JAC Design Criteria
DESIGN & CONSTRUCTION POLICIES -
JAC, Hale Pohaku, JCMT & UKIRT
A. Policies
All equipment used in JAC facilities must be designed and constructed
to
provide the safest work environment possible, within acceptable
economic
and operational limitations. If adequate controls are included in the
engineering
designs, the risks associated with most, if not all, credible hazards
can
be reduced to an acceptable level. This chapter sets out policies and
procedures
specific to the design of equipment, and to any aspects of the
construction
which are required to fulfill the design.
B. Responsibilities
The provisions of this chapter are applicable to JAC staff who manage,
design, construct, specify for purchase or inspect equipment used in
JAC
facilities. External suppliers are responsible for providing safe
equipment
and appropriate documentation.
1. JAC Project Manager:
- A JAC Project Manager will be appointed for each major design and
construction
project where new equipment will be installed at JAC facilities, or
where
existing equipment will be substantially modified.
- The JAC Project Manager is responsible for assuring that new
equipment
is of a safe design. In particular the JAC Project Manager shall assure
that:
- Any hazards are identified during the design process.
- Appropriate safety standards, to ensure compliance with the law
and
ensure
safety, are identified and followed.
- Documentation is produced and stored which is sufficient to
demonstrate
safe design and that the design was correctly implemented during
construction
and testing.
- Documentation is produced and issued outlining safe operations
and
maintenance
procedures.
- Note that appropriate liaison with external bodies or
other
JAC staff
may be required to achieve the above. This may be particularly required
where the bulk of the equipment design is performed by an external
supplier
in collaboration with JAC staff.
2. Heads of Groups:
- In the absence of a designated JAC Project Manager, the above
responsibilities
will fall upon the head of the relevant JAC Group.
- The heads of groups also have particular responsibility to ensure
that
their staff are competent (qualified) for tasks assigned to them.
3. Site Safety Advisor:
The Site Safety Advisor has particular responsibility for retaining
safety certificates which show proof of testing where legal
requirements
exists.
C. Design and Construction Procedures:
General
This section provides an overview of the Design and Construction
procedures
in use by the JAC to ensure safe design and compliance with the law.
The
subsequent sections E-F
then
cover specific details associated with different classes of equipment.
It is important to note that many items of equipment - particularly
"instruments"
may fall under several categories. The treatment of existing equipment
is discussed in section G.
1. Design Process
- Design Reviews
- Reviews which include coverage of safety shall be held at
appropriate
stages
in the project.
- The format of these reviews may be varied at the discretion of
the JAC
Project manager. A typical design review structure is:
- As early as possible in the design process a Preliminary
Design
Review
(PDR) should include an examination of all relevant safety issues.
This will include identification of hazards which could be mitigated by
design, including the use of appropriate national consensus codes.
- Prior to completion of the design a Critical Design
Review (CDR) should
include assurance that all safety issues have been dealt with
satisfactorily
and that no new issues now exist.
- Where appropriate, 'Acceptance Test' criteria shall
include
demonstration
that any necessary safety criteria have been met.
- Design Activity
- The JAC Project Manager should assure that the design is
performed by
competent
(qualified) persons.
- The Design Engineer shall use good engineering practice, and
shall
determine
and follow applicable codes and standards, analyze the design for
hazards,
and take appropriate steps to eliminate hazards or reduce the risks to
an acceptable level.
- The Design Engineer shall identify relevant design, material or
construction
codes and specify these as part of the design, where appropriate.
- Where safety critical calculations are required they shall be
checked
by
another qualified person and then retained for the life of the item.
- Equipment shall be designed to allow safe access for
maintenance or
repair.
This shall include the ability to provide for safe lock-out and tag-out
of all energy sources. See also
Chapter 13 of the JAC Safety Manual for information.
Note: the term Design Engineer is used throughout this chapter to
designate
the competent (qualified) person - usually a professional
engineer
- responsible for the overall development of the concept and detailed
design.
This phrase is used to avoid confusion over differing common usage for
the phrase 'Designer' . (e.g. in UK use often designates a senior
engineer
with design authority and in the US often designates a draftsperson
with
little design authority). - Documentation
- Documentation, including drawings, shall be maintained at a
level
adequate
to demonstrate safe design. The retention of design information in a
retrievable
format is the responsibility of the JAC Project Manager. The JAC
documentation
system for design information is as described in Appendix
3 to this Chapter.
- Equipment with more than one energy source (e.g. electrical and
hydraulic
power) will require a written procedure for lock-out and tag-out. The
JAC
Project Manager shall assure that any new written procedures required
are
incorporated into Chapter
13,
Appendix 3 of the JAC Safety Manual.
- Where materials are introduced to JAC facilities the JAC
Project
Manager
shall ensure that Material Safety Data Sheets are made available as
described
in Chapter 6 of the JAC Safety Manual.
2. Construction Process
- Note that this section is not concerned with safe workshop
practices
(which
are covered in Chapter 8 of the JAC
Safety Manual) but rather with
ensuring
that any safety critical design requirements are met during the
construction
process.
- For all in-house JAC work technicians and construction workers
shall
use
approved work practices and produce a quality product that meets design
and code requirements where specified.
- JAC use a policy of self certification and inspection, whereby
technician
is responsible for assuring that items are constructed and installed as
specified by the design drawings. The JAC Project Manager shall arrange
for inspection of contract work where required.
- Where the design requirements cannot be met, the Design
Engineer must
be
consulted for an approved solution.
- Note that JAC technicians have considerable experience and
are
encouraged
to highlight areas where design flaws may exist, or where alternative
manufacture
techniques would have merit.
3. Testing and Commissioning
- For safety critical equipment a description of tests required
before
first
use, and any routine inspection requirements, shall be provided by the
design engineer as part of the design package.
- Before releasing any equipment for general use the appropriate
tests
and
commissioning procedures - as specified in the design of the equipment
- shall be performed. These will be witnessed by a competent person,
and
relevant documentation made.
4. Codes and standards
- Where relevant, legal requirements shall be met in the design of
equipment.
In this context, some relevant legislation includes:
- The UK "Provision and Use of Work Equipment Regulations 1998",
UK HSE
- The UK "Workplace (Health, Safety and Welfare) Regulations
1998", UK HSE
- The Hawaii Uniform Building Code (UBC).
- Where practicable, relevant national consensus codes shall be
used for
the design of equipment. Some useful codes are identified where
appropriate
in the specific Procedures sections below.
- In addition to national consensus codes, the JAC Project Manager
shall
draw to the attention of the equipment design engineer the environment
at the Joint Astronomy Centre's sea level and Mauna Kea facilities for
which items must be designed. (See
Appendix
2 to this Chapter).
