBA-2
Assembly - ->
DR install & training - -X
Cryostat grounding isolation-X
CG
array mounting
in FPU & training - - ->
FPU
assembly
1k box fit-up & training |
23
SCUBA-2
Assembly - ->
CG array mounting
in FPU & training - - X
Shutter
testing - - - ->
Compressor
installation - ->
|
24
SCUBA-2
Assembly - ->
He
lines positioned
on Control room
Shutter testing - - - >
Compressor
installation - ->
|
25
Contingency
|
|
28
SCUBA-2
Assembly - ->
FPU
mounting in 1k box -X
Festoon He line installation -X
Determine alignment laser
adapter plate requirements-X
Control room roof
railing installation - - - ->
Shutter testing - - X
Compressor installation - ->
|
29
SCUBA-2
Assembly - ->
1k box installation
Move festoon hanger to
gallery stow position -X
Instrument
close-up - X
Control room roof
railing installation - - ->
Compressor installation - ->
|
30
SCUBA-2
Assembly - ->
Services connection - -X
Continuity testing ->
Control room roof
railing installation - - ->
Compressor installation - -X
|
|
|