Monday
|
Tuesday
|
Wednesday
|
Thursday
|
Friday
|
|
|
|
|
1
SCUBA-2- ->
Instrument close-up &
testing-X
MCE check-out - - ->
|
2
|
|
5
SCUBA-2- - -
>
MCE check-out - - - ->
Begin pumping - - - - >
Comp
coolant line leak fix->
Complete
warm check out -X
Fit
black body
source and check - -X
Environmental testing - X
Alignment RTH prep work- X
Provide compressed 'air' -X
Connect services to cryostat-X
Window flush tests - X
|
6
SCUBA-2- - - >
MCE check out - - ->
Pumping - - - - - ->
Compressor coolant line leak fix-X
Cable
length audit - - - >
|
7
SCUBA-2- - - >
Mount MCEs & check out ->
Pumping - - - - -X
Cable length audit -X
Leak
check,
nitrogen backfill -X
Mounting bracket
installation & adjustment -X
|
8
SCUBA-2- - - >
Pump
->
Cryostat
grounding
provisions-X
|
9
SCUBA-2- - - >
Contingency
0900 S-2 Planning Meeting
|
|
12
JCMT Closed SCUBA-2-
- - ->
Vacuum checks, rise time
check - -X
Remove
HARP link,
install temporary He lines-X
Rotate antenna - - -X
Install 'drawbridge' - X
Adjust trunion mounting brackets - - X
Fit MCEs (2 off) in extreme
locations for fit checks -X
Isolation check - X
Spatial
alignment -X
Black body boy mods - -X
Compressor coolant lines leak repair - - >
|
13
JCMT Closed SCUBA-2-
- - ->
Ops system upgrade (HPS) -X
N2 tilt alignment -X
3rd MCE check out - X
Synch box check out - X
|
14
JCMT Closed SCUBA-2-
- - ->
Tilt alignment -
- ->
|
15
JCMT Closed SCUBA-2-
- - ->
Tilt alignment
- X
Mount black body source -X
S-2 equipment checklist
(including securing all items
on upper cryostat - X
|
16
JCMT Closed SCUBA-2-
- - ->
Isolation
pad modifications -X
Mount S-2
for final integration - X
Fit pumping line to DR &
tie back to structure - X
|
|
19
JCMT Closed SCUBA-2-
- - ->
Remove
'drawbridge' -X
Rotate antenna -X
Install HARP link -X
Telescope FCO - X
Connect DR lines -X
Pump DR lines - X
|
20
JCMT Closed SCUBA-2-
- - ->
Install
PTC He lines - - - - X
Install services including air
supply - - -X
Post installation alignment work -X
|
21
JCMT Closed SCUBA-2-
- - ->
Install
services - X
Connect cryostat grounding -X
Pump cryostat - X
Charge pulse tube coolers -X
Test PCTs -X
|
22
JCMT Closed SCUBA-2-
- - -X
Final
system check-out -X
Antenna FCO - X
Pre-cool prep |
23
Contingency day
Data
acquisitions (CAW,X.Gao)
|
|
26
Memorial Day Holiday

|
27
Cryostat cooling
MCE cabling
DR gate valve checks
LN2 pre-cool & switch on PTCs
|
28
Complete LN2 pre-cool & pump
|
29
On PTCs
Cool to 4k
|
30
On PTCs
Cool to 4k
|