Notes:
- See also the note in Chapter 1.Fof the JAC Safety
Manual regarding
JAC policy for international equivalent codes.
- Compliance with local codes in the country of manufacturer
is
the responsibility
of the supplier, wherever the equipment is used in that location prior
to shipment to JAC.
D. Design and Construction
Procedures:
Mechanical
1. Lifting Equipment
1.1 Description
- Lifting equipment is particularly critical to human and equipment
safety.
Many items used at JAC facilities must be handled with lifting
equipment
for transport, loading and assembly as well as when mounting onto the
telescopes
or any off-telescope test rigs. It is therefore important that the
lifting
gear is safe, complies with the law and with relevant professional
codes
of practice.
- Lifting equipment includes the lifting device (e.g. crane), the
lifting
tackle between the crane hook and the load, attachment points to the
load,
as well as the load itself.
- Note that this section is not concerned with safe lifting
practices
(which
are covered in Chapter 8.C of
the JAC Safety Manual) but rather
with
ensuring that any safety critical design requirements are met during
the
design and construction process.
1.2 Requirements:
- Lifting Devices
- JAC must be able to demonstrate legal compliance for all parts
of the
lifting
system, regardless of the source of supply.
- Where practicable, lifting equipment shall be specified and
purchased
from
qualified commercial suppliers. These shall be compliant with the
appropriate
codes and shall be supplied with the appropriate documentation.
- General Design
- The design shall comply to a national consensus code and
shall be safe.
- The design environment is as laid out in Appendix
2 to this Chapter. The key features for design of lifting equipment
are:
- Potentials for corrosion in a tropical environment when in
Hilo.
- Possible low-temperature when at the summit of Mauna Kea.
- Lifting eyebolts shall have a preferred size metric thread.
- Lifting equipment supplied with instruments shall have been
designed
with
over-capacity to allow for weight growth due to future upgrades to the
instrument. This is in addition to the normal safety reserves,
allowance
for errors in estimating equipment mass and any allowance for proof
testing
in the design codes. The minimum allowance for a growth in mass is 25%
(e.g. a 200kg instrument shall have lifting equipment designed on the
assumption
that in 5 years time the instrument may mass 250kg).
- Non-compliant equipment
- Should JAC find that supplied equipment was not compliant
with an
appropriate
national consensus code, the options would be to either reject the
equipment,
or to arrange for retroactive certification at the supplier's cost.
- Note that retroactive certification will not be possible
where design
or
construction documentation are not available where required.
- Below the Hook Lifting Devices:
- For a description of Below the Hook Lifting Devices see the
latest
issue
of ASME B30.20.
- In addition to compliance with the selected code, JAC require
that
these
devices have been proof tested to at least 125% of the marked Safe
Working
Load.
- In addition to compliance with the selected code, JAC require
that
these
devices are delivered with the following:
- Have marked on it: the Safe Working Load marked in lb. or
kg.; the
equipment
identification number (drawing number, serial number or similar); the
date
of manufacture; the manufacturer's name and the lifting device's mass
if
greater than 15kg.
- Markings in "ton(ne)s" in any form are unacceptable.
- Manufacturing support documentation shall be supplied to
cover, where
appropriate:
evidence of proof testing; instructions for use; and manufacturing
documentation
including material supply certificates, material cast certificates and
approved welder certification.
- Design of Instruments and other Equipment which will be
lifted.
- In designing equipment for use at the JAC, consideration of
lifting
operations
shall be given. Note that this section is particularly applicable to
instruments
and electronics racks from external supply sources.
- All equipment shall have a mechanical body or framework with
sufficient
integrity to survive transport, operational and handling loads and
remain
safe. Note that per UK LOLER-98 4.b the [JAC] "shall ensure that every
part of a load or anything attached to it and used in lifting is of
adequate
strength."
- All equipment should be designed such that it may be safely
prepared
for
lifting.
- In particular JAC requires:
- Assurance that the lifting points on all equipment are safe.
This shall
be verified before any lifting takes place at JAC facilities.
- The maximum (measured) mass and the approximate location of
the centre
of gravity of all instruments must be provided to JAC before acceptance.
1.3 Codes, Testing and certification
- Where relevant, legal requirements shall be met in the design of
lifting
equipment. This includes the UK HSE Lifting Operations & Lifting
Equipment
Regulations 1998 (LOLER-98).
- Relevant national consensus codes shall be used for the design of
lifting
equipment, such as:
- ASME B30 "Safety Standard for cableways, cranes, derricks,
hoists,
hooks,
jacks and slings".
- BS 2573:Part 1:1983 "Rules for the design of cranes".
2. Load Bearing Structures
2.1 Description
- Load Bearing Structures are critical to human and equipment
safety.
They
include any items which bear or anchor the weight of personnel, or
which
carry loads where the load falling would create an unsafe condition for
personnel.
- Note that this section is not concerned with the safe working
practices
(which are covered in Chapter 8 of
the JAC Safety Manual) but rather
with
ensuring that any safety critical design requirements are met during
the
design and construction process.
2.2 Requirements:
- Where practicable, load bearing structures will be specified and
purchased
from qualified commercial suppliers. These shall be compliant with the
relevant codes, and shall be supplied with appropriate documentation.
- Compliance with local county ordinances may require the drawing
of
permits
to modify existing buildings.
- Design calculations for the structure shall have been made and
checked
where required to demonstrate safety.
- Testing requirements shall be specified by the Design Engineer
where
required.
- The design details shall include appropriate markings, which may
include:
- Safe floor loading markings.
- The equipment serial number and the date of manufacture.
2.3 Codes, Testing and Certification
- Where relevant, legal requirements shall be met in the design of
load-bearing
structures. In this context some relevant legislation includes:
- The requirements of OSHA and the Hawaii UBC where applicable.
- The UK "Workplace (Health, Safety and Welfare) Regulations
1992", UK HSE
- Note that where these codes do not apply due to the unique
design features
of the JCMT or UKIRT facilities, JAC practice shall remain to
voluntarily
comply with the spirit of these codes wherever practicable.
- Relevant national consensus codes shall be used for the design of
load-bearing
structures, such as:
- BS 5950:1:1990 "Structural use of steelwork in building".
- BS 8118:1:1991 "Structural use of aluminium".
- BS 7608:1993 "Code of practice for fatigue design and
assessment of
steel
structures"
- BS 5378:1:1980 "Safety signs and colours".
- Appropriate specifications will be made for:
- Material type and any requirement for material certificates.
- Weld procedures, materials and geometry.
- Welder qualification for load bearing weldments.
- Tests required.
- Following construction the structure shall be inspected and tests
performed
as required. In particular all anchor points for personnel fall
protection
equipment shall be load tested to meet the requirements of OSHA.
