  ETS PLANNING SCHEDULE:  May 2008 April / June

 

 

Monday

Tuesday

Wednesday

Thursday

Friday

 

 

 

 

 

 

 1

SCUBA-2- ->
Instrument close-up & testing-X
MCE check-out - - ->



 2




 5

SCUBA-2- - - >
MCE check-out - - - ->
Begin pumping - - - - >
Comp coolant line leak fix->
Complete warm check out -X
Fit black body
    source and check - -X
Environmental testing - X
Alignment RTH prep work- X
Provide compressed 'air' -X
Connect services to cryostat-X
Window flush tests - X

 6

SCUBA-2- - - >
MCE check out - - ->
Pumping - - - - - ->
Compressor coolant line leak fix-X
Cable length audit - - - >






 7

SCUBA-2- - - >
Mount MCEs & check out ->
Pumping  - - - - -X

Cable length audit -X
Leak check,
   nitrogen backfill -X
Mounting bracket
    installation & adjustment -X



 8

SCUBA-2- - - >
Pump ->
Cryostat grounding
     provisions-X






 9

SCUBA-2- - - >
Contingency
0900 S-2 Planning Meeting

 12

JCMT Closed SCUBA-2- - - ->
Vacuum checks, rise time check  - -X
Remove  HARP link,
    install temporary He lines-X
Rotate antenna - - -X
Install 'drawbridge' - X
Adjust trunion mounting brackets - - X
Fit MCEs (2 off) in extreme
  locations for fit checks -X
Isolation check - X
Spatial alignment  -X
Black body boy mods - -X
Compressor coolant lines leak repair - - >

 13

JCMT Closed SCUBA-2- - - ->
Ops system upgrade (HPS) -X
N2 tilt alignment -X
3rd MCE check out - X
Synch box check out - X

 14

JCMT Closed SCUBA-2- - - ->
Tilt alignment - - ->

 15

JCMT Closed SCUBA-2- - - ->
Tilt alignment - X
Mount black body source -X
S-2 equipment checklist
  (including securing all items
   on upper cryostat - X

 16

JCMT Closed SCUBA-2- - - ->
Isolation pad modifications -X
Mount S-2
  for final integration - X
Fit pumping line to DR &
  tie back to structure - X

 19

JCMT Closed SCUBA-2- - - ->
Remove 'drawbridge' -X
Rotate antenna -X
Install HARP link -X

Telescope FCO - X
Connect DR lines
-X
Pump DR lines - X

 20

JCMT Closed SCUBA-2- - - ->
Install PTC He lines - - - - X
Install services including air supply  - - -X
Post installation alignment work -X

 21

JCMT Closed SCUBA-2- - - ->
Install services  - X
Connect cryostat grounding -X
Pump cryostat - X
Charge pulse tube coolers -X
Test PCTs  -X



 22

JCMT Closed SCUBA-2- - - -X
Final system check-out -X
Antenna FCO - X


Pre-cool prep

 23

Contingency day

Data acquisitions (CAW,X.Gao)

 26

 

Memorial Day Holiday

 

 27

Cryostat cooling
MCE cabling
DR gate valve checks
LN2 pre-cool & switch on PTCs

 28

Complete LN2 pre-cool & pump


 29

On PTCs
Cool to 4k

 30

On PTCs
Cool to 4k

 

 

Contact: Marjorie Dougherty. Updated: Fri May 23 16:33:40 HST 2008