SCUBA-2
Infrastructure Project
JCMT
Shutdown 13-February to 17-August 2006
SCUBA-2 is
a new
instrument for the JCMT. It is an
extremely sensitive continuum array receiver which, due to its size,
cannot be
mounted easily on the telescope. Significant development of the
facility is
required to mount the instrument and its supporting equipment and
provide
servicing capabilities. The ‘SCUBA-2 Infrastructure Project’ was
developed to
provide these facilities. As part of the implementation of the project
a
telescope shutdown is required lasting six months.
Key
elements of the
project are:
The
Gallery
A
new gallery above the control room to site the support equipment for
SCUBA-2
including closed cycle cooling equipment, dilution refrigerator rack
and all
electronics other than the MCE array controllers. This gallery was
installed
prior to the shutdown and was ready for the installation of power
supplies and
coolers as part of the shutdown work.
Receiver
cabin modifications
The
receiver cabin will house a new Tertiary Mirror Unit and a set of relay
optics
to reduce the SCUBA-2 input beam to a size that can pass unvignetted
through
the left elevation bearing. To house these ‘cabin mirrors’ significant
redevelopment of the receiver cabin is required. This
includes relocation of existing equipment and modification
of the cabin bay next to the bearing.
Left
Hand Nasmyth Platform
The
left hand Nasmyth Platform that serviced the original SCUBA and allowed
access
to the receiver cabin has to be virtually eliminated to mount the
re-imaging
optics and the instrument itself. Key
work during the shutdown is removal of the existing platform and
rebuilding of
the receiver cabin access walkway. A
further part of this work is extending the mezzanine platform below to
allow
access to SCUBA-2 when installed.
SCUBA-2
mounting structure
SCUBA-2
requires a mounting frame to support the instrument and the re-imaging
‘Nasmyth
mirrors’. This structure is being
design and fabricated by contractors and will be installed by ETS staff
towards
the end of the shutdown.
Instrument
Handling and Servicing
The mass
of SCUBA-2
(~4 ton) is too heavy to be supported on the antenna and carousel floor
by
conventional means. As a result a significant part of the project is to
provide
dedicated handling equipment to install and remove the instrument. The
Carousel
floor requires strengthening and the installation of a rails system for
a
handling cart to run on. The ETS will
be installing this reinforcement during the shutdown with the handling
cart
arriving towards the end of the period.
Simon Craig, JAC Chief
Engineer
Photographs of work in
progress and completed include the refurbishment of the control and
computer rooms and can be viewed via the links in the
sidebar.