3. Personnel Accessways
3.1 Description
- Personnel Accessways include walkways, doorways, stairways,
ladders and
associated handrailing. For full definitions see the relevant code
provisions.
- Temporary accessways and scaffold must also comply with safe
design
requirements
3.2 Requirements:
- The design of personnel accessways shall be compliant with
relevant
codes,
and shall be supplied with all appropriate documentation.
- Note that personnel accessways are also Load Bearing structures
and as
such are also covered by section D.2 above.
- Temporary accessways and scaffold shall also be designed in
accordance
with the appropriate codes and shall be constructed by competent
persons
using equipment suitable for the task.
3.3 Codes, Testing and Certification
- Where relevant, legal requirements shall be met in the design of
personnel
accessways. In this context some relevant legislation includes:
- The requirements of OSHA and the Hawaii UBC where applicable.
- The UK "Workplace (Health, Safety and Welfare) Regulations
1992", UK HSE
Note that where these codes do not apply due to the unique
design
features of the JCMT or UKIRT facilities, JAC practice shall remain to
voluntarily comply with the spirit of these codes wherever practicable.
- Relevant national consensus codes shall be used for the design of
personnel
accessways, such as:
- BS 6180:1982 "Code of practice for protective barriers in and
about
buildings".
- BS 5395:1985 "Code of practice for the design of industrial
type
stairs,
permanent ladders and walkways".
4. Instrument and Cryogenic Systems
4.1 Description
- This section outlines the JAC requirements for safe design and
construction
of instruments with their associated cryogenic and vacuum equipment.
- JAC does not normally design or build instruments in house, but
does
often
interact with or overwatch external design activities.
- In addition, JAC routinely provides in-house design and
construction of
interfaces, distribution piping and valve systems. Occasional repair or
retrofit to existing equipment is also performed where required.
- A typical instrument in use at the JAC consists of several
components:
- The main instrument body, or "Dewar". A Dewar is a vessel
isolated by
vacuum,
highly reflecting walls and radiation screens used to achieve and
maintain
cryogenic temperatures. Whilst primarily a vacuum vessel, a positive
pressure
may occur at certain times eg: when warming up in some fault conditions.
- Insulation provided by a combination of vacuum, radiation
shields and
insulation
layers.
- Cryogenic cooling provided by a combination of cryogens and
cooling
machines
(e.g. Joule-Thompson or Gifford-MacMahon closed cycle coolers). The
cryogens
are usually liquid Nitrogen or Helium (though may be gaseous or even
solid
in some areas of the instrument at some times in the process).
- A "window" of material transparent at the appropriate
wavelengths. This
is often optimized for optical properties and is frequently the weakest
and most vulnerable part of the vacuum vessel.
- The internal instrument components including electronic,
electrical and
mechanical devices.
- External mechanical mounting interfaces to the telescope and
handling
gear.
- Supporting electronics, mounted nearby or remotely.
- Supporting software package(s).
- Service distribution lines and equipment for electrical power,
electronic
control, vacuum, coolant or cryogens as required.
- Supporting documentation.
- Note that this section is not concerned with the safe cryogen or
vacuum
handling practices (which are covered in Chapter 5 of the JAC Sarfety Manual)
but rather with ensuring that any safety critical design requirements
are
met during the construction process.
4.2 Requirements
- Where practicable equipment shall be specified and purchased from
qualified
commercial suppliers. These shall be compliant with the appropriate
codes
and shall be supplied with all appropriate documentation.
- The equipment design shall be safe at the pressures and
temperatures
which
may be encountered. This should include conditions encountered in
normal
usage, or when cooling down or warming up, or in certain fault or
blockage
conditions. Equipment from commercial supply sources shall where
possible
be rated for the design environment encountered at JAC facilities.
- Overpressure relief mechanisms shall be provided in all
appropriate
locations.
- When designing venting arrangements, consideration shall be given
to
avoiding
possible hazards to personnel.
- Instruments should also comply with the provision for Manual
Handling (section
D.5) and Ergonomics (section D.6).
- For dewars, particular attention shall be given to:
- Appropriate design of vacuum and pressure vessels,
incorporating
appropriate
safety reserves. This shall include a review of the implications of
failure
of the window (or other vulnerable points) on the dewar integrity,
especially
any catastrophic loss of vacuum or pressure; or any potential for
spillage
or warm up of cryogens.
- Design of the window material, which must include review of a
documented
analysis of the window design process, including:
- The window design drawings.
- The material properties.
- The strength calculations and/or experimental tests performed
in
selecting
the design.
- The expected safety reserves against failure at JAC sea level
and Mauna
Kea facilities.
- Documentation of any safety precautions, guards or working
practices
required
to enhance safety.
- Appropriate design of vessels containing hazardous materials
such as
liquid
cryogens.
- Specification of materials appropriate for use at cryogenic
temperatures
where applicable.
- Venting capacity, for example upon initial contact of cryogens
with the
warm system shall be adequate for safety.
- The stresses from thermal contraction and expansion of the
inner shell
and support members.
The above requirements must be met and approved in writing by the
JAC
Chief Engineer prior to final acceptance or operation of any instrument
at any JAC facility. - For Piping and Distribution Systems
particular attention shall be
given
to:
- Appropriate design for the type of fluid.
- Any risks which might arise from system leaks, in particular
hazardous
chemicals exposure or risk of fire.
4.3 Codes, Testing and certification
- Codes:
- Where relevant, legal requirements shall be met in the design
of
equipment.
In this context, some relevant legislation includes:
- The UK Simple Pressure Vessels (safety) Regulations 1994.
- Equipment supplied shall comply to a relevant national
consensus codes,
such as :
- Section VIII of the ASME Boiler and Pressure Vessel Code
- BS 5500:1991 "Unfired fusion welded pressure vessel".
- BS EN 1012-1 1997 "Compressors and vacuum pumps. Safety
requirements".
Note that, although not strictly applicable, there are some
useful
provisions in the UK HSE document :"Design and Construction of vacuum
insulated
road tankers used for the carriage of non-toxic deeply refrigerated
gases:
Road Traffic (Carriage of Dangerous Substances in Road Tankers and Tank
Containers) Regulations 1992".
- Testing
- Prior to acceptance by JAC all cryogenic systems, particularly
the
dewar
assembly, shall have passed a thermal shock test (initial cool down to
operational temperatures) with no loss of integrity.
- All vacuum vessels shall have passed a pump-down test (in
operational
configuration,
to operational vacuum) with no loss of integrity prior to acceptance by
JAC.
- Consideration shall be given to the need to perform
over-pressure tests
of equipment.
- Following receipt at JAC the equipment integrity should be
re-verified
to ensure that no damage has occurred during transit. Note that in
addition
to visual inspection, the initial vacuum pump down test will generally
act as a suitable detection technique for structural flaws such as
warpage
of seal faces or through-thickness cracks.
5. Manual Handling
Requirements
5.1 Description
- In many cases human effort is required to move or position
equipment,
with
or without mechanical assistance. One useful definition of manual
handling
is:
"Manual Handling means any transporting or supporting of
a load (including the lifting, putting down, pushing, pulling, carrying
or moving thereof) by hand or by bodily force" (UK Manual Handling
Operations Regulations 1992, UK HSE).
- Manual handling has a variety of associated hazards, including
the risk
of injury from falling objects, attempting to lift dangerously heavy or
awkward objects, or muscular injury through repetitiously lifting
objects
in an un-ergonomic manner.
- Where practicable, the need for manual handling of equipment or
components
should be minimized. To this end, the manual handling implications
should
be reviewed as early as possible in the design process, and also
considered
during subsequent reviews and testing.
5.2 Requirements:
- All items which require manual handling should be designed to
comply
with
good manual handling practice.
- Some design guidelines to consider, include:
- Modules designed for manual handling (lifting and carrying)
should in
general
weigh no more than 20kg, and preferably less than 15kg.
- Adequate handholds should be provided for safe lifting. It
should be
clear
whether the handholds are for use with only the sub-module to which
they
are attached or to a higher level (heavier) assembly.
- The mass should be clearly labeled, if more than 15kg, and a
note made
on the centre of gravity where this is not in an obvious location.
- Any special hazards should be clearly identified, in particular:
- Sharp edges.
- Risk of static electrical shock, with grounding points
provided where
required.
- Any items which are not secure in particular orientations.
- Appropriate written procedures and training should be provided
which
describe
the recommended handling technique, in particular where:
- Special hazards exist,
- Multi-person lifts are required,
- Special handling equipment is required.
- Special handling equipment should be provided where appropriate.
- The equipment should be designed such that it may be easily
accessed
for
manual handling, for example to:
- Remove or secure fixing points and handling equipment.
- To lift components safely, preferably in a vertical direction
with a
single
lift.
- Pick up or place down components without risk of trapping
fingers, etc.
5.3 Codes, Testing and Certification
- Where relevant, legal requirements shall be met in the design of
equipment
requiring manual handling . In this context some relevant legislation
includes:
- The UK "Manual Handling Operations Regulations 1992".
- Where practicable, relevant national consensus codes shall be
used for
the design of equipment requiring manual handling.
6. Access and Ergonomic
Requirements
6.1 Description
- The equipment shall be designed such that it may be safely
accessed at
all stages of assembly, test, installation, use, maintenance and repair.
- In general, good ergonomic design practice for ease of
installation,
use
and maintenance is preferred where practical.
- The review process must include a check that no unsafe
ergonomic
hazards exist.
6.2 Requirements:
- The equipment shall be designed such that it may be safely
accessed,
and
that appropriate provisions exist for lock-out and tag-out of all
energy
sources during:
- Routine maintenance including inspection, greasing, testing,
cryogenic
fills, tuning, calibration.
- Troubleshooting of electrical or mechanical problems in-situ.
- Repair.
- There shall be no requirement to work in areas without rapid
means of
egress.
- Adequate provisions must exist for lock-out and tag-out of all
energy
sources
during maintenance and repair.
- The design and layout should allow safe handling of hazardous
substances
(e.g.. cryogenic or high voltage electrical equipment).
- In cases where there is no safe access to a side of equipment
(e.g..
due
to walls or other structures) the design should be such that no access
is required to this side. Alternatively, the equipment should be
provided
with the capability to roll-out or similarly move, such as to allow
safe
access.
- Hazards from exposed or moving machinery shall be eliminated or
suitable
guards provided.
- Consideration should be given to good ergonomic practice to
facilitate
installation, maintenance and assembly. This is particularly useful
given
the cold, arduous, environment in which much work is performed at the
JAC.
6.3 Codes, Testing and Certification
- Where relevant, legal requirements shall be met in the ergonomic
design
of equipment.
- Equipment ergonomics should comply to relevant national consensus
codes.
E. Design and Construction
Procedures:
Electrical & Electronic
1. Electronic And Electrical Equipment
1.1 Description
- This section covers the repair, modification and design of all
electrical and electronic equipment, including
energy storage and distribution systems.
- Note that this section is not concerned with safe electrical work
practices
(which are covered in Chapter 12 of
the JAC Safety Manual) but rather with
ensuring that any safety critical design requirements are included
during
the construction process.
1.2 Requirements:
- All designs and construction standards shall be compliant with
relevant
codes listed below, and the installation shall be supplied with all
appropriate
documentation.
- Where practicable, equipment will be specified and purchased from
qualified
commercial suppliers.
- The design shall include appropriate provisions for lock-out and
tag-out
of all energy sources during maintenance and repair.
- Where necessary, the equipment shall be adequately designed to
function
safely in the Mauna Kea design environment. This is described in
Appendix
2, and the key areas of concern for electrical equipment include:
- High altitude (particularly de-rating of cooling and hence
power
capabilities).
- Low temperature and icing.
- Water ingress to the JCMT or UKIRT facilities, including up to
1" of
standing
water in the basements of either building.
- When purchases of major electrical or electronic equipment are
being
made,
consideration should be given to including the requirements set out in Appendix
1 to this chapter.
1.3 Codes, Testing and Certification
- Where relevant, legal requirements shall be met in the design of
electrical
and electronic equipment. In this context, some relevant legislation
includes:
- The UK Electrical Equipment (Safety) Regulations 1994.
- The UK Provision and Use of Work Equipment Regulations 1998.
- Where necessary, in conjunction with modifications:
- Local county electrical permits will be drawn for installation
or
construction
work.
- Only licensed personnel will be permitted to install or modify
electrical
equipment.
- Electrical and electronic equipment should comply to relevant
national
consensus codes, such as:
- The American National Electrical Safety Code.
- The US National Electrical Code (NEC) handbook, latest issue.
- Equipment listing requirements are explained in Appendix
1.
- Testing of new or modified systems shall be as directed by the
design
engineer
.
F. Design and Installation
Procedures:
Software
1. Safety Relevant Software
1.1 Description
- UKIRT and JCMT design practice is that software is not
relied
upon to provide protection of personnel. Wherever protection is
required
it is provided by hardware interlocks.
- The design of the hardware interlock shall comply to the relevant
portions
of this manual, and shall be such that it cannot be over-ridden or
bypassed
by any software. The hardware interlock may be mechanical or electrical
and examples include emergency stops, locking pins and lock-out systems.
- Software, however, remains a major component in the control of a
large
and complex telescope facility, and as such the design shall be
reviewed
to ensure that it does not constitute an added hazard.
1.2 Requirements:
- For new software projects, or updates to existing software the
JAC
Project
Manager shall arrange for appropriate design reviews.
- Consideration shall be made as to whether the software meets the
design
practice outlined in section F.1/1/1/1 above. This review shall confirm
that :
- The software is not relied upon to provide
protection of
personnel.
- Wherever protection is provided by hardware interlocks, the
interlocks
cannot be overridden by any other system.
1.3 Codes, Testing and Certification
When testing the software, particular attention shall be given to the
interaction of the software under test with other systems or staff and
appropriate safety precautions taken.
G. Review of Existing
Equipment
1. Description
- The JAC has a significant amount of equipment designed and
constructed
prior to the release of this document. This includes the telescopes
themselves,
instruments and support equipment, and the equipment age encompasses a
range of original manufacture dates, in some cases earlier than 1979 or
as late as 1997.
- Additionally, several instruments currently under construction
for
supply
to JAC were specified and designed prior to release of this document,
with
original design review dates as early as 1990. Much of the hardware for
this equipment is now in the late stages of design and manufacture and
is scheduled to arrive at JAC over a range of dates from mid 1997 to
2000.
- JAC undertakes an active safety management process which aims to
continually
improve staff safety. If in the course of this process existing
equipment
is found which is believed to be unsafe, this section shall be used as
a basis for review of the situation and corrective action.
2. Existing Equipment at JAC facilities
- Existing equipment at the JAC facilities is subject to regular
review
by
processes including Safety Tours and Risk Assessment (Chapter
1 section A2j), and the ongoing awareness and duties of the JAC's
staff
under safety legislation. Certain equipment, such as lifting devices,
are
also subject to statutory inspection schedules.
- Where equipment is found which is thought to be unsafe then a
review of
the equipment shall be arranged by the JAC Chief Engineer who shall
have
sole discretion to withdraw it from service until the review has been
held.
- The review shall cover:
- A description of the equipment.
- Why it is thought to be unsafe, e.g. due to deficient design,
deficient
construction practices, deficient supporting documentation, or a
changed
legal requirements since the date of manufacture.
- A risk assessment of the hazard posed in order to place the
review into
an appropriate safety context.
- An assessment of the work required to rectify the deficiency in
order
to
establish practicality.
- A "Sentence" of the equipment shall be made which takes into
account
all
the above factors.
- The Sentence shall be one of the following:
- To approve the equipment as safe without reservations.
- To approve the equipment for use, provided that certain
rectification
work
is performed before use, such as appropriate:
- Design calculations
- Proof testing
- Retrofit modifications.
- To permit the temporary continued use of the equipment. In
this event:
- A date shall set by which the equipment must be replaced.
- The equipment shall be suitably marked with the phrase "DO
NOT USE
AFTER
<DATE>".
- To condemn the equipment. In this event:
- The equipment shall be suitably marked with the phrase
"CONDEMNED AS
UNSAFE".
- The JAC Chief Engineer shall arrange for immediate disposal.
- The review should also consider whether any similar equipment
might be
in use at any JAC site that, by analogy, might also require
investigation.
- A record of the Review and the resulting Sentence shall be
retained by
the Site Safety Advisor.
3. Work in Progress at Supplier Sites
- Work in progress at supplier sites is subject to existing design
review
processes, to final acceptance tests as described elsewhere in this
chapter,
and to the ongoing awareness and duties of the supplier under safety
legislation.
- As early as possible, following publication of this document, the
JAC
Project
Manager shall ensure that the ongoing work is reviewed for compliance
with
the requirements of this chapter.
- Where items are not in compliance the JAC Project Manager shall,
where
practicable, require that the appropriate design or construction work
be
performed prior to acceptance of the equipment by JAC.
APPENDICES
Appendix 1: Guidelines for the Purchase
of
Major Electrical or Electronic Equipment
General
This Appendix is included for information and where applicable, as
a set of guidelines to major equipment purchases.
All systems shall comply with NFPA 70 and ANSI C2. Electrical systems
shall
be designed so that all components operated within their capacities for
the initial and projected loads. Preferred standard voltages in
conformance
with ANSI C84.1 shall be used, with a single-voltage level
characteristic
in any classification, to minimize stocks of spare equipment and to
standardize
operating and maintenance practices and procedures.
Electrical materials and equipment shall be UL- or FM- tested, with
label attached, for the purpose intended, whenever such products are
available.
Where there are no UL- or FM- Listed products of the type, testing and
certification by another nationally recognized testing agency may be
acceptable.
The prior written approval of the JAC Chief Engineer is required in all
such cases. Installation methods shall be in accordance with the
manufacturer's
instructions. with NFPA 70, and with other applicable requirements.
On-site acceptance testing shall be required for each major
electrical
system. Tests shall be specified to demonstrate that each function and
important parameter is implemented. Specific criteria shall be included
to determine pass/fail acceptance. Copies of test results shall be
submitted
for approval.
Wiring Systems
- Raceways that penetrate fire-rated assemblies shall be
non-combustible.
The complete installation shall be suitably sealed to maintain the
established
fire ratings as defined in UL Building Materials Directory and UL 1479.
Raceways embedded in masonry for concrete shall be 3/4 inch minimum and
shall be adequate in number and capacity for the initial and projected
facility requirements.
Electrical Metallic Tubing shall not be installed where subjected to
physical
damage during installation or while in service. When EMT is used
outdoors
or in damp locations, compression type (rain tight) fittings must be
used.
Conductors
- Conductors for interior electrical systems shall be copper,
except that
aluminum conductors size No. 4 AWG and larger may be used. Conductors
for
poser and lighting branch circuits shall be not smaller than No. 12.
Power
and lighting conductors shall be 600-volt, Type THHN,THWN. Termination
of aluminum conductors on copper or aluminum pads shall comply with
IEEE
141.
Voltage levels, grounded conductors, equipment grounding conductors,
and
ungrounded conductors shall be identified following NFPA 70.
Receptacles
- Receptacles shall comply with general grade and a GFCI protected
receptacle
shall be used in compliance with NFPA 70.
Lightning Protection
- Lightning protection systems shall comply with NFPA 78. Lightning
protection
systems shall be considered for buildings over 50 feet in height, and
for
building containing valuable equipment.
Motors
- Motors shall comply with NEMA MG-1, except that hermetic
refrigerant
motor
compressors shall comply with UL 984.
Motors shall not exceed their continuous horsepower rating, including
service
factor, when the driven equipment is operating at the greatest
horsepower
conditions it is likely to encounter. Starting and running
characteristics
shall be coordinated with the driven machine and motor control
equipment.
Motor enclosures shall be drip-proof for indoor dry locations and
totally
enclosed or totally enclosed fan-cooled for outdoor or other wet
locations.
Motors shall be designed for continuous service at 40 degrees C
ambient
temperature. Motors shall operated at full capacity, with a voltage
variation
of plus or minus 10 percent of the nameplate voltage. Motor
characteristics
shall be selected to avoid excessive acceleration time for motors
driving
large masses and starting under load.
Motor Control
- Control equipment shall comply with the NEMA ICS standards and UL
508
All motors shall be provided with fully coordinated control equipment
to
perform the functions required. Overcurrent devices shall be provided
in
each ungrounded conductor; overcurrent devices located in the motor or
controller shall be rated in accordance with the manufacturer's
instructions.
Control devices shall be of adequate voltage and current rating for
the duty to be performed. Pilot control circuits shall operate with one
side grounded, at no larger than 120 volts. Where control power
transformers
are required, they shall be located inside the associated motor starter
housing, shall be protected against faults and overload by properly
sized
overcurrent devices, and shall be of sufficient capacity to serve all
the
devices connected to them with out overload.
Lighting Systems
- Interior lighting systems shall comply with IES Lighting
handbook.
Lighting
power budget shall be determined in conformance with ASHRAE standard
90.
Exit and emergency lighting systems shall comply with NFPA 101 and NFPA
110.
Fire Alarm Systems
- Fire alarm and supervisory systems shall comply with NFPA 71,
NFPA
72A,B,C,D,E,F,G,H,
NFPA 1221 and ANSI C2 and appropriate for the location.
Appendix 2: Environmental Conditions
for
Equipment in use by the Joint Astronomy Centre
- The aim of this document is to summarize design environment
information
for the use of equipment design engineers at the JAC or supplier
organizations.
- Detailed information has been provided for the telescope sites on
Mauna
Kea, with lesser detail being provided for the Hilo Base facility.
- The ranges here are based partly upon codes and standards where
these
apply,
and partly upon operating experience on Mauna Kea over ~15 years. In
particular
survival ranges may be non-conservative on longer time spans dependent
upon the assumed probability of excursion.
- Reference to appropriate standards and site surveys may provide
better
detail on extreme limits or statistical range data.
- In general the "Operating" conditions apply with the telescope
configured
for observing, the "Survival" conditions with it closed up and shut
down.
Thus telescope based equipment may presume the protection of the
telescope
enclosure to some degree (e.g. against wind, snow, debris).
- The symbol "xx" denotes missing information. Where information is
provided
for only one of JCMT or UKIRT it may usually be used as a guideline for
the other site. Any parties with referenced data or educated opinions
are
welcome to contact the JAC Chief Engineer.
- The notes marked "r" below provide specific reference material,
those
marked
"d" provide some discussion based on JAC design experience and/or
relevant
references.
Table 1: JAC Environmental Conditions
| Parameter [units] |
Site |
Operating Envelope |
Notes |
Survival Envelope |
Notes |
| Temperature
[degC]
|
JCMT
UKIRT
Hilo
|
-10 to +20
-10 to +7
+17 to + 28
|
r4
r6
r15
|
-25 to +25
xx
+ 11 to + 35
|
r1
xx
r15
|
| Temperature Change
[degC /hr]
|
JCMT
UKIRT
Hilo
|
0.2-5.0
xx
xx
|
r6 |
5
xx
xx
|
r6 |
| Humidity
[% rh]
|
JCMT
UKIRT
Hilo
|
5 to 90 (condensing)
5 to 90 (condensing)
50 to 100
|
r1
r1
r15
|
0 to 100 (condensing)
0 to 100 (condensing)
30 to 100 (condensing)
|
r1
r1
guess
|
| Humidity Change
[%rh/hr]
|
JCMT
UKIRT
Hilo
|
100
xx
xx
|
guess
xx
xx
|
100%
xx
xx
|
guess
xx
xx
|
| Wind:
[kph - 3sec gust]
|
JCMT
UKIRT
Hilo
|
0-64
0-x
n/a
|
r5,d3
xx
n/a
|
200
266
170
|
r1, d1
r14
r10
|
| Altitude
[m]
|
JCMT
UKIRT
Hilo
|
4081
4194 +/- 6.0
xx
|
r1
r7
xx
|
n/a
n/a
n/a
|
n/a
n/a
n/a
|
| Position
[deg ' "]
|
JCMT
UKIRT
Hilo
|
(155 28'36"), (+19 49'24"')
per r16
(19 49 22.10741), (155 28 37.20394) per r18
(155 28'23.6" +/- 0.2"), (+19deg 49'32.2
"+/- 0.2")
per r7
(19 49' 20.75334"), (155 28'
13.17630")
per r18
(15deg) , (+19.5 deg)
|
r16,18
r7,r18
r1
|
n/a
n/a
n/a
|
n/a
n/a
n/a
|
| Air Pressure
[mBar]
|
JCMT
UKIRT
Hilo
|
600 to 700
605 (mean)
1000
|
r1
r8
guess
|
600 to 700
n/a
n/a
|
r1
n/a
n/a
|
| Air Pressure
Change
[mBar/hr]
|
JCMT
UKIRT
Hilo
|
50
xx
xx
|
r1
xx
xx
|
xx
xx
250
|
d7
xx
ascent
|
| Debris |
JCMT
UKIRT
Hilo
|
dust & occasional insects
xx
Insects, VOG, Laze
|
xx
xx
xx
|
windblown cinder & debris
xx
xx
|
d2
xx
xx
|
| Precipitation,
Rain
[see units]
|
JCMT
UKIRT
Hilo
|
No
observing
No observing
~2500 [mm/yr ]
|
d4,r8
d4,r8
r2
|
381mm/yr
(incl snow)
381mm/yr (incl
snow)
max 428 [mm/24hr]
max 3290 [mm/yr]
|
r8,r2
r8,r2
r16
r16
|
| Precipitation,
Snow & Ice
[mm]
|
JCMT
UKIRT
Hilo
|
No observing
No observing
n/a
|
r1,d4
d4
xx
|
141 kg/m2
146 (horiz)- 293 (vert) kg/m2
n/a
|
r2
xx
xx
|
| Vibration |
JCMT
UKIRT
Hilo
|
see earthquake notes
see earthquake notes
see earthquake notes
|
xx |
see earthquake notes
see earthquake notes
see earthquake notes
|
xx |
| Telescope
Acceleration
[see units]
|
JCMT
UKIRT
Hilo
|
0.1deg/s2
(observing)
xx
n/a
|
r2
xx
|
0.1°/s2
(slew)
xx
n/a
|
r2
xx
|
| Gravitational
Acceleration
[m/s2]
|
JCMT
UKIRT
Hilo
|
xx
xx
xx
|
xx |
0.4g lateral /
0.4g horizontal.
"
"
|
r17 |
| Radiation
[kW/m2]
(normal incidence)
|
JCMT
UKIRT
Hilo
|
0-1.3 (duration : 14hr
day)
xx
xx
|
r1 |
1.3 (14 hr day)
xx
xx
|
r1 |
Other Notes
Vibration
and Earthquake notes
References
Design Notes Misc
Design Notes
Vibration
and
Earthquake notes
- Earthquakes probably provide the worst case vibration loading on
most
equipment,
in addition to the basic overload or lateral "g" loading situation for
which equipment should be designed. A variety of loading information,
some
of it contradictory, has previously been available at the JAC due to
varying
dates of adoption. The current U.S.geological Survey rating for Hawai'i
was updated to UBC Zone 4 in 1997, per r17. This provides for a
0.4g
lateral / 0.4g horizontal.
- Spectral contents and duration data may also be available for
some of
these
reference sources.
- For observing regimes on telescope instruments the vibration
environment
is highly location specific and the JAC should be consulted closely in
designing for such conditions.
- For information older codes applied at JAC included:Definition
is
is available as noted below.
- UBC Zone III (r3)
- 0.3g lateral, 0.1g vertical (r1)
- 0.4g, any direction (r6,r9)
- UBC Zone IV earthquake (r6,r9)
- 0.3g any direction (r10)
References
- r1 Mauna Kea Specification MT02.
- Depression temperature minimum quoted in JCMT Carousel manual,
cross
referenced
to MT02.
- Earthquake: 0.3g max lateral, 0.1g vertical. Frequency 1-10Hz
simple
harmonic.
20 sec duration
- r2 Based on r1, page xx
- quoting 100 Tonne snow load on roof (at ~ 30 m diameter )
- r3 Based on r1, page xx
- quoting UBC Zone III. UBC details are , see xx.
- r4 Based on r1, page xx.
- Upper temperature will depend upon direct solar heating.
Ambient air
rarely
exceeds 16°C
- r5 Based on Current practice. See Chapter xx, section xx of this
manual
- 64 kph based upon current practice.
- Note that though r1 quotes a design limit of 80kph this is
rarely
attainable
due to gust resonance of festoon cables, roof and doors.
- r6 Gemini Environmental Design Requirements ICD-G0013 Rev B.
- Seismic base acceleration: 0.4g, 0,5-100Hz. Any axis.
- r7 Per UKIRT web page.
- For position the coordinate system is believed to be Geodetic,
Old
Hawaiian
Datum.
- This differs from the standard Geodetic, North American Datum
(1927)
updated
to1983, by a predicted amount 341m N, 291 m W (translation of
coordinate
grid from OH to NA'83).
- The altitude refers to the dome floor, interpolating from the
source
map
contours.
- The reference altitude is not stated: this is conventionally
the local
mean sea level.
- Contours were derived by (revised) photogrammetry in 1978.
- r8 CFHT Observers' Manual - Section 5 - SITE CHARACTERISTICS Web
based.
- 15mm/year figure is suspect as contradicted by MT02, which
contains a
'real'
map with the figure 15"/yr.
- Mauna Loa slope (at solar observatory) figures (see r16)
- for RAIN are for 21" max rainfall in year, 8" max rainfall in
1 day
- for SNOW are for 4.5" max snowfall in year, 3" max snow depth.
- r9 Seismic Risk of the Summit Area of Haleakela Volcano, Dr.
A.S.Furumoto,
Hawaii Institute of Geophysics
- Probability of Magnitude 7 earthquake by 2034: ~40%
- Recommended design load for Mauna Kea 0.4g lateral /0.4g
vertical
- r10 ANSI/ASCE 7-95 Minimum Design Loads for Buildings and other
structures
- r11 source: Anecdotal: Tribune Herald Volcano Update article (?)
- The Big Island of Hawaii was updated to UBC IV in 1990's
- r12 not used
- r13 UKIRT Dome Performance Requirements Specification UKIRT 4
(Issue
1),
22.May.75
- Section 2.1 (b) quotes: ice load 146 kg.sq.m horizontal
surfaces, 293
kg.sq.m
vertical surfaces.
- r14 Merz & Mclellan Calc Sheet , UKIRT Job No. 184-015. May.87
- 160mph quoted as measured at site. 104% factor applied for site
roughness
& height constraints.
- r15 NOAA Western Regional Climate Centre, online data. http://www.wrcc.sage.dri.edu/index.html
- r16 JCMT GPS clock readout, 02.Feb.98 six satellite lock,
non-differential.
- r17 US Geological Survey web page: Hawaai
Earthquake
hazards http://hvo.wr.usgs.gov/earthquakes/hazards/
- r18
: per IfA aerial survey map
Coordinates of Mauna Kea Telescopes : The following
coordinates
were determined from an aerial survey made on September 25, 1996.
| Telescope |
NAD 83 |
Old Hawaiian |
Altitude |
| Latitude (North) |
Longitude (West) |
North |
East |
(feet) |
| 0.6-m |
19 49 17.81149 |
155 28 15.46587 |
359995.495 |
509025.550 |
13734.67 |
| 2.2-m |
19 49 22.76784 |
155 28 09.96073 |
360495.640 |
509551.095 |
13824.00 |
| CFHT |
19 49 30.90648 |
155 28 07.95258 |
361316.785 |
509742.720 |
13793.00 |
| IRTF |
19 49 34.38594 |
155 28 19.19564 |
361667.615 |
508669.260 |
13674.76 |
| UKIRT |
19 49 20.75334 |
155 28 13.17630 |
360292.335 |
509244.110 |
13774.60 |
| JCMT |
19 49 22.10741 |
155 28 37.20394 |
360428.610 |
506950.115 |
| CSO |
19 49 20.77658 |
155 28 31.78945 |
360294.405 |
507467.055 |
| Keck 1 |
19 49 33.40757 |
155 28 28.98665 |
361568.775 |
507734.525 |
13646.92 |
| Keck 2 |
19 49 35.61788 |
155 28 27.24268 |
361791.795 |
507901.000 |
13646.92 |
| Subaru |
19 49 31.81425 |
155 28 33.66719 |
361407.970 |
507287.690 |
13658.14 |
| Gemini |
19 49 25.68521 |
155 28 08.56831 |
360790.000 |
509684.000 |
13823.62 |
Typical grid convergence for the
Old Hawaiian
coordinates is 0 00 30.
Typical scale factor for the Old Hawaiian
coordinates
is 0.99996675.
Last updated September 22, 1998 Richard
Wainscoat rjw@ifa.hawaii.edu
Design Notes
- d1 Note that a "3second gust" wind speed implies a peak wind
speed
found
by averaging data over a three second interval. It does not imply that
the high wind condition will only last for 3 seconds (!). ASCE-7-95 and
later standards are tending to quote 3 second gusts as the older
"fastest
mile" data (how long a packet of wind would take to travel one mile) is
no longer widely collated. Note also that the wind loadings may take
appropriate
account for the reduced air density, and hence reduced air mass.
- d2 For outside enclosures, care should be taken to ensure no
penetration
- particularly of windows and doors - by missile damage is likely to
occur
(or that the building is designed to survive loss of outer shell
integrity)
- d3 "Wind Loading on large astronomical telescopes" F.Forbes Kitt
Peak
Observatory
& G.Gabor Lawrence Berkeley Labs, Iniversity of California. Undated
(but post 1979). provides site wind spectra for UKIRT.
- d4 No observing should occur during precipitation or in
cloud/fog.
However,
both UKIRT and JCMT do experience some water ingress due to leakage or
delays in closing up due to hardware faults or slowness in closing
during
intermittent good-bad weather. JCMT has experienced pooling of water up
to 1" deep in certain basement areas. Condensation on, or leakage onto,
all exposed surfaces may occur from time to time.
- d5 In most snow or ice conditions, JCMT cannot be opened until
all ice
and snow is removed from the door and roof trackways. Attempts to open
before removing the ice generally leads to ripped brush seals, damaged
flashing and the potential for overload or derailing of roof and doors.
Additionally, any snow or ice left on non-moving surfaces (mainly on
the
roof) will lead to water ingress problems upon melting so must also be
removed.
- d6 UKIRT is vulnerable to icing of the main dome brush seals,
which may
take several days to thaw. Attempts to rotate before the ice thaws
generally
leads to ripped brush seals, damaged flashing and the potential for
overload
of the dome motors.
- d7 Based on a 2hr transit time from Hilo to Mauna Kea.
Misc. Design Notes
Consideration should be given to several effects of high altitude
when
designing all equipment. This includes:
- Atmospheric Composition effects
- ozone and ultraviolet may degrade certain polymers
- humidity is generally lower than at sea level, though may vary
on short
timescales. This may cause dimensional and strength changes in polymers
and adhesives
- cure times of adhesives, grouts, and cements are often reduced
by a
combination
of cold and reduced partial oxygen pressure.
- Low Air Pressure
- low vapor pressure may promote out-gassing of volatiles from
polymers,
greases and oils.
- reduced atmospheric pressure will affect pressure vessel
design, and
consideration
to potential change of pressure on ascent from sea level should be given
- Lower Air Density affects:
- reduced convective cooling due to reduced air density impacts
electrical
equipment's ratings for power dissipation, delivered power and life.
- air conditioning calculations are also impacted including,
convective
cooling
coefficients, fan power ratings, mass flow calculations, and cooling
power
of ambient air.
- Low temperature
- Equipment may remain 10-15degC cooler than a typical
as-manufactured
shop-floor
environment, and thus precision tolerances may need to be calculated to
allow for operation at lower temperature.
- Low temperature Ductile-Brittle transition may promote early
fracture
of
some materials, including some construction steels.
- reduced ductility of polymers may occur.
- Grease and oil viscosity will be reduced.
- Low humidity
- Electrostatic discharge hazards often exist in times of low
humidity.
- The dry cinder soil also hinders grounding and special
grounding
layouts
are in use at UKIRT and JCMT.
- Users
- Reduced oxygen levels, in conjunction with cold temperatures
and long,
unusual work hours will degrade the physical and mental abilities of
most
workers.
- Consideration should always be given to keeping mechanisms,
labels and
instructions simple, robust and easy to understand.
- Corrosion and Debris:
- The Mauna Kea does not generally promote corrosion, unless
equipment is
exposed to rain, standing water or condensation. Volcanic dust is
however
pervasive, and the dust may be highly abrasive. Neither JCMT nor UKIRT
are by any means 'clean room' environments, and conditions are more
typical
of a workshop than a laboratory.
- The Hilo environment is severely corrosive. The atmosphere is
warm and
moist, promoting rusting of most steels and mold growth on organic
materials.
Equipment may be exposed to salt spray in transit by sea. Volcanic
gases
and byproducts also pervade the atmosphere.
- Vibration:
- Some data exists at JAC, although tending to be very
location/instrument
specific. Contact the relevant JAC project manger for information if
required.
- Packing and Transportation environments
- The packing and transportation environment are often severe and
should
be considered in designing equipment. Precise details will depend on
shipping
environment and route. Outline information is available, for example in
the US Government MIL-STD-810E. The Gemini Environmental Requirements
ICD-G0013-B
document quotes:
- altitude 0 to 15,500m
- temperature (inside packing) -25°C to +71°C
- Temperature shock +/- 35°C
- Relative Humidity 0-100% (condensing)
- Wind speed 0-67 m/s
- gravity orientations: any axis
- Shock : 15g peak accel. any axis
Vibration: PSD 0.015g²/Hz 10 to 40 Hz and
0.00015g²/Hz
500 Hz
Last Update:
29.Sep.98
I.Pain. . Added confirmed earthquake zone and reference r17.
Appendix 3: The JAC
Engineering
Documentation System
The JAC Engineering documentation system for design information: is
as follows
- Drawing information for JCMT, UKIRT and JAC facilities is located
in
several
locations, each with an appropriate indexing system.
- Drawings in electronic format are located on central disk
space(s)
maintained
by the computer services group. Access to these files is restricted to
authorized persons, generally Design Engineers and JAC Project Managers.
- Drawings in hardcopy format are located in the Drawing Storage
Room at
JAC Hilo, or in other locations designated by the JAC Project Manager.
- Duplicate copies of hardcopy drawings are located for reference
purposes
at the UKIRT and JCMT sites.
- JCMT design information is located in the following areas:
- The JCMT Documentation index <http://www.jach.hawaii.edu/JCMT/pages/technical.html>
which
consists of several sections for
- Design documents from the original design of the JCMT
- Operational notes including technical descriptions and
procedures for
current
systems.
- Technical reports, such as feasibility studies and detailed
investigations
of existing phenomena.
- Software design and documentation notes.
- Other information storage is the responsibility of the Project
Manager.
Information is generally located at the Hilo base office of the
appropriate
Design Engineer(s). There is no overall index.
- UKIRT design information is located as designated by the UKIRT
Technical
Manager or the JAC Project Manager or Design Engineer as appropriate.
There
is no indexing system.
|